Change Orders. Build the project that was bid and awarded.

Slides:



Advertisements
Similar presentations
Change Order Missouri Local Programs How to Complete a Change Order & Get it Approved.
Advertisements

Field Orders on Construction Contracts Guidance Document CLC-8 May 13, 2013.
For State Agencies. Contract Elements Scope of Work Routing & Contract Mgmt Negotiations Contract Information & Forms.
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control.
Preparing a Post Bid Report Preparing a Post Bid Report NYS OGS Design & Construction Group Cost Control.
Chicken Soup for the Purchasers’ Soul The greatest power we have as purchasers is the power of competition.
INDOT Contractor Prequalification.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
Timely Payment Task Force Conaway Conference 2015 Chris Engle, Director of Public Agencies, Ohio Contractors Association Gary Angles, Administrator Office.
CONSTRUCTION ADMINISTRATION Preconstruction Operations Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
State Aid (SALT) prepares the Federal Agreements and the Amendments for  Force Account (FA)  Right of Way (ROW)  Preliminary Engineering (PE)  Construction.
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
Reimbursements for Local Programs Taylor Rossetti Local Government Coordinator Local Programs Team Sara Janes Local Programs Coordinator.
Material Management. Materials should be ordered early –Minimize risk of price inflation, lack of materials –Just in time delivery minimizes space required.
For West Virginia Department of Education DISCLAIMER This PowerPoint presentation serves only as a snapshot of purchasing regulations. Please visit the.
Adjustment & COCP Barbara Kwok Licensing Operations Specialist.
Performance Monitoring All All Contracts require basic monitoring once awarded. The Goal of contract monitoring is to ensure that the contract is satisfactorily.
WETLANDS and ODOT Environmental Services Oregon Department of Transportation.
Construction Engineering 380 Contract Changes. Types of changes –Cardinal change- drastic change, either single direction or accumulated change in scope.
1 Addendum Preparation Process ESC-OE Caltrans. 2 Introduction An addendum is a change in contract requirements for an advertised project for which bids.
State Auditor’s Office Change Order Pricing Practices Performance Audit of Eight Local Governments Puyallup City Council February 7, 2012 Chris Cortines,
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
First 5 LA Invoicing & Budget Modification Workshop OHCD Contractors FY
PTA Treasurer Training Pam Grigorian August 20, 2015.
Nabil dmaidi1 Bid Submission Documents A LATE BID IS NO BID.
COMPLIANCE WITH GRANT IMPLEMENTATION PROCEDURES TxDot Grant Fund Project.
MOASBO Spring Conference Bill Sloan – Rockwood School District Director of Purchasing and Transportation.
Professional Services Contracts in conjunction with Organizational Excellence Made Easy.
Procedural Requirements For Force Account Work on Federal and State Projects 2015 ACCA Conference Orange Beach, Alabama.
Remarks will print on the completed form Generate Quantity Book Entry Generate Pay Quantity.
CONSTRUCTION ADMINISTRATION Changes and Extra Work in Construction Management Dr. Alaattin Kanoğlu Spring, 2013 Professonal Practice Management I.B.U.
Completing the State Aid Payment Request (SAPR). Tips Each spring check on the State Aid Finance web page for the current version of the State Aid Pay.
Total Item Price: $ Dollars. Website: Price: $60.00.
Kenneth D. Fenton P.S. Clark County Engineer’s Office.
YUSUF OZ FATIH BOLUKBAS HUSEYIN ANIL KARABULUT. A contract is a legally binding agreement between two or more parties.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
King Fahd University of Petroleum & Minerals
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
CAREER TECHNICAL EDUCATION FACILITIES PROGRAM Cycle 2 Conversions.
Trivia Certification Program Trivia Mark Foster ODOT Region 1 Liaison and Federal Aid Specialist March 12, 2010.
CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.
American Recovery and Reinvestment Act of 2009 Energy Efficiency and Conservation Block Grant Program Small City and County Grant Kick-Off Meeting California.
Office of Procurement Services.  Vendor Application Website: 
Measurement and Payment
LPA Program Federal-aid Issues for Local Agencies Mike Morrow – December 10, 2010.
OTC Pres: Bid & Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office.
OVERHEAD COSTS IN BUILDING CONSTRUCTION IN SAUDI ARABIA Author: Mohammad Al-Shahri (1997) Presented By Fawaz Al-Ghamdi January 1, 2005.
CVE 4070 Construction Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
Consolidated Plan Programs Universal Application Process Budget & Financial Analysis Mandatory Workshop March 24, :00 p.m. 1 Laura Stagner Director.
KYTC Change Order (Contract Modifications).
CHANGE ORDER Minor annoyances for Bob Once you start change order get reviewed and processed!
Contract Basics For Utah State Agencies Prepared by:
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Discussion of the Differences Public Works Law and Bid Law
Personal Services/ Memorandum of Agreements
CONTRACT ADMINISTRATION
Contract Basics For State Agencies.
Content of Tender Dossier Instructions to Tenderers
State Aid Construction
Completing the State Aid Payment Request
Force Accounts.
Work Orders I will be reviewing Work Orders and addressing some problematic issues.
Construction Contracts
State Aid Construction
Directed Change Constructive Change
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

