ISSUES WITH RETROFIT REQUIREMENTS FOR HVRT 1. CURRENT SITUATION WGRs HAVE HAD A CLEAR LIMIT OF 1.1 pu SPECIFIED FOR HVRT IN THE GUIDES WGRs ARE NOW BEING.

Slides:



Advertisements
Similar presentations
An Overview of the Development of a Renewable Energy Project And the 5 Major Milestones to Achieve Financing By Robert Hunter Director of Operations, Green.
Advertisements

STATUS OF BULK ELECTRIC SYSTEM DEFINITION PROJECT
Recent NERC Standards Activities RSC – Jan. 5, 2011 NSRS Update Date Meeting Title (optional)
November 19, 2013 Preparing a Successful RFP to get Desired Results.
ERCOT VRT Study, Phase I ERCOT ROS Meeting December 10, 2009.
Chapter 6. Explain the process a HCO generally goes through in selecting a HCIS. Describe the SDLC and its four major stages. Discuss the various stages.
USAID Africa Bureau EIA Procedures for Sub-Projects
System Strength Discussion
Time for a new standard - AS General Conditions of Contract
Integrating Wind on Weak Grids – CREZ Panhandle Region Sharyland Utilities July 16, 2014.
Generation Interconnection Overview
Specification Writing Presentation Training & Development.
Chapter 17 Acquiring and Implementing Accounting Information Systems
Wind Grid Codes GE Energy Asia Development Bank
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
ERCOT John Adams September 14, 2012 Planning Guide concepts for dealing with Sub Synchronous Resonance in ERCOT & other issues.
Evaluation of RURAL MIGRANT SKILLS DEVELOPMENT AND EMPLOYMENT PROJECT CzechDET2009 Group 3.
FAR PART 45 – Government Property
North Eastham Wind Feasibility Study Results Brian Eastman Eastham Energy Committee Kristen Burke Massachusetts Technology Collaborative Ric O’Connell.
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
FAR Part 2 Definitions of Words and Terms. FAR Scope of part (a)This part – (1) Defines words and terms that are frequently used in the FAR; (2)
Entity Registration Under EPAct 2005 Public Power Council April 6, 2006 Louise McCarren Chief Executive Officer WECC.
Project WECC-0100 Update Reliability Subcommittee February 2014.
Steve Rueckert Director of Standards TPL Discussion – PCC Steering Committee March 25, 2014.
RTWG Report to TAC August 5, 2010 Howard Daniels.
Procedures and Forms 2008 FRCC Compliance Workshop April 8-9, 2008.
TERM LOANS PROCEDURAL REQUIREMENTS. Obligations of assistance.
Actions Affecting ERCOT Resulting From The Northeast Blackout ERCOT Board Of Directors Meeting April 20, 2004 Sam Jones, COO.
Engineering a sustainable future 1 ERCOT Voltage Ride-Through Study Workshop June 26 th, 2009.
1 Texas Regional Entity 2008 Budget Update May 16, 2007.
WELCOME TO UNB. MARK McGEEHAN Assistant Manager, Procurement Services 3 plus years with UNB 28 years in Healthcare Procurement Current member of APPA.
Submitting IT Purchasing Statements of Work to DIR SB 20 COMPLIANCE FOR TEXAS STATE AGENCIES TECHNOLOGY SOLUTIONS FOR GOVERNMENT AND EDUCATION.
PRR835 – Reactive Power Capability Requirement
Project System Protection Coordination Requirement revisions to PRC (ii) Texas Reliability Entity NERC Standards Reliability Subcommittee.
Project Management Models
Item 5d Texas RE 2011 Budget Assumptions April 19, Texas RE Preliminary Budget Assumptions Board of Directors and Advisory Committee April 19,
Managing Authority of EU Funds – Ministry of Finance 1 Methodology of selection of project applications for EU funds including preparation of appraisal.
NPRR425 - Creation of a WGR Group for GREDP and Base Point Deviation Evaluation and Mixing Turbine Types Within a WGR Art Deller, P.E. RARF Workshop 8/29/13.
PLANNING ENGINEERING AND PROJECT MANAGEMENT By Lec. Junaid Arshad 1 Lecture#03 DEPARTMENT OF ENGINEERING MANAGEMENT.
Salient IRR Revisions Alternative Methods of Procurement.
Operational Issues & Risks ERCOT Operations Planning August 22, 2008.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
ERCOT VRT Voltage Ride Through Standards. Standards Groups Edison Electric Institute (EEI) National Electrical Manufactures Association (NEMA) American.
Distributed Generation Registration June 30, 2008.
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
Chapter 8 Final Construction Final construction in the SDLC Construct and test programs Construct and test the database Obtain additional hardware Prepare.
Grid Operations Report To ERCOT Board Of Directors December 16, 2003 Sam Jones, COO.
1 DESIGN RESPONSIBILITIES Contract Information Supplied by Design Team Responsibility of the Precaster Option I Provide complete drawings and specifications.
ROS July 10, 2008 Meeting WOTF Update on ROS Action Plan Summary: EECP Step #2 (Feb.26 th, 2008) Mark Garrott WOTF Chair.
Panhandle Renewable Energy Zone (PREZ) Study
ERCOT DYNAMICS WORKING GROUP Report to ROS August 16, 2007 Vance Beauregard, American Electric Power.
CREZ Related Generation Interconnection Studies July 2008 Jeff Billo RPG meeting
Respect for the Individual · Humility · Innovation · Excellence · Teamwork · Integrity System Strength/Short Circuit Current Minimum Requirement June 5,
Generation Adequacy Task Force Meeting April 10, 2014.
October 15, 2012 PV & Storage Workshop ERCOT’s Interconnection Process John Adams Principal Engineer.
Ajay Pappu Resource Integration Department ERCOT Generator Frequency Relay Settings Survey Dec 2013.
Reliability Standard TPL Transmission System Planned Performance for Geomagnetic Disturbance Events September 28, 2016 TPL Standard Status.
GIC System Model Workshop
Freeport Area Master Plan Project -
NERC Lessons Learned Summary
ISSUES WITH RETROFIT REQUIREMENTS FOR HVRT
Using Analytics To Improve Contract Lifecycle Management
Phase Angle Limitations
FAR Part 2 - Definitions of Words and Terms
Planning Geomagnetic Disturbance Task Force (PGDTF) Update to the ROS
Reliability and Operations Subcommittee Report
Background (history, process to date) Status of CANs
Standards Review Subcommittee Update
Project WECC-0100 Update Reliability Subcommittee
Presentation transcript:

ISSUES WITH RETROFIT REQUIREMENTS FOR HVRT 1

CURRENT SITUATION WGRs HAVE HAD A CLEAR LIMIT OF 1.1 pu SPECIFIED FOR HVRT IN THE GUIDES WGRs ARE NOW BEING DEVELOPED THROUGHOUT ERCOT IN MANY STAGES OF COMPLETION BASED UPON CURRENT STANDARDS ERCOT PANHANDLE STUDIES INDICATE CERTAIN CONTINGENCIES CAN RESULT IN VOLTAGE SWINGS EXCEEDING 1.1 pu 2

CURRENT SITUATION CURRENTLY DEVELOPERS ARE CONTACTING VENDORS AND PERFORMING STUDIES TO DETERMINE THE ABILITY TO COMPLY WITH HIGHER HVRT REQUIREMENTS A NERC HVRT STANDARD (PRC-024) IS BEFORE FERC FOR FINAL APPROVAL; IF APPROVED, PRC-024 ALLOWS FOR A 5 YEAR PHASE IN 3

KEY ISSUES/QUESTIONS IT IS NOT CLEAR WHY THE CURRENT HVRT STANDARDS ARE NOT WORKABLE DEVELOPERS MAKE SIGNIFICANT COMMITMENTS WELL BEFORE THEY SIGN THE SGIA MAKING UNTIMELY CHANGES COSTLY THE COMPLETED TSP FISs IN THE PANHANDLE DO NOT INDICATE ANY VOLTAGE SWING PROBLEMS 4

KEY ISSUES/QUESTIONS UNDER WHAT CONDITIONS DO THE STUDIES INDICATE POSSIBLE PROBLEMS ARE THE MODELS CORRECT CHANGES TO STANDARDS MUST BE MADE WITH ENOUGH LEAD TIME TO ALLOW THE INDUSTRY TO RESPOND EFFICIENTLY NEW HVRT STANDARDS APPLIED TO THE POI ARE FAR MORE DEMANDING THAN HVRT STANDARDS APPLIED TO THE TURBINES 5

KEY ISSUES/QUESTIONS ANY CHANGES THAT ARE SHOWN TO BE NECESSARY AND EFFICIENT MUST BE PHASED IN ( PRC-024 ALLOWS FOR 5 YEARS FOR FULL IMPLEMENTATION ) IF NEED IS DEMONSTRATED ONLY IN THE PANHANDLE, THEN OTHER AREAS SHOULD NOT BE INCLUDED IN NEW STANDARDS IF NEED IS DEMONSTRATED THEN ALL TECHNOLOGIES IN THE PANHANDLE SHOULD BE INCLUDED, NOT JUST WGRs 6

KEY ISSUES/QUESTIONS COMPLIANCE EVALUATION CRITERIA NEED TO BE ESTABLISHED WHICH PROVIDE MODELING REQUIREMENTS AND ASSUMPTIONS TO BE USED BY DEVELOPERS/TSPs THRESHOLDS OF PANHANDLE DEVELOPMENT NEED TO BE ESTABLISHED WHERE THE HIGH VOLTAGE PROBLEMS FIRST APPEAR 7

WGR PROJECT DEVELOPMENT ACQUIRE LAND (LEASES) WIND SURVEY ERCOT INTERCONNECT REQUEST PRELIMINARY DESIGN CONTRACT FOR TURBINES/ WARRANTIES CONTRACT FOR CONSTRUCTION/WARRANTIES FINAL DESIGN FIS REQUEST CONTRACT FOR BOP CONTRACT FOR PPA/FINANCIAL HEDGES CONTRACT FOR BOP FIS COMPLETED FINAL DESIGN OBTAIN FINANCING SIGN SGIA POST SECURITY BUILD 8