Greta’s Grand Valley Wind Farm Contributing to Ontario’s Energy Future March, 2012 Greta Energy Inc.

Slides:



Advertisements
Similar presentations
The three most important considerations for development of wind farms are: LAND with good to excellent wind resource CONTRACT to sell electricity produced.
Advertisements

Overview of the South African Renewable Energy Independent Power Producer Programme (IPP Program) Bruce Linke Finance and Projects 30 April 2012.
Wind farm project “Pakline – Ljubusa – Kupres” Sarajevo, 15 March 2011.
Arklow - GEWE 3.6 MW Offshore Project Lessons Learned
Strictly Private & Confidential 1 Tunis, 21 October 2009 Nur Energie Solar Development in the Mediterranean Basin.
Integrated Assessment of Off-shore Wind A Research Partnership between: Grand Valley State University Michigan Alternative and Renewable Energy Center.
North Hoyle Offshore Wind Farm 17th April 2002 BONUS Energy A/S.
Making the Right Wind Power Investment University of Toronto Wind Workshop October 12th, 2005 Mike Crawley, President/CEO AIM PowerGen Corporation.
Community Energy Opportunities Jon Bell Business Development Manager Mosscliff Environmental Ltd.
NovEnergia II Technical Bureau - Sep08 THE OPPORTUNITIES OF HUNGARIAN WIND ENERGY Álvaro Rodrigues September 2008.
Understanding Ontario’s Electricity System
World Market Update 2002 March Page 1 - Market Status - Demand Side Supply Side - Market Forecast - Forecast until 2007 Predictions
Renewable Energy in Oman Public Authority for Electricity and Water Khalil Alzidi Senior Renewable Energy Engineer.
Encouraging Green Power: Cooperation between the Private Sector and Government Avi Brenmiller, May
BUSINESS and POLICY BB1: Leading EU markets: achieving the vision Wind Energy in Italy: policy framework, incentives, industry and market development Luciano.
The Status Of The Electric Grid In ERCOT The Electric Reliability Council Of Texas Sam R. Jones, P.E. ERCOT – Retired As a retiree of ERCOT this presentation.
Grand Valley Phase III Developing Ontario’s Clean Energy Future April 2012 Greta Energy Inc Confidential.
Wind energy in NZ 20% wind by 2030 Eric Pyle, Chief Executive, NZ Wind Energy Association.
Nova-Eco Ukraine Alexander Fediaev United Nations Climate Change Conference - Nairobi, 14 November 2006 Owner of a 300 MW wind power project developed.
Scandia Wind Southwest LLC Development of large scale windpower Presentation for landowners Bovina May 8th 2009.
Lily Lake Solar Farm “Ontario’s First 10 MW Municipally Owned Solar Farm”
Biogas Workshop 10 th March 2009 ANF Energy Solutions Inc Power Purchase & Connection Power Purchase and Grid Connection Procedures Aidan Foss ANF Energy.
Presentation by Mr Sarvesh Kumar GLOBAL OPPURTUNITIES 1.
Small Farm Profitability: Is Wind Energy the Answer? 1
20% by 2030 The future of wind energy in New Zealand Eric Pyle, Chief Executive.
Real Implications of Alternative Energy Sources for Communities WCCMA 2008 Summer Conference Roger Garratt Director, Resource Acquisition & Emerging Technologies.
© Offshore Wind A big opportunity? GA-EMA Conferences 22 October 2014.
PJM© PJM Confidential PJM Generation Interconnection Overview Virginia Offshore Wind Conference Virginia Beach June 22, 2011 Paul McGlynn General.
Boreal Renewable Energy Development Ferriter Scobbo & Rodophele PC Outback Engineering Richard C. Gross, Inc. March 12, 2009 Notus Clean Energy LLC Wind.
Presentation to San Diego Sierra Club Richard Caputo 12 Nov 07 Renewable Energy Parks.
Forest Engineering Group Autumn Symposium Sept 2009 Presentation by Fergus Tickell Managing Director Northern Energy Developments Ltd.
Quantum Leap in Wind Role of Institutions and Regional Cooperation Chunhua Li DGM Goldwind International June 2011, Manila.
Avista’s Flexibility Overview James Gall Senior Power Supply Analyst Contact:
