17. January 2008 DB Export section DRB & The Øresund Link Peter Lundhus Man. Dir. Femern Bælt A/S.

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

ISTISNA AS MODE OF FINANCE
Legislative framework for the further implementation of EGNOS and Galileo Etelka BARSI-PATAKY MEP, EPP-ED Group.
1 Unit C3 Finance, legal Affairs and Partner support CALL FOR PROPOSALS APPLICATION PROCEDURE SPECIFIC ADMINISTRATIVE AND FINANCIAL ISSUES Version
Select a frontpage and insert content – remember to delete all other frontpage slides Subtitle, max 1 line Titel, max 3 lines Insert Name of Author above.
Contracts – important issues
A framework for organising and financing infrastructure provision Jan-Eric Nilsson, VTI.
SPUTNIC – Strategies for Public Transport in Cities Strategies for Public Transport in Cities Funded by the EU PT Market.
Guide for setting up Framework Agreements
NETLIPSE Infrastructure Project Assessment Tool Stuart Baker, Deputy Director of National Rail Projects Department for Transport, UK Vilnius, May 18, 2010.
© OECD A joint initiative of the OECD and the European Union, principally financed by the EU Mag. Martin Oder, LL.M. OECD/SIGMA Concessions and Public.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
© OECD A joint initiative of the OECD and the European Union, principally financed by the EU CONCESSIONS IN TURKISH LAW İbrahim BAYLAN Legal Adviser Public.
© OECD A joint initiative of the OECD and the European Union, principally financed by the EU The Private Sector Perspective on PPP Projects/Concessions.
TRENTO RISE ICT for Quality of Life Francesca Cinardo Legal aspects of Joint Pre-Commercial Procurements: from modeling to implementation Geneva – February.
Phases of A BOT Project Prepared By :Afaf Bu-khawa Course title: Technology Implementation,MGT 620.
1 12 th Implementation Group Meeting 26 th March 2009 Establishing a SAO in the CS Region.
Determination of Construction Contract Duration for Public Projects in Saudi Arabia By: Ahmed Saleh Al-Sultan, June 1989 Presented by Sameh Elish January.
Delivery Methods  The Players from Handbook of Architectural Practice, Chapter 9.1 by Phillip Bernstein FAIA  Variables from Handbook of Architectural.
“Lessons Learnt” workshop on 18 th June, Sofia Project Implementation Support Service Agreement (PISSA) TA BG BSF S6 - Capacity building István.
Construction Industry Development Board development through partnership Construction Procurement documents 2c.
ACE, ECCE & EFCA SEMINAR 21 October 2004 New EU Public Procurement Directive: EUROPEAN HARMONISATION OF PROCUREMENT PRACTICES IN THE SECTOR OF THE ENGINEERING.
WORLD MEETING OF CUSTOMS LAW BRUSSELS , September “ Studies on Harmonization of Customs Law and Contributions of the Academy for updating and.
This Presentation is a Copyrighted Property of Waller S. Poage, AIA, CSI, MAI, CVS – All Rights are Reserved Session CDT 01 – Fundamentals Lesson CDT 1.3.
ABA Dispute Resolution Section Women in Dispute Resolution December 2014 Dispute Boards: An Introduction Deborah Bovarnick Mastin Law Office of Deborah.
Hungarian audit experiences related to projects implemented with the co- operation of the private sector Prof. Dr. Gusztáv Báger director general Better.
TO ACCOMPANY HORNGREN HARRISON BAMBER BEST FRASER WILLETT.
Michael Steinicke Free choice and PPP Status in Denmark SOI March 30th 2008 Professor Michael Steinicke University of Southern Denmark.
© Cengage Learning – Purchasing & Supply Chain Management 4 ed ( ) Practice 19. Public procurement and EC directives.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Financing and regulating highway construction in Scandinavia – experiences and perspectives Svein Bråthen Molde University College
Creating the global research village EU Procurement Nicola Anson, DANTE TF-MSP Meeting, 1 March 2011.
