G020009-00-L E7 Lessons Learned Mark Coles Feb. 4, 2002.

Slides:



Advertisements
Similar presentations
Total Productive Maintenance
Advertisements

Stefan Hild S4 Data Workshop, Hannover, May 2005 Title 1 kHz Glitches in S4 Max-Planck-Institut für Gravitationsphysik (Albert-Einstein-Institut)
For the Collaboration GWDAW 2005 Status of inspiral search in C6 and C7 Virgo data Frédérique MARION.
Calibration of the gravitational wave signal in the LIGO detectors Gabriela Gonzalez (LSU), Mike Landry (LIGO-LHO), Patrick Sutton (PSU) with the calibration.
GWDAW 16/12/2004 Inspiral analysis of the Virgo commissioning run 4 Leone B. Bosi VIRGO coalescing binaries group on behalf of the VIRGO collaboration.
G Z 1 Block-Normal, Event Display and Q-scan Based Glitch and Veto Studies Shantanu Desai for Penn. State Burst Group And Glitch Working Group.
MCTS GUIDE TO MICROSOFT WINDOWS 7 Chapter 10 Performance Tuning.
1 In-Process Metrics for Software Testing Kan Ch 10 Steve Chenoweth, RHIT Left – In materials testing, the goal always is to break it! That’s how you know.
LIGO-G W Lessons Learned From E7 at LIGO Hanford Observatory Fred Raab Daniel Sigg.
1 ITC242 – Introduction to Data Communications Week 12 Topic 18 Chapter 19 Network Management.
LIGO Reduced Data Sets E7 standard reduced data set RDS generation for future runs decimation examples LIGO-G Z Isabel Leonor (w/ Robert Schofield)
SE 450 Software Processes & Product Metrics Reliability Engineering.
G D Interferometer Status LSC Meeting, Ann Arbor, June 4, 2005 Daniel Sigg.
DITSCAP Phase 2 - Verification Pramod Jampala Christopher Swenson.
LIGO-G Z Detector Characterization Summary K. Riles - University of Michigan 1 Summary of Detector Characterization Sessions Keith.
Maintaining and Updating Windows Server 2008
Introduction to Computer Technology
Detector Characterization in GEO 600 by Alicia M. Sintes-Olives on behalf of the GEO-DC team Universitat de les Illes Balears
Hunt for Molecules, Paris, 2005-Sep-20 Software Development for ALMA Robert LUCAS IRAM Grenoble France.
LIGO-G Z Detector Characterization Summary K. Riles - University of Michigan 1 Summary of Detector Characterization Activities Keith.
MCTS Guide to Microsoft Windows 7
LIGO-G D Commissioning PAC11, 2001 Daniel Sigg, LIGO Hanford Observatory.
LIGO-G Z NSF Review LIGO Scientific Collaboration - University of Michigan 1 LSC Participation in Initial LIGO Detector Characterization.
LIGO-G DM. Landry – Amaldi5 July 9, 2003 Laser Interferometer Gravitational Wave Observatory Monitoring LIGO Data During the S2 Science Run Michael.
Max-Planck-Institut für Gravitationsphysik (Albert-Einstein-Institut) Institut für Atom- und Molekülphysik Detector Characterization of GEO 600 during.
Virgo Commissioning update Gabriele Vajente for the Virgo Collaboration LSC/VIRGO Meeting – MIT 2007, July LIGO-G Z.
LIGO- G Z 03/23/2005LSC Meeting March BlockNormal Near-Online S4 Burst Analysis Keith Thorne Penn State University Relativity Group (Shantanu.
The Role of Data Quality in S5 Burst Analyses Lindy Blackburn 1 for the LIGO Scientific Collaboration 1 Massachusetts Institute of Technology, Cambridge,
G Amaldi Meeting 2015, Gwangju, South Korea1 Status of LIGO June 22, 2015 Daniel Sigg LIGO Hanford Observatory (on behalf of the LIGO Scientific.
LIGO Z LIGO Scientific Collaboration -- UWM 1 LSC Data Analysis Alan G. Wiseman (LSC Software Coordinator) LIGO Scientific Collaboration.
Maintaining and Updating Windows Server Monitoring Windows Server It is important to monitor your Server system to make sure it is running smoothly.
Martin Hewitson Overview of DC work. GEO DC workshop June DC work Noise characterisation Noise projections, noise sources, noise couplings Calibration.
1 Data quality and veto studies for the S4 burst search: Where do we stand? Alessandra Di Credico Syracuse University LSC Meeting, Ann Arbor (UM) June.
LIGO-G D Global Diagnostics and Detector Characterization 9 th Marcel Grossmann Meeting Daniel Sigg, LIGO Hanford Observatory.