A Status Report on Wind Energy Opportunities in Canada Robert Hornung, CanWEA EWEA Conference March 2, Athens.
Creating A Greener Energy Future For the Commonwealth Procurement of Renewable Energy on Landfills January 19, 2010 Courtney Feeley Karp, Esq.
Development of renewable energy A chance and a challenge for Poland.
Frankfurt (Germany), 6-9 June 2011 W. Niederhuemer – Austria – RIF Session 4 – Paper PROBABILISTIC PLANNING FOR A HIGHER INTEGRATION OF WIND TURBINES.
1 Renewable Energy at Closed Landfills June 17, 2009 Jim Christo Massachusetts Renewable Energy Trust.
Supply Opportunities in Canada’s Wind Energy Market Stephen Rach CanWEA Toronto, Ontario October 6, 2010.
1 Power – The Wind Way. 2 Windy Years India Currently holds a cumulative capacity of over 21000MW in India. Wind power growth in India has seen various.
City of Fort Collins Wind Power Program March 24, 2004 John Phelan, PE Energy Services Engineer.
Liberalization of Electricity Market in Taiwan Su, Jin-sheng Energy Commission Ministry of Economic Affairs August 8, 2001.
Beyond Mandates, Does Green Pave the Way? Marlene Santos Vice President, Customer Service Florida Power & Light Company October 17, 2009.
Privatization and Liberalization of the Electric Power Industry in Taiwan Energy Commission Ministry of Economic Affairs October 5, 2001.
Feed In Tariffs A Policy for Rapidly Expanding Renewable Energy Deployment.
Wind farm Kalin / Bulgaria. Wind farm Kalin / Bulgaria – 99 MW ♦ 55 x Vestas V100 with 1,8 MW rated power ♦ 95 m hub height ♦ average wind speed 5,9 m/s.
Renewables Integration Development Project North West of the Island of Ireland Louis Fisher, EirGrid.
Mortenson Canada Corporation Proprietary and Confidential Construction and Contracting Clean Energy BC November 8, 2010.
Renewables and System Services Ann Scully.
Divider custom What’s this layout for? Use this if you with to change the colour of the lines Sustainable Power – Unpacking the Buzz Word The world’s leading.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
THE 2005 CERT ENERGY ROUNDTABLE Ontario’s Electricity Sector: The Hybrid Model Takes Shape By: Ron Clark May 31, 2005.
1 Experience from Finland Christian Llull, Ho Chi Minh City, 23rd November 2015 ? Cooperation & Partnership in Wind Project Development.
Bob Cupit Manager, Energy Facility Permitting Minnesota Public Utilities Commission.
In 2014, the average levelized price of signed wind power purchase agreements was about 2.35 cents per kilowatt-hour. This price is cost competitive with.
1 SYMPOSIUM: U G A N D A A F T E R I D I A M I N A N D M I L T O N O B O T E Hamburg, Germany 29 th September 2008 INVESTMENT OPPORTUNITIES IN POWER GENERATION.
© «Samruk-Green Energy» LLP BRIEF COMPANY OVERVIEW March «Samruk-Green Energy» LLP Bagdat Oral Project Manager.
North Coast Wind Farm Tolano Environmental Consulting.
Wind Prospect Experience and Practicalities of Wind Energy International Cooperation Forum for Energy Service Companies (ESCO’s) - Opportunities in China.
Challenges for Wind Farm Development in Bulgaria: The Environmental Aspect Case study: Saint Nikola Wind Farm, Kavarna April 2009.
Georgy TAVADZE Chairman Georgian National Energy Regulatory Commission (GNERC) Budapest, Hungary April 14, th Annual Meeting of the Energy Regulators.
Wind Development in an Evolving Power Market
“Caucasus Power Transmission Network’’ (Armenia-Georgia overhead transmission line/substations) Loan Project.
Presentation to the Enron Corp. Finance Committee
March 2, 2014 One sector, one target, one message The pathway towards 100 EUR / MWh in 2023.
© 2016 Global Market Insights, Inc. USA. All Rights Reserved Hybrid Solar Wind Energy Storage Market to grow at 9%+ CAGR from :
Wind Industry Market and Policy Overview
Renewable Energy Markets
U.S./European Cost Comparison Study Preliminary Results
Your partner with over 70 years of experience
Presentation transcript:

Greta’s Grand Valley Wind Farm Contributing to Ontario’s Energy Future March, 2012 Greta Energy Inc

Ontario’s Electricity Market at a Glance Green Energy and Green Economy Act (GEA) includes streamlined approval process for wind projects Guaranteed Feed-in Tarrif (FIT) of $135/MWh Clear legislation and responsive government eliminate bureaucratic roadblocks vis-à-vis other markets SOURCE: IESO World-class legislative environment for wind power Anticipated growth in wind energy supply Large & integrated electric system While wind accounted for only 1.9% of total electric output in 2010, the Independent Electricity System Operator anticipates the GEA will accelerate the expansion of wind energy by thousands of megawatts Over 500 MW of additional installed capacity under development Ontario is Canada’s largest producer and consumer of electricity with over 38 GW of installed capacity Large peak consumer demand and integration with hydro supply favor additional wind production

Proposed Wind Farm 19.8 MW Installed capacity in Phase I and II (Up to 40 MW in Phase III) 10 km north of the town of Grand Valley and 21 km northwest of the town of Orangeville Relatively simple terrain with gentle slopes and elevation ranging between m 19.8 MW Installed capacity in Phase I and II (Up to 40 MW in Phase III) 10 km north of the town of Grand Valley and 21 km northwest of the town of Orangeville Relatively simple terrain with gentle slopes and elevation ranging between m

Grand Valley Project Overview Phase 1Phase 3 Capacity Turbine Selection 19.8 MWUp to 40 MW Siemens SWT MW Next steps New land acquisition (signing option to lease agreements) Anticipated Commercial Operation Date: April 5, 2012

Project Status Overview Project RequirementStatus Wind assessment ✓ Completed by Garrad Hassan Noise assessment ✓ Complete and approved by government Turbine layout ✓ Complete and approved by government Turbine selection ✓ Siemens SWT Private Land Leases ✓ Acquired Environmental Impact Assessment ✓ Completed by Environment Business Consultants Inc. Architectural and engineering drawings ✓ Complete Building permit ✓ Acquired Insurance ✓ Acquired 50 MW Grid Connection ✓ Complete Financing procured ✓ Acquired and guaranteed Engineering and constructionExpected 2012 completion Assessment Planning and Approvals Project completion

Project Status Details Option to Lease agreements are fully executed with nine landowners for Phase 1&2 Phase 3 is in the land acquisition stage. Phases 1&2 of the project have obtained Connection Impact Assessment (CIA) approvals for Vestas V90 turbines CIA revisions currently being obtained for Siemens SWT turbines Phase 1 has entered into a Connection Cost Agreement with Hydro One Networks Inc, the Local Distribution Company; Phase 2 will also shortly Two met towers in close proximity to proposed turbine locations collected wind data from All significant environmental approvals and milestones completed for Phase I and II It is anticipated that a significant amount of the environmental studies completed for Phase 1&2 can be applied towards obtaining a Renewable Energy Approval (REA) for Phase 3 Garrad Hassan was contracted to create the optimal turbine layout, taking into account noise setbacks and other constraints Land Control Wind Measurement Grid Connection Environmental Approvals Turbine Layout