Produced by: Cement Plant Shutdowns During Lean Times Seth A. Tyler TXI.

Slides:



Advertisements
Similar presentations
MAINTENANCE PLANNING AND SCHEDULING
Advertisements

TOTAL QUALITY MANAGEMENT (TQM) Increasing Productivity.
Facilitated by Joanne Fraser RiverSystems
Project Management What is it? The management and control of a group of interrelated tasks required to be completed in an efficient and timely manner.
Scope Creep Who is the Ring leader of your Circus
Lean Accounting and Value Stream Costing
Business Plan Preparation Frank Moyes Leeds College of Business University of Colorado Boulder, Colorado 1 Financial Plans.
Defining the Activities. Documents  Goal Statement defines why helps manage expectations  Statement of Work what gets delivered defines scope  Software.
Project Management for Public Health Professionals February 2011 David Sabapathy, MD, MBA, PEng Department of Community Health Sciences 3 rd floor TRW.
“80% of software projects fail”  Standish Report (1995) Standish Report 16.2% completed on-time and on-budget with all features and functions as initially.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
SchedulingProducingControllingSchedulingProducingControlling.
 A project is “a unique endeavor to produce a set of deliverables within clearly specified time, cost and quality constraints”
Copyright © Houghton Mifflin Company. All rights reserved. 6-1 Chapter 6 The Basics of Planning and Project Planning.
Implementing and Managing a Maintenance Plan The Maintenance Plan Ken Henman.
Evaluation#3 MS Project Objectived u In this lab you will learn: – how to add the resources into tasks. –How to review resource assignment information.
Be more effective at “planning the work and working the plan” Project Management Tips.
Copyright © Houghton Mifflin Company. All rights reserved. 6-1 Chapter 6 The Basics of Planning and Project Planning.
Introduction: Throughout history and especially in today’s global economy, companies and agencies are constantly looking for ways to do more and more with.
Produced by: 5 Keys Proven to Enhance Worker Performance E.J. (Ted) Lister Lister Management Inc.
Introduction to Business 3e 9 Part III: Management Copyright © 2004 South-Western. All rights reserved. Improving Productivity and Quality.
Introduction- Project Management By Ctrl+C & Ctrl+V 1.
Foundations of Technology.  To familiarize students with the function, applications, and requirements of construction management.
Department of Innovation & Technology City of Boston Five Key Ways to Be a Successful Project Manager March 2014.
Lecture4 : Project planning Lecturer: Kawther Abas 447CS – Management of Programming Projects.
Chapter 3: Project Management Omar Meqdadi SE 2730 Lecture 3 Department of Computer Science and Software Engineering University of Wisconsin-Platteville.
Lean Project Management
Switch off your Mobiles Phones or Change Profile to Silent Mode.
Lecture 7. Review of Lecture 6 Project Scheduling: The process of defining project activities, determining their sequence, estimating their duration Scheduling.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Lecture 3 Managing the Development Project SFDV Principles of Information Systems.
CASE STUDY EXAMPLE Work Process Flow Charts. WORK IDENTIFICATION / WORK ORDER PROCESSING Review Notification Asset Coordinator Notification complete and.
UNIT II RCM PROCESS Module 2 PLANNING AND PREPARATION " Copyright 2002, Information Spectrum, Inc. All Rights Reserved."
Contract Training Class I
Tm&i 2010 VII.1 technology management & innovation introduction to project management (iii) reviewing & operating projects.
Lecture 3 Title: Information Technology Project Methodology By: Mr Hashem Alaidaros MIS 434.
Project management.  To explain the main tasks undertaken by project managers  To introduce software project management and to describe its distinctive.
PLUG IT IN 6 Project Management. 1.Project Management for Information Systems Projects 2.The Project Management Process 3.The Project Management Body.
Produced by: Towards a Rational Cost Model Presenter: Tom Lenahan Tom Lenahan Limited.
Fiscal Planning (Budgeting). Fiscal Planning Fiscal planning is not intuitive; it is a learned skill that improves with practice. Fiscal planning requires.
Quizzes From fall Survey results.
Management and Leadership. Frank faced a number of challenges as he sat at his work station Monday morning. He is a supervisor of a production line at.
McGraw-Hill /Irwin Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. Chapter 7 Profit Planning.
Copyright © 2003 Primavera Systems, Inc Primavera User Conference Real World Outage Planning and Control presented by Mike Stone w/ Professional.
Project Management Inspections and Reviews 1 February.
Project Management Organization Scheduling 31 January.
Recruitment & HR. You’ll discover:  Tips on hiring the right people  Why & how to facilitate Performance Reviews  How to Motivate Your Team  Importance.
Budgeting 101 “Piece of the Puzzle” By: Michelle Schumann – IT Student Mentor.
Compensation Methods.
MARCH 1 Project Management Problem statement l no hurdles, no problem just a goal l open-ended … no single correct answer l closed-ended … single answer.
Produced by: Use The Fundamentals To Drive Waste From Your STO By: Craig Pindell.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
University of Calgary Continuing Education Construction Contract Law and Documents Week 12 Changes Delays Claims Contract Documentation.
1 Project Management Software management is distinct and often more difficult from other engineering managements mainly because: – Software product is.
MH...CH LECT-021 SYSTEMS CONCEPT Adopting a materials handling systems from overall optimization point of view. Adopting a materials handling systems.
Switch off your Mobiles Phones or Change Profile to Silent Mode.
What is a Project? “ Unique process consisting of a set of coordinated and controlled activities with start and finish dates, undertaken to achieve an.
Management, Supervision, and Decision Making Chapter 2.
HCIS 410 Read, Lead, Succeed/Uophelpdotcom For more course tutorials visit
Practical IT Research that Drives Measurable Results Establish an Effective IT Steering Committee.
Agenda Ej Lister – President & CEO – STOnavigator™ inc.
Project Management Jukka A. Miettinen September 4, 2006
Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
Maintenance Scheduling
MAINTENANCE PLANNING AND SCHEDULING
Organizations, Constraints & Projects
INDUSTRIAL FIREPROOFING Evaluation Services
Teaching slides Chapter 13
Time Scheduling and Project management
Presentation transcript:

Produced by: Cement Plant Shutdowns During Lean Times Seth A. Tyler TXI

Cement Plant Outages in Lean Economic Times Outage Preparation Outage Execution Key Learning's Questions Key Topics of Presentation

Introduction & Overview TXI-Midlothian Cement Plant Process o Limestone o Silica o Alumina o Iron o Fire o Clinker o Gypsum

Introduction & Overview TXI-Midlothian Cement Plant

Introduction & Overview TXI-Midlothian Cement Plant Major Equipment o Crushers, Vertical Roller Mill, Rotary Kiln, Finish Mills (6), Scrubber, RTO Typical Outages o Kiln (1 major and 1 minor per year) o Finish Mills

Slide 6 Cement Plant Outages in Lean Economic Times No Contractors, No Overtime, No Money Changing Goals o Production to Cash Preservation o Proactive (fix it) to Reactive (defer the cost) o Minimizing Risk to Taking on More Risk o Around the clock to four tens and everything in between o Two Weeks to Two Months, Three Mondays o Resource Abundance to Resource Constraint (contractors) o Lack of Sense of Urgency, Challenge of Motivation

Slide 7 Outage Preparation The Most Critical Step, Regardless of the Economy Pre-Planning o At least one meeting per month o We try for one per week (We have 6 mills, 1 kiln) Safety o Pre-Outage Contractor Safety Meeting  Set Expectations and Consequences  Send out Packets at least 2 weeks prior to meeting  Insurance Requirements

Slide 8 Outage Preparation The Most Critical Step, Regardless of the Economy Scheduling o Gantt Chart

Slide 9 Outage Preparation The Most Critical Step, Regardless of the Economy o Use Gantt Chart  Details-more time up front, but will help with the “little things” that always get you in the end  Assign Resources for each task  Use Critical Path Function  Cold Oil-Put the Task on the Chart o Excel vs. Project

Slide 10 Outage Preparation The Most Critical Step, Regardless of the Economy Parts Staging o Specific areas for parts, preferably near equipment location o Use a shipping container-Inconvenient, but you can lock up parts o Difficult in lean times due to lack of resources o Have suppliers tag parts and hardware so you know where they go—Work Order and Asset Number

Slide 11 Outage Execution It’s The Best of Times and The Worst of Times… Parts Staging o Chasing parts  Even though parts are staged, you still have to get them  Contractors stay on job, employees get parts  No contractors

Slide 12 Outage Execution It’s The Best of Times and The Worst of Times… Daily Planning Meeting o One formal meeting daily-All Stakeholders are Represented o Contractors present o Agenda-Follow it o Discuss progress in each area on Gantt Chart-This should be updated prior to meeting. o Rental Equipment, Scaffolding, Cranes, Electrical needs… o Give all an opportunity to speak-go around the room

Slide 13 Outage Execution It’s The Best of Times and The Worst of Times… Daily Planning Meeting-Financial Discussion o Contractors are not Present o All contractor time should be turned in and received daily  We have a specific Time Sheet we require them to use  We have their labor rates for each craft  We are watching each contractor total to see if we are getting in trouble in any specific area o All direct charges should be updated daily o All Inventory issues should be updated daily

Slide 14 Outage Execution It’s The Best of Times and The Worst of Times… Shift Handover meeting o We have these at each job location o Supervisors are there o No night shift!

Slide 15 Outage Execution It’s The Best of Times and The Worst of Times… Contractor Control o Start out with none, bring in as needs increase o Minimize weekend work if possible (start on Monday) o Bring in slowly and get out fast—don’t keep too many for too long o Kiln cool down o Watch the in and outs

Slide 16 Outage Execution It’s The Best of Times and The Worst of Times… Scope Creep o Management team discusses risk and rewards of performing unplanned work. Budget Shrinkage o We don’t have the money…  We re-prioritize the work  Willing to accept future downtime---but keep good notes

Slide 17 Outage Execution It’s The Best of Times and The Worst of Times… Expecting the Unexpected o Know there will be things o Depend on your Technicians to come up with solutions Rental Equipment Management o Assign one person to be responsible coordinating rental equipment  Understand the rental terms—28 days o Assign equipment to each job and share when possible  There are those who didn’t plan and they will “borrow”…

Slide 18 Outage Execution It’s The Best of Times and The Worst of Times… Consumables o Clearly dictate to contractors what you will pay for and what you will provide.  This should be in the pre-outage contractor package o Have hardware supplier restocking every day, twice a day when going back together. Utilize Production  Inspections and minor repairs

Slide 19 Outage Execution It’s The Best of Times and The Worst of Times… After Action Review Meeting o What went right o What went wrong o List for next year o Contractor evaluation

It’s the Little Things…. Hardware, Parts Staging are Critical to Success o Vendor managed at least daily, tag parts Plan, Plan and Plan Some More o Use detailed Gantt Chart o Stick to your meeting agenda Keep Track of Your Expenses o Receive contractor time daily o Keep up with inventory and direct charges daily Key Learning’s

Questions? Cement Plant Shutdowns During Lean Times

Produced by: Seth A. Tyler TXI