Change Orders

Build the project that was bid and awarded

Change Orders Build the project that was bid and awarded

Change Orders Build the project that was bid and awarded The ONLY permissible change orders are for changes required to complete the project as originally scoped

Change Orders Build the project that was bid and awarded The ONLY permissible change orders are for changes required to complete the project as originally scoped

Change Orders Build the project that was bid and awarded The ONLY permissible change orders are for changes required to complete the project as originally scoped LPAs cannot use local funds for work beyond the original scope

Change Orders Build the project that was bid and awarded The ONLY permissible change orders are for changes required to complete the project as originally scoped LPAs cannot use local funds for work beyond the original scope

Change Orders Amend the contract – Adding or deleting work (quantity adjustments) – Additional costs for differing site conditions – Changes in the scope of work that affects: Sequence Method of construction Efficiency of work – Changes for the convenience of the owner – Changes needed due to actions of others

Elements of a Change Order Elements of a change order: Face (Identification): – PROJECT - Quantity – C/R/S- Ref # – Fed #- Part Code – Fed Acceptance type- Item Code – CHANGE ORDER- Item Description – CO number - COST INFO – WORK INFO - Unit Price/Lump Sum – Units of measure - Total +/- and Total

Elements of a Change Order Body of Change Order – Reference Number, Extra Work Number, Part Code – Reason Code – Explanation of necessity Problem/solution Approach to change order pricing – Schedule impact Signatures – Agency – Contractor

Elements of a Change Order Attachments – Approval by ODOT Construction Monitor (EVERY change order) – Authorization by internal controlling board (City Council, County Commissioners, etc.) – FHWA approval (on Federal Oversight projects) – Supporting documentation (letters to/from Contractor, ODOT, internal engineers) explaining change - Cost Analysis

Change Order Pricing Agreed unit price – Use prices already in the contract – Compare prices for similar work statewide Similar quantities Similar area of state Available on website Production rate calculations – Agreed lump sum – Force Account

Change Order Pricing Force Account (C&MS ) (ODOT’s least favored, Contractor’s favorite) Work Force (name, class, hrs. reg., hrs. OT) Equipment (“Blue Book”, type, model, age, capacity, hrs. worked, hrs. idle) Materials (invoices: description, qty., price) 3 rd Party Billing (invoices) Allowable markups (see C&MS ) Inefficiencies

Change Order Pricing Changes to the plans involving extra or changed work could affect the schedule – delays turn into dollars. Project Schedule important tool. DOCUMENT, DOCUMENT, DOCUMENT Someone who knows nothing about the project should be able to come back five years later and with only the change order and attachments understand why and how a change order was processed.