Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.

Slides:



Advertisements
Similar presentations
Additional CREs to address Stability Limits Beth Garza TAC June 26, 2008.
Advertisements

Houston Region Import Capacity Project Planning for Reliable Power.
RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Regional Planning Group Project
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Navarro to Houston Presentation to ERCOT RPG August 27, 2013.
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
BRAZOS ELECTRIC COOPERATIVE Dobbin 345 Project David Albers, P.E. Manager – System Planning.
OPERATING IN THE EAGLE FORD SHALE
ERCOT PUBLIC 8/19/ LTSA Scenario Results Updates August, 2014.
California Energy Commission Workshop Nuclear Power Plant Issues
U.S. Transmission Capacity & Reliability Are we willing to do what it takes to preserve the transmission option? David R. Nevius - NERC.
ERCOT PUBLIC 4/21/ Loss of Load Probability Assessment for NERC April, 2015.
Houston Area Dynamic Reactive Project March 11,
Charles Hosken, General Manager Imperial Irrigation District
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
July 13, 2012 Transmission Needs Analysis Scenario 1 Update: BAU All Technologies.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
1 WMS Report To TAC September In Brief Four Working Group Reports Four Working Group Reports One Task Force Report One Task Force Report Three.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
Economic Planning Criteria Question 2 1/7/2011 Joint CMWG/PLWG Meeting March 4, 2011.
SM April Peak Week Operations Review Presentation to ISO Business Issues Committee May 22, 2002.
December 7, 2012 Transmission Needs Analysis Scenario 5/7 Update.
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
MISO Northwest Exploratory Study Presented to National Wind Coordinating Committee Participants in study – MISO, Various utilities in Minnesota, North.
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
Impacts of Environmental Regulations in the ERCOT Region Dana Lazarus Planning Analyst, ERCOT January 26, 2016.
Long Term Study Transmission Results May 21 st, 2013.
ESI Alternate Economic Study Process E-RSC Meeting October 21, 2010.
CREZ - Voltage Profiles on Series Compensated Lines Prepared by Paul Hassink with AEPSC ERCOT RPG, 11/11/11.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
Jeff Billo Manager, Transmission Planning
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
ERCOT – MISO DC Tie Study Comments
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC May 6, 2004 Transmission Services Ken Donohoo, Manager of System Planning Dan Woodfin,
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
December 14, 2007 RPG - CREZ Meeting CREZ Transmission Optimization Study: Update Warren Lasher ERCOT System Assessment.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Response to TAC Questions on PGRR031 TAC– January 28, 2014 Jeff Billo, ERCOT 1.
2006 Preliminary Reliability Study Results Bryan Guy September 7, 2006.
2016 LTSA Update Doug Murray 6/21/2016. Agenda Introduction Scenario Retirement Process Scenario Summary Results Appendix.
2008 Annual Five Year Plan Update 4 For RPG-CREZ Meeting 12/14/2007 Department of Regional Planning Harry Liu.
Houston Import Project – ERCOT Independent Review
Houston Import Study Update
Transmission Planning in ERCOT- Overview
2016 RTP Update November, 2016 RPG Meeting.
Warren Lasher Manager, Long-Term Planning and Policy
Presentation transcript:

Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013

Agenda Houston Import Needs Discussion GP&L/TMPA Affected Facilities – Existing N-H corridor Impact of N-H import/solution on Gibbons Creek Additional Considerations Transmission Options Studied Preferred Options

Houston Import Needs Discussion Base case reliability need observed for Houston import for 2018 Thermal overloads under N-1 + G-1 conditions observed to be key drivers for the reliability need N-H transfer levels modeled at 3100 MW for the 2018 study case Houston Import reliability needs and long-term effectiveness of proposed solutions sensitive to the following N-H transfer levels Generation availability within Houston and along the N-H import path Long term Houston load deliverability may require significant re-conductor and/or upgrades of existing N-H corridors Important consideration when evaluating feasibility of import options

GP&L/TMPA Affected Facilities – Existing N-H Corridor Significant history of anticipated congestion on existing N-H corridors across various ERCOT Houston Import study efforts ERCOT Houston Import Study Update (April 2010) – “2014 benchmark case showed heavy congestion on Singleton-Zenith 345-kV line for the contingency loss of Roans Prairie-Kuykendahl/ Singleton-Tomball 345-kV double circuit. Congestion also observed on Jewett-Singleton and Twin Oak-Jack Creek 345-kV lines” ERCOT 2012 Long Term Study (LTS) – Scenarios of Interest from Houston Import standpoint Scenario #2: Base with All Tech and Retirements (retirement of legacy natural gas-fired generators) Scenario #3: Base with All Tech and Incremental Wind