VALUE FOR MONEY 1 OGC buying.solutions Procurement of Projects Presented by Andy Hamer Pre Accession Advisor, Finance Ministry.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
January 31, …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.
Councillor Community Fund Isabell Procter Director of Resources Francis Fernandes Borough Secretary.
July 2013 What you need to know about procuring suppliers Deborah Ramshaw and Lois Shield.
© OECD A joint initiative of the OECD and the European Union, principally financed by the EU Ensuring Good Quality PPP Projects Martin Darcy United Kingdom.
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
The 4 th Railway Package: Impact for the keepers Clio Liégeois.
© OECD A joint initiative of the OECD and the European Union, principally financed by the EU Private sector interests in legal protection Tomaž Vesel First.
Cooperationand consortium building Luis Araque de Juan European Commission International Cooperation and Development DEVCO/EuropeAid Unit R.3 Legal Affairs.
Project Management Birutė Markevičiūtė Joint Technical Secretariat Lead Partner Seminar 13 October 2008, Riga.
EMTA General Meeting Prague May 2012 Round table on PSO Regulation 1370/2007 “Two years after enforcement, where are we? How efficient is the regulation?
Technical Assistance Office TCP Projects 2005 Contractual and Financial Management Administrative and Financial Handbook Prepared by IA, 14/12/2001 SOCRATES.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
Rail Schemes and the PPP Model November Rail Schemes and the PPP Model  Rail Schemes  PPP model  Successful Projects  Lessons Learned  Conclusions.
Introduction to Procurement for Public Housing Authorities Getting Started: Basic Administrative Requirements Unit 1.
Commercial Law and International Transactions Basic Information on the Course Time & Location: –Thursday; room a.m. Commercial Law (lecturer.
PERSONAL SERVICE CONTRACTS MEMORANDUMS OF AGREEMENT PROCESS Amy Monroe, Procurement Teri Mason, Budgets Thelma Hawkins, Grants Management Karen Wirth,
Michael Replogle Chairman, Partnership on Sustainable, Low Carbon Transport And Deputy Commissioner for Policy, New York City Department of Transportation.
GROUP CERTIFICATION: THE INTERNAL CONTROL SYSTEM Istituto per la Certificazione Etica ed Ambientale.
How to succeed in International Tenders Ing. Miloš TKÁČ MTC – Engineering / Consulting / Sales Južná trieda 93 – P.c. Strojár, Košice tel.: 055 / 6808.
Public – Private Partnership in Vietnam: A new approach Ho Chi Minh City – June 2010.
Nordic transport infrastructure market – modelling and forecasting methods for asset management and business development Markku Riihimäki, Pekka.
Conflict of interest in the public sector: the Victorian experience The 7th National Investigations Symposium Jo Carden, Director Ombudsman Victoria.
Marek Stavinoha Legal officer DG MOVE A4 European Commission
Rail Baltica procurement organisation and regulations
Martin Klatt, PhD. Centre for Border Region Studies, Sønderborg
Partnership Defined “An association of two or more persons to carry on as co-owners a business for profit.” Attributes: Agreement, expressed or implied.
PRESENTATION OF MONTENEGRO
What is a grant? A direct financial contribution – donation – from EU budget An action - contributing to EU policy achievement Functioning of a body acting.
open BIM in Denmark Jan Karlshøj, Chairman of buildingSMART Nordic
DG Environment, Unit D.2 Marine Environment and Water Industry
Better Skills for Better Employment
State Aid and public funding of infrastructure - a challenge for Governments and public Authorities Preben Sandberg Pettersson, Head of State Aid Division,
Andrea Sundstrand Associate Professor
Corruption Risk Management (CRM)
Order 600/2017 – The issue and the potential exits
European Company Law Dorota Wieczorkowska
Presentation transcript:

17. January 2008 DB Export section DRB & The Øresund Link Peter Lundhus Man. Dir. Femern Bælt A/S

17. January 2008

Øresund – Crossing a Border Copenhagen Malmø

17. January 2008 Who am I?  Contractor 20 years  Owner 20 yrs. - involved in the 3 major links Great Belt Link Øresund Link Fehmarn Link ?

17. January 2008 The organisation behind the 3 Links Femern Belt Link BanverketVägverket Øresund (Land) Sund & Bælt Holding The Danish stateThe Swedish state SVEDAB (Land) Øresund Link Consortium 50 % Great Belt Link

17. January 2008 Tunnel assembly factory, Copenhagen

17. January 2008 Øresund – T tunnel units

17. January 2008 Bridgefoundation assembly line, Malmö

17. January 2008 Øresund – placing a 7000 T bridge section

17. January 2008 The connecting bridge section – 4 years + 1 mths.

17. January 2008 Consortium Agreement § 1 Name and Operations of the Consortium 1. In the light of the provisions of the agreement dated 23 March 1991 between the governments of Sweden and Denmark the Parties hereby establish a consortium, which, under the name : ØRESUNDSKONSORTIET shall on behalf of both Parties and as a single entity own and be responsible for the planning, designing, financing, construction, operation and maintenance of a toll-funded fixed link for rail and road traffic between Kastrup and Limhamn, hereinafter referred to as “the Øresund Link”. 2. The operations of the Consortium shall be conducted in accordance with sound business principles.

17. January 2008 Main numbers Øresund duration:8 years Construction time:5 years Contracts:9 major (10+ nationalities) Budget:Euro 3 billion (1990 prices) Monthly T/O:Approx. US $ 50 million

17. January 2008 Bridgebuilder job Contractors Parliaments The Press The Owner Individuals Companies Organisations Authorities in general Local authorities Consultants Other Fixed Links Competitors (ferries) Rail operators Infrastructural managers Shareholders ”Neighbours” around Øresund The public in general OH 09

17. January 2008 “He flung himself from the room, flung himself upon his horse and rode madly off in all directions.” Stephen Leacock What strategy ?

17. January 2008 Partnership - Goals, a comparison ‘Owner’ requirements:  Value for money  Timely completion  On budget Contractor’s intentions:  Value for money  Timely completion  On (his) budget (= profit) OH 03

17. January 2008 Partnership - Historic conclusions (mine) General observations over time: 1.‘Owners’ are rarely aware of their obligations in the process 2.The result is an unclear contract 3.An unclear contract is not a satisfactory foundation for cooperation OH 04

17. January 2008 Partnership - ‘Owners’ responsibilities # 1 a)Define clearly - his functional requirements - his timeframe - his quality level b)Choose risk philosophy c)Choose advisors d)Choose contractors OH 06

17. January 2008 Partnership - ‘Owners’ responsibility # 2 Understand the relationship:  Time,  Quality, and  Money Any change after award:  only 2 out of 3 – can remain fixed at the same time. OH 07

17. January 2008 Partnership - Konsortiets original choices Konsortiet decided: -to be a competent ’Owner’ - to produce no budget surprises, - allow contractors to make money - to ensure long term good quality Mental consequence:  “We are a Contractor ourselves - the Main Contractor” i.e. part of the solution to the problem, - not part of the problem itself. OH 08

17. January 2008 Partnership # 1- How? Co-operation happens only, if both parties profit from it OH 10

17. January 2008 Partnership #2 - Contract basis  Clearly written contracts Based on expectations of co-operation, not conflicts  Clearly defined requirements No compromise on quality (= low maintenance)  Construction contracts had a clear division of risks, i.e. gambling belongs to the Owner all defined risks, not under the contractor’s control, were price-able all risks under the contractor’s control belonged solely to the contractor OH 12

17. January 2008 Procurement The procurement of works follows EU Directive 93/37/EEC of 14 June 1993: Restricted procedure with prequalification

17. January 2008 Tendering basis  Transparency required  EEC 93/37 most advantageous tender  Design + Construct Delegation / Partnership Functional criteria Illustrative Design (For information only) DRB included (General Conditions

17. January 2008 Intergrated contract principles  Milestone Concept Max. 1% (paid when all NCO fixed) Selfcontrol  Dispute Review Board Decision on manning at award Frequent meeting schedule

17. January 2008 DRB operations  Individual DRBs  DRB meeting frequency 2-3 months  No DRB ever had to make a decision i.e. No claims

17. January 2008 All objectives were met:  The link opened on July 1, 2000 (9 months early)  Budget not exceeded  Within environmental framework  No contractors lost money on the project  No arbitrations or disputes  No political or media-related complications A textbook win-win situation Win-win situation