SPP’s 2013 Energy Consumption and Capacity 2 12% annual capacity margin requirement CapacityConsumption Total Capacity 66 GW Total Peak Demand 49 GW.

Slides:



Advertisements
Similar presentations
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
Advertisements

Public Service Company of New Mexico
Clean and Affordable Energy Future in Northwest U.S. Nancy Hirsh NW Energy Coalition October 1, 2014.
Update on EPA Activities MOPC July 15-16, Current Known Impacts –Retirements –De-ratings –Outage Impact Studies Proposed Clean Power Plan 2 Topics.
Ad Hoc West-wide Resource Assessment Team (WRAT) : Assessment of Western System Adequacy in the Short-term Jeff King Northwest Power Planning Council Presentation.
Reliability Risks and Lessons Learned In The Wake Of The Polar Vortex OPSI Annual Meeting October 14, 2014.
PJM© PJM as Part of the Eastern Interconnection KEY STATISTICS PJM member companies 750+ millions of people served 60 peak load in megawatts.
1.  Purpose  To present Staff’s Preliminary Findings on the 2012 Integrated Resource Plans of:  APS – Arizona Public Service Company  TEP – Tucson.
Congestion Management in a Market Environment 2 nd CIGRE / IEEE PES International Symposium San Antonio, Texas October 5, 2005 Kenneth W. Laughlin.
WECC PCC Meeting Salt Lake City, UT March 26, 2014.
WECC PCC Meeting Salt Lake City, UT July 16, 2014.
Susan Covino Senior Consultant, Emerging Markets March 31, 2015
Clean Air Act Section 111(d) Indiana Energy Association September 11, 2014 Thomas W. Easterly, P.E., BCEE Commissioner IN Department of Environmental Management.
California Energy Commission Workshop Nuclear Power Plant Issues
WGG Coal Retirement Case Transmission Repurposed for Renewables.
Energy Business Solutions Michigan IRP Working Group Meeting June 10, 2005.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
GE Energy Asia Development Bank Wind Energy Grid Integration Workshop: Issues and Challenges for systems with high penetration of Wind Power Nicholas W.
1 Transmission Development at Ameren and in the Midwest ISO Mid-America Regulatory Conference Maureen A. Borkowski June 8, 2010.
Electric Generation Reliability Remarks Before the Pennsylvania Public Utility Commission 2011 Summer Reliability Assessment Meeting June.
ERCOT PUBLIC 4/21/ Loss of Load Probability Assessment for NERC April, 2015.
SPP.org 1. SPP: Demand Response and Advanced Metering in Arkansas.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
Electric Reliability and the Clean Power Plan Branden Sudduth Director, Reliability Planning W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Overview of the North American and Canadian Markets 2008 APEX Conference in Sydney, Australia October 13, 2008 Hung-po Chao Director, Market Strategy and.
Highlights of AESC 2011 Report Vermont Presentation August 22, | ©2011 Synapse Energy Economics Inc. All rights reserved.
1 New England Demand Response Resources: Present Observations and Future Challenges Henry Yoshimura Demand Resources Department ISO New England, Inc. Holyoke,
Liberalization of Electricity Market in Taiwan Su, Jin-sheng Energy Commission Ministry of Economic Affairs August 8, 2001.
Update - RTOs and Capacity January 28, Purpose of Presentation Update the Commission on issues related to – (1) Ameren Missouri – potential Local.
Texas Wind Energy American Meteorological Society Summer Community Meeting – Norman Oklahoma Henry Durrwachter, P.E. August 12, 2009.
Preliminary Results with the Regional Portfolio Model Michael Schilmoeller for the Northwest Power and Conservation Council Generation Resource Advisory.
Clean Air Act Section 111(d) Indiana State Bar Association Utility Law Section September 4, 2014 Thomas W. Easterly, P.E., BCEE Commissioner IN Department.
ISO Outlook Summer 2005 and Beyond Senate Energy, Utilities and Communications Committee February 22, 2005 Jim Detmers Vice President of Grid Operations.
