P.N. Burrows BDS/MDI, LCWS08 Chicago, 17/11/081 Beam-based feedback for LC ILC luminosity goal 10**34 / cm**2 / s 3000 or 6000 bunches, spacing 150 - 300ns.

Slides:



Advertisements
Similar presentations
P.N. Burrows ATF2 Project Meeting, KEK, 14/12/091 Feedback On Nanosecond Timescales Philip Burrows Glenn Christian Hamid Dabiri Khah Javier Resta Lopez.
Advertisements

Testing and Development of Feed-Forward System for ATF2 A. Kalinin Accelerator Science and Technology Centre, Daresbury Laboratory, UK Fifth ATF2 Project.
Philip Burrows CLIC MDI Meeting 6/11/091 Design issues for IP intra-train feedback Philip Burrows John Adams Institute Oxford University.
Philip Burrows ALCPG Workshop, SLAC: BDIR Working Group 08/01/04 Feedback on Nanosecond Timescales (FONT): FONT2 December 2003 run results Philip Burrows.
Philip Burrows LCABD Meeting, RHUL 12/04/07 WP7: Beam feedback and control systems Philip Burrows John Adams Institute Oxford University.
FONT4 Status Report Glenn Christian John Adams Institute, Oxford for FONT collaboration.
P.N. Burrows ATF2 Project Meeting, KEK, 18/12/061 Philip Burrows John Adams Institute Oxford University LCABD ATF / ATF2 ESA Miscellaneous FONT.
P.N. Burrows GDE/MDI Vancouver 19/7/06 (T-488) Philip Burrows John Adams Institute Oxford University EM Background Tests of Feedback BPM.
Feed forward orbit corrections for the CLIC RTML R. Apsimon, A. Latina.
Progress towards nanometre-level beam stabilisation at ATF2 N. Blaskovic, D. R. Bett, P. N. Burrows, G. B. Christian, C. Perry John Adams Institute, University.
Philip Burrows Third Mini Workshop on Nano Project, KEK 30/5/05 Philip Burrows Queen Mary, University of London Overview of Intra-train Beam Feedback Program.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett*, Talitha Bromwich, Glenn Christian, Michael Davis, Colin Perry.
FONT IP intra-train feedback prototype status
Philip Burrows LCUK Meeting, Oxford 29/01/04 Feedback on Nanosecond Timescales (FONT): FONT2 run results Dec 03/Jan 04 Philip Burrows Queen Mary, University.
Accelerator R&D on LC - Activities of ATF & STF - 1. Introduction 2. ATF 3. STF 4. Summary Seiya Yamaguchi, KEK The US/Japan Collaboration in High Energy.
Feedback on Nanosecond Timescales (FONT) - Review of Feedback Prototype Tests at ATF(KEK) Glenn Christian John Adams Institute, Oxford for FONT collaboration.
Font 4 Review Digital Feedback System BPM Analogue Processor Digital Processor Feather Kicker Power Amplifier Pick up StriplinesKicker StriplinesBeam.
Development of beam-based intra-train feedback systems Glenn B. Christian Post-doctoral Research Assistant on Feedback on Nanosecond Timescales (FONT)
1 FONT Results 2010 Philip Burrows Robert Apsimon, Doug Bett, Glenn Christian Michael Davis, Colin Perry, Javier Resta Lopez John Adams Institute Oxford.
Philip Burrows ECFA LC Workshop, Warsaw, 10 June Philip Burrows John Adams Institute Oxford University G. Christian, C. Clarke, B. Constance, H.
Feedback On Nano-second Timescales: An IP Feedback System for the Future Linear Collider Requirement for a fast IP beam-based feedback system Simulation.
Feedback for CESR TA Michael Billing May 17, 2007.
Feed forward orbit corrections for the CLIC RTML R. Apsimon, A. Latina.
Feedback On Nanosecond Timescales (FONT): Robert Apsimon, Philip Burrows, Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Davide Gamba,
2 nd EuroTeV Scientific Workshop, Orsay 16 th May 2006 WP2 : Beam Delivery System D. Angal-Kalinin ASTeC, CCLRC Daresbury Laboratory.
3/25/2006 KEK LCPAC Marc Ross - SLAC 1 Results of Beam Instrumentation Studies at ATF 1.Nanometer resolution Beam Position Monitors 2.High resolution readout.
P.N. Burrows ECFA/GDE Meeting, BDIR session, Valencia, 9/11/06 Philip Burrows John Adams Institute Oxford University FONT4 tests at KEK/ATF EM background.
Magnet Motion Produces Luminosity Loss. NLC Feedback Operation Kicker Gain Bunch Charge Measure deflected bunches with BPM and kick other beam to eliminate.
Development of a Low-latency, High-precision, Intra-train Beam Feedback System Based on Cavity Beam Position Monitors N. Blaskovic Kraljevic, D. R. Bett,
Preliminary Design of FONT4 Digital ILC Feedback System Hamid Dabiri khah Queen Mary, University of London 30/05/2005.
Philip Burrows ATF 15/03/05 FONT Group Progress + Plans 2005 Philip Burrows, Christine Clarke, Glenn Christian, Hamid Dabiri Khah, Stephen Molloy, Glen.
1 FONT R&D status Philip Burrows Douglas Bett, Neven Blaskovic, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John Adams Institute Oxford University.
Philip Burrows ALCPG11, Eugene 21/03/111 Performance of FONT at ATF2 Philip Burrows John Adams Institute Oxford University.
1 FONT IP Feedback System Implications of increase of L* Philip Burrows John Adams Institute Oxford University.
Philip Burrows ATF2 project meeting 14/1/111 Plans for ATF2 IP Feedback Philip Burrows, Colin Perry John Adams Institute Oxford University.
Design and Simulation of Intra-train Feedback Systems at ATF2: Current Status and Future Plans Javier Resta Lopez (JAI, Oxford University) for the FONT.
Philip Burrows 2 nd Nano Workshop, KEK 11/12/04 Plans for FONT3 and Future Feedback Experiments Philip Burrows Queen Mary, University of London ILC system.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett*, Talitha Bromwich, Glenn Christian, Michael Davis, Colin Perry.
Feedback On Nanosecond Timescales (FONT) Philip Burrows Neven Blaskovic, Douglas Bett*, Talitha Bromwich, Glenn Christian, Michael Davis**, Colin Perry.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John.
UK LC accelerator programme Philip Burrows John Adams Institute Oxford University 1.
Design of ATF2 feedback/feed-forward systems Javier Resta Lopez (JAI, Oxford University) for the FONT project group LC-ABD meeting Birmingham, 17-18th.
ATF2: Summary of Scheduling Strategy Session Grahame Blair Feedback and Feedforward systems Fast Kicker for ILC bunch train structure Laser-wire Shintake.
Philip Burrows ATF2 project meeting 1/07/101 Plans for ATF2 IP Feedback Philip Burrows, Colin Perry John Adams Institute Oxford University.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John.
CLIC-UK Programme Status Philip Burrows John Adams Institute Oxford University 1.
1 IP FB tests at ATF2 Philip Burrows Douglas Bett, Neven Blaskovic, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John Adams Institute Oxford.
G.R.White: F.O.N. T. From Ground Motion studies by A.Seryi et al. (SLAC) ‘Fast’ motion (> few Hz) dominated by cultural noise Concern for structures.
IoP HEPP/APP annual meeting 2010 Feedback on Nanosecond Timescales: maintaining luminosity at future linear colliders Ben Constance John Adams Institute,
Luminosity Issues for LC BDS Glen White, SLAC LCWS2013, Tokyo November 12, 2013.
Overview of progress at FONT Neven Blaskovic TMD technologies CASE student John Adams Institute Oxford University.
FONT4 Status Report Glenn Christian John Adams Institute, Oxford for FONT collaboration.
1 FONT IP FB Philip Burrows Robert Apsimon, Doug Bett, Neven Blaskovic, Glenn Christian, Michael Davis, Colin Perry John Adams Institute Oxford University.
Feedback On Nanosecond Timescales (FONT) Philip Burrows Neven Blaskovic, Talitha Bromwich, Glenn Christian, Colin Perry, Rebecca Ramjiawan John Adams Institute,
Philip Burrows X-band 2010 Daresbury 2/12/101 Advanced beam feedback systems Philip Burrows John Adams Institute Oxford University.
Fast Beam Collision Feedbacks for luminosity optimisation at next-generation lepton colliders Philip Burrows John Adams Institute Oxford University.
Phase Feed-Forward Piotr Skowroński (CERN)
Dither Luminosity feedback versus Fast IP feedback
BDIR/MDI Summary ECFA Final Plenary
In collaboration with P. N. Burrows, A. Latina and D. Schulte
CLIC-UK Oxford Activities
BDIR/MDI Summary ECFA Final Plenary
SD0/QD0 Cryomodule Jitter Tolerance
CLIC Drive Beam Stabilisation
Progress towards nanometre beam stabilisation at ATF2
Intra-Pulse Beam-Beam Scans at the NLC IP
Progress towards nanometre level beam stabilisation
E-JADE and the ATF beam stability goal
Feed forward orbit corrections for the CLIC RTML
Hit density at scoring planes at r=10, 30, and 50 cm.
Presentation transcript:

P.N. Burrows BDS/MDI, LCWS08 Chicago, 17/11/081 Beam-based feedback for LC ILC luminosity goal 10**34 / cm**2 / s 3000 or 6000 bunches, spacing ns  DIGITAL FB approach CLIC luminosity goal 10**35 / cm**2 / s c. 100 bunches, spacing c. < 1ns  ANALOGUE FB approach

P.N. Burrows BDS/MDI, LCWS08 Chicago, 17/11/082 e- e+ IP beam-based feedback for LC

P.N. Burrows BDS/MDI, LCWS08 Chicago, 17/11/083 KickerBPM 1 Digital feedback Analogue BPM processor Drive amplifier BPM 2 BPM 3 e- FONT4 ILC prototype at KEK/ATF 3 bunches, ns spacing 1.3 GeV

P.N. Burrows BDS/MDI, LCWS08 Chicago, 17/11/084 KickerBPM 1 Digital feedback Analogue BPM processor Drive amplifier BPM 2 BPM 3 e- FONT4 ILC prototype at KEK/ATF

P.N. Burrows BDS/MDI, LCWS08 Chicago, 17/11/085 Example (1) of May 2008 Results low gain medium gain high gain

P.N. Burrows BDS/MDI, LCWS08 Chicago, 17/11/086 Example (3) of May 2008 Results

Slack = 22 ns Latency = slack = 132 ns + 8ns (1/Q) Bunch 1 Kicker pulse Bunch 2 154ns LatencySlack Latency measurement