GP&L/TMPA Affected Facilities – Existing N-H Corridor Significant history of anticipated congestion on existing N-H corridors across various ERCOT Houston Import study efforts (Contd.) ERCOT 2012 Long Term Study (LTS) – Scenarios of Interest from Houston Import standpoint Scenario #5-a: Drought Scenario Summer capabilities of existing water – consuming resources de-rated Increased peak load Scenario #7: BAU – Hi Natural Gas Characterized by a high natural gas price ($9.55 by 2016, $13.7 by 2022) Resources retire in 2018 and 2022 for competitive reasons

GP&L/TMPA Affected Facilities – Existing N-H Corridor Estimated Congestion Costs, N-H Constraints, ERCOT LTS Effort Source: ERCOT DOE Long Term Study (ERCOT POI Site)

GP&L/TMPA Affected Facilities – Existing N-H Corridor Houston Import, Congested Elements, ERCOT LTS Effort

GP&L/TMPA Affected Facilities – Existing N-H Corridor 2015 & 2017 Projected Economic Constraints, ERCOT C&N Report 2012 (Source: ERCOT 2012 Constraints & Needs Report)

GP&L/TMPA Affected Facilities – Existing N-H Corridor All ERCOT Houston Import evaluations indicative of significant anticipated congestion on existing N-H corridor Two key GP&L/TMPA facilities part of the congestion constraints 345kV Gibbons Creek – Twin Oak 345kV Gibbons Creek - Singleton Avoiding congestion (and overloads) on existing N-H corridors will provide significant cost savings to Houston region Provides significant economic benefits to any Houston reliability project Prevent the need to take additional outages to re-conductor 345kV lines along an already congested N-H corridor Critical aspect to be taken into account when evaluating import project options

Houston Import – Impact on TMPA/GP&L Facilities Need to alleviate congestion/potential overloads on TMPA/GP&L transmission facilities in existing N-H corridor as part of Houston Import Need to ensure that potential Houston import solutions divert enough power from existing N-H corridors Looping N-H projects via intermediate stations South – Houston projects with large enough transfer capability to offset flows from the north Direct solutions with series compensation Transmission solutions looped through existing TMPA facilities may exacerbate over-voltage issues under light load conditions TMPA RPG approved project for 130-150 MVAR reactor on 345kV Gibbons Creek expected to address this issue

Additional Considerations Recent history of Gibbons Creek unit being requested to provide VAR support during high N-H transfer levels (at the cost of active power to TMPA member cities) Gibbons Creek unit exempt from PRR830 requirements Gibbons location significantly strong with little ability of external reactive equipment impacting voltage downstream Optimal approach would be to reduce impedance between Gibbons & Houston thereby improving voltage conditions in the region Ability to reduce the “N-1” impact created by the proposed solution itself Important to ensure that the proposed solution does not become the single largest contingency for Houston import Utilize existing infrastructure and expansion capability to reduce the reliability impact for the outage of the proposed option

Transmission Options Studied (Source: CTT/GP&L Houston Import RPG Submission)

Preferred Options Preferred Options, Houston Import Study (Source: CTT/GP&L Houston Import RPG Submission)

Preferred Options Test Project 2022 capital cost ($M) Reliability benefit of test project ($M) Capital Cost Adjusted for Reliability Benefit ($M) Production Cost Savings ($M) 1/6 of Capital Cost ($M) 1/6 of Adjusted Capital Cost ($M) Meet ERCOT Economic Criteria ? Limestone-Gibbons Creek-Zenith 268.4 120.6 147.8 36.6 44.7 24.6 Yes Watermill-Big Brown 208.2 23.1 185.1 0.1 34.7 30.9 No Lake Creek – Navarro 104.1 42.1 62.0 1.7 17.3 10.3 Lake Creek – Watermill 297.4 19.0 278.4 0.4 49.6 46.4 Clear Spring - Hill County 0.0 4.1 17.4 Hays - Kendall second 345kV circuit 41.8 3.2 7.0 Sandow - Garfield 133.8 4.0 22.3 ERCOT LTS Scenario 3, 2022 Economic Project Assessment

Preferred Options 345kV Limestone – Gibbons Creek - Zenith Most optimal performing option in terms of incremental Houston import capability vs project cost (across options providing greater than 2500 MW Houston import capability) Houston import capability observed to be as high as 3000 MW with MLSE upgrades on TMPA N-H facilities Virtually no need to upgrade existing N-H corridor to achieve import capability Flexibility to achieve close to 3500 MW Houston import capability with upgrades on N-H corridor in long term Deemed economic via the ERCOT LTS Study for 2022 (S3) with significant reliability benefits ($121M) Provide all the benefits stemming from Gibbons Creek – Zenith Limestone provides access to significant generation in the North

Preferred Options 345kV Gibbons Creek – Zenith Provides close to 2000 MW of Houston import capability at significantly high MW/$M Requires comparatively less upgrades on existing N-H corridor to achieve Houston import capability level 345kV Gibbons Creek – Tomball Provides close to 2200 MW of Houston import capability at significantly high MW/$M May require reactive equipment enforcements in the long term to result in Houston import levels greater than 3000 MW

Questions/Discussion