LIGO-G D What can we Expect for the “Upper Limit” Run Stan Whitcomb LSC Meeting 13 August 2001 LIGO Hanford Observatory A Personal Reading of.
LIGO-G D Status of Stochastic Search with LIGO Vuk Mandic on behalf of LIGO Scientific Collaboration Caltech GWDAW-10, 12/15/05.
Status of coalescing binaries search activities in Virgo GWDAW 11 Status of coalescing binaries search activities in Virgo GWDAW Dec 2006 Leone.
LIGO-G D LSC Meeting Nov An Early Glimpse at the S3 Run Stan Whitcomb (LIGO–Caltech) LIGO Scientific Collaboration Meeting LIGO Hanford.
Preparing GEO600 for Gravitational Wave astronomy (A status report) Martin Hewitson, AEI Hannover for GEO600.
Pipeline Basics Jared Crossley NRAO NRAO. What is a data pipeline?  One or more programs that perform a task with reduced user interaction.  May be.
1 LESSONS FROM VIRGO+ May 17th 2010 E. Calloni for the Virgo collaboration.
LIGO-G D 1 Status of Detector Commissioning LSC Meeting, March 2001 Nergis Mavalvala California Institute of Technology.
G Z Test Mass Butterfly Modes and Alignment Amber Bullington, Stanford University Warren Johnson, Louisiana State University LIGO Livingston Detector.
3/21/06G D S4/S5 Calibration Status Brian O’Reilly For the Calibration Committee LSC March 2006 Brian O’Reilly For the Calibration Committee LSC.
LIGO- G D E7: An Instrument-builder’s Perspective Stan Whitcomb LIGO Caltech LSC Meeting Upper Limits Plenary Session 22 May 2002 LIGO Livingston.
LIGO-G M LIGO Status Gary Sanders GWIC Meeting Perth July 2001.
Gabriele Vajente ILIAS WG1 meeting - Frascati Noise Analysis Tools at Virgo.
May 29, 2006 GWADW, Elba, May 27 - June 21 LIGO-G0200XX-00-M Data Quality Monitoring at LIGO John Zweizig LIGO / Caltech.
S.Klimenko, LSC, August 2004, G Z BurstMon S.Klimenko, A.Sazonov University of Florida l motivation & documentation l description & results l.
LIGO-G D Commissioning at Hanford Stan Whitcomb Program Advisory Committee 12 December 2000 LIGO Livingston Observatory.
LIGO-G Z Detector Characterization Issues K. Riles - University of Michigan 1 Introduction to Detector Characterization Sessions Keith.
LIGO-G Z Detector Characterization SummaryK. Riles - University of Michigan 1 Summary of Detector Characterization Sessions Keith Riles (University.
Caltech, February 12th1 Virgo central interferometer: commissioning and engineering runs Matteo Barsuglia Laboratoire de l’Accelerateur Lineaire, Orsay.
LIGO-G Z Introd. to Detect. Charact. Sessions K. Riles - University of Michigan 1 Introduction to the Detector Characterization.
LSC meeting – Mar05 Livingston, LA A. Di Credico Syracuse University Glitch investigations with kleineWelle Reporting on work done by several people: L.
LIGO-G Z Detector Characterization Summary K. Riles - University of Michigan 1 Summary of the Detector Characterization Sessions Keith.
LIGO Livingston Observatory Commissioning Status and Proposed Commissioning Activities Prior to S1 Mark Coles May 13, 2002.
LIGO-G D S2 Glitch Investigation Report Laura Cadonati (MIT) on behalf of the Glitch Investigation Team LSC meeting, August 2003, Hannover.
LIGO-G Z Report on the S2 RunK. Riles / S. Whitcomb 1 Report on the S2 Run Keith Riles (University of Michigan) Stan Whitcomb (LIGO–Caltech)
Maintaining and Updating Windows Server 2008 Lesson 8.
Page 1 Coles – Operating the Observatories PAC 9 Dec. 13, 2000 G L Operating the Observatories Mark Coles.
WaveMon and Burst FOMs WaveMon WaveMon FOMs Summary & plans
Report on the S2 Run Keith Riles (University of Michigan)
Virgo Update – LSC meeting
First look at Injection of Burst Waveforms prior to S1
S2 Bilinear Couplings Study
Improving LIGO’s stability and sensitivity: commissioning examples
Lessons Learned from Commissioning of Advanced Detectors
Preparing GEO600 for Gravitational Wave astronomy (A status report)
LIGO Scientific Collaboration - University of Michigan
Presentation transcript:

G L E7 Lessons Learned Mark Coles Feb. 4, 2002

G L 2 Run Statistics Summary LLO-4KLHO-4KLHO-2KAll three together Total lock time 284 hours294 hours214 hours140 hours Duty cycle71%72%53%35% Total time locked > 15 min 249 hours231 hours157 hours72 hours Long lock duty cycle 62%57%39%18%

G L 3 Cumulative statistics at LLO

G L 4 Run time distribution at LLO Run CategoryPer cent of total run time Long locks~62% Intermittent locking (<15 min)~9% Seismic interference~25% Time server and calibrations~5%

G L 5 ASC – noise from optical levers Periscope vibration Photodetector pre- amplifier Johnson noise Frequency noise + Sensitive to alignment, fringe offset in PMC, Laser glitches LLO Noise Factors “low noise mode”

G L 6 What did we learn…  That will improve the conduct of the next run?  That will aid in completion of commissioning?  That will help LIGO to attain reliable full-time operation as a scientific observatory Topics:  Detector stationarity and stability  Hardware performance: reliability, robustness  Software and controls: reliability, performance, ease of use  Operations procedures: calibrations, check lists, shift duties, shift lengths, staffing numbers, other human factors, etc.  Inter-site planning and coordination

G L 7 Detector Performance  Noise stationarity »We made and archived spectra 3-10 times per day throughout the run (usually 3 per shift when locked), more than 100 archived spectra during run »“Canonical” comparison format for data – between times of day and between interferometers is very helpful –We decided on a particular way of doing this during E7. –Based on E7 experience, we should establish a standard for future science runs to represent calibrated sensitivity so ALL detectors participating will have compatible plots for easy comparison »Need to tell difference between spectrum changing and calibrations changing – need to think about how to optimize this for future runs

G L 8

9 Calibration  Updates made three times during run  Calibrations synchronized between sites  CARM and DARM control signals stable within about ~5%  AS_Q and REFL_I &Q signal varied by perhaps ~20-30% over the run due to alignment and offset drifts (calibration uncertainty determination in progress)  Indicates there are slow changes in noise spectrum that occur during long locked stretches- due to e.g. tidal shifts at LLO (tidal feedback servo not yet implemented at LLO)  How frequently should we calibrate in order to maximize ability to analyze data?  A standard procedure for calibration that is automated as much as possible would be very welcome in future runs. Present method is time consuming and requires several hours of precious “prime time”

G L 10 LLO Calibration Stability 12/311/61/14 CARM_CTRL 0.86e-90.85e-90.83e-9 DARM_CTRL 0.86e-90.85e-90.83e-9 MICH_CTRL 9.47e-99.1e-99.4e-9 AS_Q 1.63e-141.4e e-14 REFL_I 5.63e-145.0e e-14 REFL_Q 8660e e e-14 PRELIMINARY – UNCERTAINTIES NOT YET ESTABLISHED

G L 11 Hardware Reliability  Microseismic feed forward worked very well except in 2 cases where shape of microseismic peak changed significantly. Ability to adapt filters to accommodate other shapes is needed.  Hardware failures during run were minor: »GDS clock True Time server Y2K+2 fault promptly fixed by setting up alternate time server on UNIX workstation. »One disc on RAID system for frame builder failed for 1 sec frames (but without harm since RAID) »Cold weather was a cause for concern in air compressor system due to residual water. Added to operator watch list  Need to have operator visibility into data logging process: »EPICS screen of frame builder diagnostics with web interface developed during run (Chethan). Added to operator checklist for future runs.  Updated on-line operator check list seemed to work well, insuring that even obscure sub-systems are looked at regularly.  When seismic noise was too high to maintain lock (typically weekdays) we operated with a single arm locked. »Is this useful?

G L 12 Software Reliability  CDS software was robust  DCU’s operated without reboot, and very limited problems in general with data acquisition  Except for GDS Time Server Y2K+2 problem, operation was smooth and almost trouble free

G L 13 Realtime Data Monitoring Suggestions:  Realtime lock statistics are nice to have as a monitor of shift performance  More data monitors that display realtime data in a way that is helpful to the on-shift staff for hardware monitoring and data quality »AS_Q BLRMS monitor created (by Ed Daw) during run to look at time evolution of AS_Q signal in particular frequency bands is a good example of a useful monitor »LIGO could create a list of DMT monitor items that the project would like to have the LSC provide. »Use Data Viewer to display trends of data monitors »Develop standards for interface and display of DM variables  Tedious to compare spectra which use different calibration files - an easy way to overlay data from different calibrations would be helpful

G L 14 More realtime suggestions…  Some additional live data quality factors for noise performance during run will be helpful for future runs. Example: »Live spectrograms using spectrum analyzer (last day of run) => easy to see burst noise »Enhancements to data quality monitor such as trigger rates, histograms of time between triggers, trend lock length vs time of day »Monitor injected cw signal long term as a realtime measure of spectral quality and calibration (in progress – Sergei Klimenko) »R0 and integrated R**3 (enhancement of Sam Finn’s binary inspiral model and BENCH program to work with realtime data), etc. »Probability distributions of the signals/signatures to look for. Ability to discriminate non-Gaussian behavior is critical.

