1st Quarter Contractor Business Meeting March 13 th, 2015 Yesika L. Kain/Ben Mulherin Plant Engineering Facilities Session.

Slides:



Advertisements
Similar presentations
Tower Crane Safety Regulations
Advertisements

MU Aerial Lift Building Training
FHM TRAINING TOOLS This training presentation is part of FHM’s commitment to creating and keeping safe workplaces. Be sure to check out all the training.
Scissor Lift Safety Training
ELEVATING WORK PLATFORMS By Richard Hadcroft. PARTIES INVOLVED.
1 Struck-By Module 3. 2Objectives After this module you should be able to – identify the most common struck-by hazards – take the necessary steps to avoid.
1293 Airport Road Beaver, WV Phone: (304) Fax: (304) Crane Safety Vincent J. Giblin, General President.
4th Quarter Contractor Business Meeting November 4, 2011 Mike Kehoe Plant Engineering Facilities Session.
1st Quarter Contractor Business Meeting March 9, 2012 Mike Kehoe Plant Engineering Facilities Session.
Cranes and Slings Major Causes of Crane Accidents
Powered Industrial Trucks - Operator Training
1st Quarter Contractor Business Meeting March 8, 2013 Mike Kehoe & Yesika Castro-Hernandez Plant Engineering Facilities Session.
OSHA Office of Training & Education
Moments of Inertia Polar moment of inertia – Used when calculating the torsion – Indication of resistance to torsion – Solid Shaft – J = π R 4 / 2 Area.
Crane Operations Objective
SAFE HANDLING OF PRECAST CONCRETE PRODUCTS
Crane Safety, Subpart N
Crane and Hoist Training
Cranes, Hoists and Truck Hoists
Electrocution 44% Rigging Failure 15% Load Handling 14% Operator Error 7% Overload 7% Dismantling Boom 5% Wire Rope Failure 3% Miscellaneous 3% Struck.
1 Cranes Module 13. 2Objectives After this module you should be able to – identify the most common crane hazards – take the necessary steps to avoid those.
Cranes, Derricks, Hoists, Elevators, & Conveyors for Construction
Safety Training: Technical Training Clearance Procedure Authorized Employee This course is best viewed with headphones or speakers, the audio.
3 rd Quarter Contractor Business Meeting September 9, 2011 Mike Kehoe Plant Engineering Facilities Session.
Fork Lift Safety Awareness Powered Industrial Truck Operation Training.
4th Quarter Contractor Business Meeting December 5 th, 2014 Yesika L. Kain Plant Engineering Facilities Session.
Cranes, Derricks, Hoists, Elevators, & Conveyors for Construction.
Material Handling Safety This material was produced under the grant SH SH1 from the Occupational Safety and Health Administration, U.S. Department.
Fall Protection in the Roofing Industry
Engineering Manufacturing Facilities
Material Handling. Introduction Handling and storing materials include a wide variety of tasks like: Hoisting tons of steel with a crane Driving a truck.
Powered Industrial Trucks 29 CFR Disclaimer As a committee of a national organization, the Safety, Health & Environmental Committee of NPCA.
BUILD WITH US. ™ Contractors
Construction Safety Council. by David G. Allie Subpart R - Steel Erection ( ) Tiered buildings not adaptable to temporary floors - Safety.
Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC Brad Solheim Department of Labor & Industries Crane.
3nd Quarter Contractor Business Meeting September 14, 2012 Mike Kehoe Plant Engineering Facilities Session.
Forklift Safety Training
Most Frequently Cited Serious Violations Construction – FY 2011 OSHA Federal Standards October 1, 2010 – September 30, 2011.
Scissor Lift Safety Training Working Safely on Scissor Lifts 29 CFR OSHA Scaffolding Safety Requirements.
NECA & Salisbury Assessment Solutions Partnership.
4.2.8 Student Book © 2004 Propane Education & Research CouncilPage Installing Aboveground ASME Tanks Installing aboveground tanks is an important.
This presentation is for illustrative and general educational purposes only and is not intended to substitute for the official MSHA Investigation Report.
2.5.5 Student Book © 2004 Propane Education & Research CouncilPage Coordinating Loading and Unloading of ASME Tanks Using Contractor- Operated.
Most Frequently Cited Serious Violations Construction – FY 2009 OSHA Federal Standards October 1, 2008 – September 30, 2009.
Standard 29 CFR Part Sling and Lifting Devices Training.
Sling Load Capacity and Sling Angles
Log dumps, Ponds and Yards Section L of the Forest Activities Code.
Sling Safety (Level 1 Rigger). Objectives Be familiar with regulations regarding slings. Be familiar with regulations regarding slings. Understand safe.
2nd Quarter Contractor Business Meeting June 8, 2012 Mike Kehoe Plant Engineering Facilities Session.
FORKLIFT OPERATION TRAINING
Linehandler. Disclaimer DISCLAIMER: The contents of this document are intended only for the informational use of the addressee. The information contained.
Overview of ASME P Planning for Load Handling Activities
SCG-SH-0200 Southern Company Generation Clearance Procedure Awareness Training for Contractors and Nonlisted Personnel.
Cranes, Derricks, Hoists, Elevators, and Conveyors - Subpart N Section 6 Robert Poole St. Paul Fire & Marine Insurance Company.
Electrical Safety OSHE 382, Spring 2016
Cessco Fabrication & Engineering Ltd.
Most Frequently Cited Serious Violations
Most Frequently Cited Serious Violations
Who is Responsible for Overhead Crane and Hoist Operations
Better to Lockout/Tagout Than to Luck Out!
Lifting & Rigging Continuing Education Fourth Quarter 2016
Limit Switches What are some different types of limit switches?
Most Frequently Cited Serious Violations
PPE Program 29 CFR OSHA requirement for this company to have a Personal Protective Equipment Program to protect employees from exposure to.
Top Ten Violations in Construction FY 2018
Working Near Forklifts
Most Frequently Cited Serious Violations
Cranes and Hoists Standard 29 CFR Part
Click to start.. Click to start. Rigging for a safe lift SAFETY TALKS! for PowerPoint © MMIV Bongarde Holdings Inc.
Powered industrial Trucks (GI-Part 21)
Presentation transcript:

1st Quarter Contractor Business Meeting March 13 th, 2015 Yesika L. Kain/Ben Mulherin Plant Engineering Facilities Session

Agenda Crane Accident from Travel Path Foul (Ben Mulherin) Contractor Lifting and Handing (Jennings Spease) PPE During Cold Weather (Rod Taylor) Aerial Equipment (Rod Taylor) Speed Limit Change (Rod Taylor) 2

Crane Accident from Travel Path Foul A crane crew was tasked with removing a JLG out of a Dry Dock using crane. While in the process of traveling the crane, the crane’s gear trucks made unplanned contact with a “ladder-up” that had been installed on catwalk of the dry dock. The contact caused damage to the “ladder-up”. There was no damage to the crane. The crane path was walked and cleared to proceed by leg walkers prior to crane movement and the “ladder-up” was not identified in the “up” position. “Ladder-up” devices have been removed in areas that will impact crane travel path. 3

Crane Accident from Travel Path Foul 4 The flowchart below describes the actions required to determine if the project will breach the crane envelope.

Crane Accident from Travel Path Foul Per SOP O (Facilities Design Process) The figure below outlines the fouling parameters for a Gantry Crane and Whirler Crane or Post Crane operation 5 The two illustrated crane envelopes include the structure in blue and the buffer zone in yellow along the entire travel path or throughout the swing radius. Do not exclude the envelope areas above the crane as well as along the sides and any space along the travel path as part of the crane envelope.

Contractor’s Lifting and Handling Briefing 6

Certificate of Compliance 7

Forklift Attachments (a)(4):Modifications and additions which affect capacity and safe operation shall not be performed by the customer or user without manufacturer’s prior written approval. Capacity, operation and maintenance instruction plates, tags or decals shall be changed accordingly (a)(5):If the truck is equipped with front-end attachments other than factory installed attachments, the user shall request that the truck be marked to identify the attachments and show the approximate weight of the truck and attachment combination at maximum elevation with load laterally centered (a)(6):The user shall see that all nameplates and markings are in place and are maintained in a legible condition. 8

“Free Rigging” Free rigging is the direct attachment to or placement of rigging equipment (slings, shackles, rings, etc.) onto the tines of a powered industrial truck for a below-the-tines lift. This type of lift does not use an approved lifting attachment. Although free rigging is a common practice, it could affect the capacity and safe operation of a powered industrial truck. 29 CFR (a)(4) requires that “Modifications and additions which affect the capacity and safe operation shall not be performed by the customer or user without manufacturers prior written approval. Capacity, operation and maintenance instruction plates, tags or decals shall be changed accordingly. Information shown is from OSHA standard interpretations 9

If you cant get Manufacturer’s Approval Employers must seek written approval from powered industrial truck manufacturers when modifications and additions affect the capacity and safe operation of powered industrial trucks. However, if no response or a negative response is received from the manufacturer, OSHA will accept a written approval of the modification/addition from a Qualified Registered Professional Engineer. A Qualified Registered Professional Engineer must perform a safety analysis and address any safety and/or structural issues contained in the manufacturer's negative response prior to granting approval. Machine data plates must be changed accordingly. Of course, the use of an approved attachment to make lifts would be a viable alternative for an employer who does not seek written approval from a manufacturer or a Qualified Registered Professional Engineer. However, please be aware that OSHA would consider the lack of manufacturer's approval to be a de minimis violation if the employer has obtained written approval from a qualified Registered Professional Engineer after receiving no response or a negative response from the powered industrial truck manufacturer. If the manufacturer's response was negative, then the engineer, prior to granting approval for the modification or addition, would need to perform a safety analysis and address all safety and/or structural issues contained in the manufacturer's disapproval. Information shown is from OSHA standard interpretations 10

PPE During Cold Weather During cold weather only approved items may be worn underneath hard hats. 11

Aerial Lifts Picture below is of damage to an NNS Aerial Lift 12

Speed Limit Change 13 The 10 mph speed limit zone has been extended from the north side of Building 256 to the south side of Building 103.

QUESTIONS? Please submit your questions related to sourcing topics at the following address: If you have questions regarding this presentation, please contact your Contract Coordinator/Field Engineer or: Ben Mulherin This presentation will be posted on the public NNS website for your reference. 14