Alternativenergy Flat Ridge Wind Facility Ted Hofbauer – Asset Manager.

Slides:



Advertisements
Similar presentations
Infrastrukturë Backbone ALBANIAN NATIONAL FIBER OPTIC NETWORK.
Advertisements

The three most important considerations for development of wind farms are: LAND with good to excellent wind resource CONTRACT to sell electricity produced.
RES Americas Kansas Wind and Renewable Energy Conference 2008.
Offshore Wind 2004 From Vindeby to Nysted A Manufacturer’s Experience Henrik Stiesdal Bonus Energy A/S.
Alberta’s Future Electricity Needs: What’s the Real Story? Economic Developers of Alberta Annual Professional Conference April 10, 2014 John Esaiw, Director.
Duke Energy Carolinas Dan River Combined Cycle Project 8/17/10 For Vogt Power, my best estimate is 214 shipments (rail, truck, LTL, and small parcel- UPS.
SkyPower Corp. PRESENTATION.
EverPower Eastern Projects Buckeye Wind Project Champaign & Logan Counties, Ohio 100 MW Highland Wind Project Krayn, Pennsylvania 115 MW The Allegany.
Meeting with Rep. _______________ Solar Industry Representatives May 5, 2010.
American Public Power Association The Challenge of Building a Coal Plant in Today’s Environment Raj Rao President, Indiana Municipal Power Agency Chairman,
Why We Made the Decisions We Made and Where We Are in Building New Generation February 17, 2005 Prepared by Nilaksh Kothari, P.E. General Manager Manitowoc.
Community Energy Opportunities Jon Bell Business Development Manager Mosscliff Environmental Ltd.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
2015/06/091 Overview of Maintenance & Infrastructure Delivery of Eskom Overview of Maintenance & Infrastructure Delivery of Eskom Eng Logan Pillay Eskom.
Copyright © 2004 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Chapter Five Income Measurement and Profitability Analysis.
1 Renewable Energy in the Northwest: Wind Energy Presented By Stephen C. Hall STOEL RIVES LLP Journal of Environmental Law and Litigation Symposium University.
Greta’s Grand Valley Wind Farm Contributing to Ontario’s Energy Future March, 2012 Greta Energy Inc.
Real Implications of Alternative Energy Sources for Communities WCCMA 2008 Summer Conference Roger Garratt Director, Resource Acquisition & Emerging Technologies.
Negotiating Wind Park Easements and Analyzing Comparable Sales presented by Justin Bierschwale Bierschwale Appraisals PO Box College Street Junction,
Kansas Renewable Energy KDHE Geology Seminar September 05, 2013 TAKING RENEWABLE ENERGY TO HEART. Taking renewable energy to heart.
Desert Sky Wind Farm January 2004 Welcome Desert Sky Wind Farm Pecos County, Texas.
BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation April 10th, 2013.
Powering Wolverine’s Renewable Future Presented to Great Lakes Regional Wind Institute Detroit, Michigan by John P. Miceli, Energy Market Analyst March.
CONFIDENTIAL AND PROPRIETARY Invenergy’s Views on Cogeneration Opportunities Presented to: April 30, 2015.
Fossil Gulch Wind Park Presented By Jeff Duff Vice President, Airstreams LLC Welcome.
PJM© PJM Confidential PJM Generation Interconnection Overview Virginia Offshore Wind Conference Virginia Beach June 22, 2011 Paul McGlynn General.
Wyoming Infrastructure Authority Developing Electric Infrastructure for the Future of the West Energy Gateway Update Presented by Darrell T. Gerrard Vice.
Boreal Renewable Energy Development Ferriter Scobbo & Rodophele PC Outback Engineering Richard C. Gross, Inc. March 12, 2009 Notus Clean Energy LLC Wind.
Renewable Energy Delivery, Scheduling, and Firming / Shaping
Twin Groves Wind Farm Bloomington Moraine McLean County, Illinois A Strong Beginning for Illinois Wind Robert Nagel
NASHVILLE ELECTRIC SERVICE | Association for Financial Professionals March 2012.
Town Of Douglas A Review of the Town’s Proposed Tax Incentive Financing (TIF) Agreement With American Pro Wind, LLC Presented To The Douglas Finance Committee.
Wind Energy 101 NextEra Energy Resources February 23, 2010 Adam Rickel.
Development and Construction of On- Shore Windfarms Andrew Aveyard Green Cat Renewables Jim Wilkinson CA Blackwells.
Presented to American Society of Civil Engineers Oregon Section Environmental & Water Resources Group Dana Siegfried David Evans and Associates, Inc.
Fire Island Wind CIRI, through its Fire Island Wind LLC subsidiary, is developing Southcentral Alaska’s first utility-scale wind project Aerial view of.
DALLAS BAR ASSOCIATION ENERGY LAW SECTION REVIEW OF OIL & GAS LAW XXIII SEPTEMBER 11-12, 2008 Lisa Chavarria Stahl, Bernal & Davies, LLP Austin, Texas.
Town of Orleans Wind Energy Project Berkshire Renewable Energy Summit June, 2005 Kevin Galligan
1 | Program Name or Ancillary Texteere.energy.gov Percheron Power, LLC’s Proof of Power Project on Potholes East Canal (POP ‐ PEC) 2011 Water Power project.
Mortenson Canada Corporation Proprietary and Confidential Construction and Contracting Clean Energy BC November 8, 2010.
Southwest Renewable Energy Transmission Conference May 21, 2010 This report contains transmission planning data that may be conceptual in nature and is.
Eugene Water & Electric Board. Dave Churchman Manager, Power Operations Eugene Water & Electric Board.
© 2004 The McGraw-Hill Companies, Inc. McGraw-Hill/Irwin Chapter 5 Income Measurement and Profitability Analysis.
1 Invenergy. Harnessing the Wind Transmission System Typical Wind Park Electrical Transmission System.
TRANSMISSION INFRASTRUCTURE IMPROVEMENTS — Current Projects — The Center for the New West “ The Sun Valley Energy Roundtables 2006” November 30 – December.
Presented to ABA RADER Committee/Columbia Law School's Environmental Law Society Symposium INTRODUCTION TO RENEWABLE ENERGY DEVELOPMENT Becky.
Session 22 (R) Utility Scale Solar Development Power Purchase Agreements (PPAs) April 04, 2016.
Welcome to Cedar Ridge Wind Farm Alliant Energy’s first fully owned-and-operated wind facility.
Berkshire Wind: Joint Action By Communities with Common Goals Presented by: David Tuohey, Director of Communications & External Affairs Massachusetts Municipal.
Florida Keys Electric Cooperative Association, Inc. Storm Hardening Florida Public Service Commission May 1, 2008 Scott Newberry, CEO John Stuart, COO.
Miller Driscoll Building Committee Construction Update Thursday April 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations.
__________________________ © Cactus Moon Education, LLC. CACTUS MOON EDUCATION, LLC ENERGY FROM THE WIND WIND TECHNOLOGIES.
USAID Afghanistan Engineering Support Program (ESP) Pre-Bid Meeting July 14, 2015.
Meeting Nantucket’s demand for electricity, today and tomorrow. Upgrading Nantucket’s Electric Grid.
Brownsville Overview Management Presentation November 2000
Lincoln Energy Center Overview
Wheatland Overview Management Presentation October 2000
Akuo Energy USA NM EnergyPlex Conference
Enron Corp. Board of Directors Presentation
Gleason Overview Management Presentation October 2000
Community Wind Development
Brownsville Overview Management Presentation December 2000
Presentation to the Enron Corp. Finance Committee
A. Datum Corp. Bid package overview.
Barry Ingold Senior Vice President, Generation.
SunZia Project Description
COMMUNITY UPDATE OCTOBER 23, 2013
Lafayette New Terminal Program Update
Maryland Offshore Windfarm Project
Funder Preferred Risk Allocation
Presentation transcript:

alternativenergy Flat Ridge Wind Facility Ted Hofbauer – Asset Manager

2 Flat Ridge Wind Facility - Overview A 100 MW Wind Facility located ~24 miles southeast of Pratt, KS in Barber County consisting of 40 Clipper Liberty C-96 turbines, each rated at 2.5 MW Located on leases totalling more than 5,500 acres. Owners are Westar Energy, Inc and Flat Ridge Wind Energy, LLC (a wholly owned subsidiary of BP Alternative Energy) Flat Ridge Wind Energy has sold 50% of the Flat Ridge Wind Facility assets to Westar Energy, Inc. which will own and cause its half of the facility to be operated to serve its customers. BPAE was contracted by Westar to build and operate the wind facility Flat Ridge Wind Energy, LLC has entered into a long-term wholesale power sales agreement with Westar Energy, Inc. to sell the remaining 50 MW of Flat Ridge Wind Facility capacity and energy for a term of twenty years Interconnection to the grid via the Sunflower Electric Power Cooperative balancing authority area

3 Flat Ridge Wind Facility - Construction Construction commenced in April 2008 with road cutting and foundation excavation

4 Flat Ridge Wind Facility - Construction Turbine foundation and pedestal following concrete pouring

5 Flat Ridge Wind Facility – Turbine Erection Turbine erection is in progress Turbine base and lower tower section being installed Gearbox being installed into a Nacelle

6 Flat Ridge Wind Facility – Additional activities Collection system trenching and cable installed, transmission lines and substation installed, O&M building installed concurrent with critical activities

7 Flat Ridge Wind Facility – Key Stats To date, the Wind Facility has reached these milestones: Over 7 miles of transmission line installed ~18 miles of collection system cable installed Received over 520 truckloads of equipment and parts Over 117,000 total hours worked with 220 staff at the peak of construction Employed five cranes in the installation process Included over 16 companies in the Engineering, Procurement, Construction and Commissioning Average of 58,000 miles driven each month is support of the construction. Activities aligned with growing seasons as much as possible to minimize crop damage. The site has encountered many days of inclement weather this summer while experiencing only one OSHA recordable incident and no “Lost Time” days.

8 Flat Ridge Wind Facility – Project Completion The Flat Ridge Wind Facility is currently scheduled to achieve substantial completion in October 2008 Commissioning activities will then commence. Commercial Operations are scheduled for December 2008