G L 15 Environmental Couplings  Operation over New Year’s holiday was a good choice seismically for LLO. That, plus rain two days, reduced logging and other outdoor activity which contribute to overall seismic environment.  Auto traffic on-site across cattle guard couples pretty strongly into AS_Q, REFL_I, and REFL_Q signals. We should remove cattle guard since it is no longer needed (and investigate whether the one close to the highway degrades the data too.)

G L 16 Human Factors  Shift lengths »10 hour shifts seemed to work very well. Operator feedback uniformly positive. »Operator shifts: 7am – 5pm, 4 pm – 2 am, and 10 pm – 8 am so that there is a big crew during prime operating time – very helpful for calibrations and house keeping chores »Only one operator on day shift Mon-Fri. –This should be changed – too stressful with one because of the amount of day time activity that comes through the control room, really need two people »Scientist shifts were 12 hours. Some positive feedback but lots of negative feedback that this was too long and people were too tired for there to be much effective overlap. »Albert Lazzarini has raised the issue of beds on site for driving safety  Operator responsibilities »Uniform positive response from scientific staff regarding quality of operator support to maintain operation, fill out check lists, etc. »Operator shift check list worked well, but a bit tedious. It ensures that someone looks at the operational status of a large number of systems at least three times per day, but automated alarms can replace some of this in the future.

G L 17 Human Factors…  Scientist responsibilities »Less well defined, but there is a very wide spectrum of operating experience of scientists on shift. Strong operator support makes this issue less pressing at present, but we should think about how to make this a more effective role for the scientists on shift to act as representatives of the LSC to “QC” the data during future science runs –Strengthen intellectual coupling of scientists to the operational activities –Task lists evolved during the run, continue to think about how to use these effectively –Most scientists were very conscientious in carrying out shift responsibilities –Hard to quantify how to actively check for problems in addition to what’s on the list, but more guidance for future runs will be helpful

G L 18 Human Factors…  One of the biggest benefits of E7 is that it got a large number of people to look at the data and consequently unanticipated instrumental signatures were identified in the data. This is a very good start to a role we want to foster for scientific shift taking  Suggestions »LSC operations bootcamp preparatory to S1 »Feedback that more discretionary time while at site would be useful to give visitors chance to work on analysis software and other related projects rather than just be on shift all the time – another motivation for shorter shifts

G L 19 Human factors…  Coordination between LIGO sites and GEO, ALLEGRO »Continue to evolve master run schedule list –Examples: Calibrations periods, signal injections, planned operational status of LSU bar, scheduled disruptions, etc. –Some of this was done for E7, but we can enhance for next time –Coordination with ALLEGRO needs to improve »Enhance usefulness of daily run coordination calls –It’s a valuable resource, how do we make the most use of it? –Review of structured information such as daily run summaries, planned schedule changes, other? –Informal telephone calls between control rooms worked very well for quick communication of status information

G L 20 Human factors…  Continue to develop operator documentation: »We had procedures for how to put IFO in robust mode, low noise mode, single arm lock – but they got revised a lot during the run. »Need to continue adding to and updating this documentation. »More and better on-screen help files on control screens. E7 run helps focus attention on this need. –What we have is very helpful, but we need to add to it –More details, standard formatting to improve readability, add names of experts, etc.

G L 21 Final suggestions  Auto files are great, need more utilization – but need to be carefully implemented »BURT files to change operating mode but: need to update filters after BURT »AUTOLOCK script for acquire of lock in recombined mode was very helpful »Expand these tools for the next run.  More system level documentation. What we have already available has proven very useful - especially helpful for quick access to system level information and to those less familiar with system as a quick learning tool. »block diagrams of optical configuration, control topologies, CDS architecture »Additional diagrams such as filter topology, etc., would be helpful  Greater organization of e-log to find important information »Reference spectra »Procedures and operating instructions »Configuration changes  Time to begin implementing Systems Identification concepts? »Quantitative methods for determining when to recalibrate »Generalization of micro-seismic feed forward filters? »Identification of recalibration points? Make sure both sites benefit from each other’s experience!