Target Update – Mico Meeting Monday 21 st April 2008 General Expect to obtain new coils for stators anytime New Shafts at RAL for metrology. Will be back.

Slides:



Advertisements
Similar presentations
Seminar on Circuit Breaker
Advertisements

MICE Magnetic Investigation of T2 MICE/ISIS Target Meeting 17 th September 2010 P J Smith – University of Sheffield.
MICE MICE Target Mechanism Paul Smith University of Sheffield 8 th June 2010 (Based upon talk given by Chris Booth at CM26)
MICE Target Report Video Conference 15/03/07 Chris Booth Sheffield 15 th March 2007.
The MICE Target Lara Howlett University of Sheffield.
Progress on Target Design Chris Booth Sheffield 2 nd August 2004.
Target Operation and Status Report Chris Booth for Target Team 20 th October 2008.
Monday Warm Up November 11.
Conduction, Convection, & Radiation
MICE TARGET HARDWARE C. Booth, P. Hodgson, R. Nicholson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England. 1 - The MICE Experiment.
Just cause you got the monkey off your back doesn't mean the circus has left town.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MICE Target Schedule Chris Booth Sheffield 12 th June 2006.
MICE Target Status Chris Booth Sheffield 10 th May 2006.
TARGET WORKSHOP – SHEFFIELD HALLAM UNIVERSITY Monday 2 March 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Target alignment with ISIS beam centre.
TARGET WORKSHOP – IMPERIAL COLLEGE LONDON Friday 8 May 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Vessel mods. 2.TC performance. 3.Wiring.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
MICE Target Review Chris Booth Sheffield 12 th June 2006.
Magnet and Absorber Heat Loads and Cooling with Various Small Coolers
MOM - M.ApollonioAccel. R&D/Physics and IADR - RAL - 19/3/ Summary of MICE operations – 14/15 March 2008 AIMS - establish MICE beamline in ISIS synchrotron.
(FEA) Analysis P J Smith University of Sheffield 27 th November 2008.
Charging System Fundamentals
DESIGN AND OPERATIONAL EXPERIENCE OF THE MICE TARGET Target Drive The linear electromagnetic drive that has been designed to meet these requirements consists.
Design Challenge Electric Motor Casey Wu Physics 4B Nov.-Dec., 2009.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
MICE Target Mechanism P J Smith University of Sheffield MICE CM 18 RAL June 2007.
S A Griffiths Target Review Jan 2009 Target Electrical / Control Schematic HexBridge Power electronics Interface PSU Capacitor Bank Local Control Interface.
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
MOM report – part I Roumen Tsenov as MOM ( )
Practical Electricity. Recap…  5 important formulae: Q = Charge (Coulomb) I = Current (Ampere) t = time (second) V = Voltage or potential.
Three-Phase AC machines
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
MICE Target - Risk Lara Howlett University of Sheffield.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
Target Status CM19 RAL October 2007 P J Smith – University of Sheffield.
1 Short Model Coils George Ellwood, Simon Canfer Jan 08.
MICE Target Mechanical Design l Status of Target ref. Schedule »Drawings –Drawing list created (see next slide) includes inventory –Drawings being released.
MICE TARGET OPERATION C. Booth, P. Hodgson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England. 1 – The MICE Experiment2 - The.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
Heat Transfer Simulation for the Welding of the T-Section.
Target tests 1 st – 2 nd Nov. Chris Booth Sheffield 7 th December 2006.
SEPTEMBER 2002 Pixel Support Tube A. Smith LBNL 1 ATLAS Pixel Detector Heater Panel Testing Alexis Smith September 17, 2002.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
Chapter 7-2 Electric Current. Electric Pressure (Voltage) Charges flow from high-voltage areas to low-voltage areas Think about it like water: water flows.
Spacing of Cu clamp = 10” Clamp plate width = 2.5”, thickness = 0.375” Thickness of conductor insulation = 0.03” Thickness of coil ground wrap = 0.03”
Target Status Report Chris Booth & Paul Hodgson Sheffield 18 th Sept ember2008.
Spectrometer Solenoids MICO 194 Steve Virostek LBNL July 25, 2012.
Chris Booth & Paul Smith Sheffield 16 th August 2007 MICE Target Installation.
Cement Mill 1 (Jan 2006) Current & Voltage. Cement Mill 1 (Apr 2008) Current & Voltage.
ATF2 Magnets ATF2 Magnets 14 Sep 2007Cherrill Spencer, SLAC. Cooling Solid Wire Sextupoles 1 Report of the effort to cool an old FFTB solid wire sextupole.
Pier Paolo Granieri, TE-CRG Collimation Upgrade Specification Meeting #35 21 st March, 2014.
Cooling System Get the engine up to optimum operating Temperature as quickly as possible and maintains it at that temperature. Controls the heat produced.
Internal Guide : Batch No : 4 Mrs.Punyavathi Madam
CONCEPTUAL DESIGN OF D2 MECHANICAL STRUCTURE S. Farinon, P. Fabbricatore (INFN-Sezione di Genova) Sept. 17 th 2014.
1)A g sample of vanadium (specific heat of 0.49 J/g˚C) was heated to ˚C (its initial temperature). This piece of vanadium is then placed into.
Solid-State Controls and Systems Electricity for Refrigeration, Heating and Air Conditioning 7th Edition Chapter 18 Solid-State Controls and Systems.
Chapter 13 – AC Motors AC motors convert AC electrical energy to Mechanical energy.
Chris Booth Sheffield 29th March 2006
Stator Plan & Schedule Chris Booth 2nd March 2009
P. J. Smith on behalf of the MICE target team.
S. Feher MICE Magnet Readiness Review RAL, June 28th, 2016
MICE Target Report Video Conference 29/11/07
AC Motors AC motors convert AC electrical energy to Mechanical energy.
Three-Phase AC machines
A presentation on Measurement of Winding Resistance and Insulation Resistance of 3 Phase 11 kV/ 433 V, 16KVA Oil cooled type Transformer PRESENTED BY:
Three-Phase AC machines
Status of Target Design
1. TURBOGENERATOR ROTOR WINDINGS
Electric Machine Design Course
Presentation transcript:

Target Update – Mico Meeting Monday 21 st April 2008 General Expect to obtain new coils for stators anytime New Shafts at RAL for metrology. Will be back at Sheffield soon (This week?) Other?

Thermal Tests 24 coils in each stator – In the ‘current’ design there are 6 copper shims (25um) between each pair of coils to extract the heat from the coils. The heat flows from the shims into a copper water cooled Jacket where it is extracted. All of the heat extraction components have to be earthed. A metallic bore that runs through the centre of all the coils and separates the stator from the ISIS vacuum is also earthed Last two ‘demonstrator’ stators failed due to electrical breakdown between the coils and earth. Cause is due to insufficient insulation between live and earthed parts. We built a new test stator out of the coils we rescued from the two damaged stators.

New stator We built in two ‘parts’ to test two different materials. Bottom half of the stator we used a pair of Mica washers to separate the coils from the copper. shims – Mica 50um Thick, so we could only use 2 copper shims Top half of the stator we used Kapton to separate the coils from the copper shims – Kapton 25um Thick, so we could only use 4 copper shims. Centre Bore Insulated with several wraps of 25um Kapton. All coils Insulation Tested to > 1000 Volts. Put pairs of T/C in on both sides of insulation. Coils Copper Shims Kapton Mica Top half of Stator Bottom half of Stator

Coils and Coil Varnish are both rated to a maximum of 200 deg C. Kapton Rated to 400 deg C Exact Mica Rating is unknown but will be >>200 deg C T/C connected to: Between coils 6/7 (Kapton Insulation) Between coils 12/13 (Kapton/ Mica Interface) Between coils 18/19 (Mica Insulation) Water In Water Out Actuator has been run for about 45 minutes Old Actuator use to run at about deg C with water temp in of ~15 deg C

MICA T/C Coil / Insulation Temp Insulation / Shim Temp Cooling Water In ~0.5 Hz~1.0 Hz

Coil / Insulation Temp Insulation / Shim Temp Cooling Water In KAPTON T/C ~0.5 Hz~1.0 Hz

MICA & KAPTON Results Combined ~0.5 Hz~1.0 Hz

Conclusions Adding Insulation Increases the operating temperature of the stator (as expected!) but is within specification of the components The added Insulation also appears to provides adequate electrical protection. (Insulation tested to >1KV) Normal running is at ~200V with spikes up to ~600V expected. Only done a single short run! We would like to run the actuator for an extended period to show long term reliability. Water temperature at ISIS is ~30 deg C as opposed to the ~12 deg C we used. Expect operating temperature at ISIS to be even higher than illustrated here. Higher temperature may impact upon the life of the permanent magnets. This is currently unknown If running at a higher temperature does reduce the life of magnets then the target can be run at a slower rate – but clearly impacts upon MICE running. If this is the case then future development could reduce power consumption of actuator but would need significant development. (Not for now!)