K E M A T & D C O N S U L T I N G Power System Conference, Clemson, South Carolina, March 8-11, 2005 Principles and Issues Relating to the Interconnection.
Page 1© 2009 Quanta Technology LLCPage 1 November 2007 BGE January 4, 2008 Strategic Midwest Area Renewable Transmission (SMART) Study October 06, 2009.
EPA’s Proposed Clean Power Plan House Committee on Natural Resources and Environment February 12, 2015 Tegan B. Treadaway Assistant Secretary Office of.
RELIABILITYFIRST CORPORATION Long Term Resource Assessment 2010 – 2019 Board of Directors Meeting September 30, 2010 Presented by Jeff Mitchell.
PJM©2015 ATTACHMENT TO TESTIMONY OF ANDREW OTT OHIO ENERGY MANDATES STUDY COMMITTEE MARCH 18,
TOP and BA Responsibilities SPP Wind Workshop May 30, 2013.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
Power Association of Northern California Maintaining Grid Reliability In An Uncertain Era May 16, 2011 PG&E Conference Center Jim Mcintosh Director, Executive.
2006 SPP RTO Expansion Plan Carl A. Monroe July 30, 2006.
Puerto Rico Electric Power
Long Term Study Scenarios and Generation Expansion Update October 12, 2012.
Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
Southern California Edison The San Onofre Nuclear Generating Station April 14, 2011.
Monterey Plaza Hotel October 8-10, 2007
Environmental Benefits of Renewable Portfolio Standards in an Age of Coal Plant Retirements September 10 th, 2015 Energy Policy Research Conference Denver,
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Updated 1/28/2011. Renewables Integration Plans and Challenges March 8, 2011 Jay Caspary ·
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016.
Coordinated Planning Concept (For Discussion Only) revised 11/30/04 07/01/04.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
SERC Reliability Corporation 1 SERC RELIABILITY CORPORATION MID-AMERICA RELIABILITY CONFERENCE June 21, 2006 COLUMBUS, OHIO.
ISO Confidential Overview of California’s Current Drought and its Effects on the Energy System Dede Subakti, P. E. Director, Operations Engineering Services.
Planning the Networked Grid Transmission Planning J.E.(Jeff) Billinton Manager, Regional Transmission - North Building the Networked Electricity Grid –
Clean Power Plan EW Tim Wilson Director of Energy Supply Services.
Sixth Northwest Conservation & Electric Power Plan Draft Wholesale Power Price Forecasts Maury Galbraith Generating Resource Advisory Committee Meeting.
Regional Implications of the Clean Power Plan Lanny Nickell Midwest Energy Policy Conference October 6 th,
The Midwest ISO – Platform to Meet Tomorrow’s Challenges Wisconsin Industrial Energy Group August 7, 2008.
I-5 Corridor Reinforcement Project
Evolving Economic Dispatch in SPP
Transmission Planning at PJM Interconnection LLC
Key Findings and Resource Strategy
About Dominion: One of America’s Leading Energy Companies
New England Electricity Restructuring Roundtable September 18, 2009
Jim Mcintosh Director, Executive Operations Advisor California ISO
Presentation transcript:

SPP’s 2013 Energy Consumption and Capacity 2 12% annual capacity margin requirement CapacityConsumption Total Capacity 66 GW Total Peak Demand 49 GW

SPP’s Operating Region 3 Current 77,366 MW of generating capacity 46,136 MW of peak demand 48,930 miles transmission: ⁻69 kV – 12,569 miles ⁻115 kV – 10,239 miles ⁻138 kV – 9,691 miles ⁻161 kV – 5,049 miles ⁻230 kV – 3,889 miles ⁻345 kV – 7,401 miles ⁻500 kV – 93 miles Future (October 2015) Adding 3 new members (WAPA, BEPC, and HCPD) + 5,000 MW of peak demand + 7,600 MW of generating capacity 50% increase in SPP’s current hydro capacity

SPP’s Current Coal Status for 2018 Derated Capacity Retired Capacity Remaining Capacity LEGEND

Goals for States in SPP *Includes Future States with IS Generation in SPP (N. Dakota, S. Dakota, Montana, and Wyoming) Fossil Unit CO2 Emission Rate Goals and Block Application (lbs/MWh) SPP State Average 2012 Rate = 1,699 SPP State Average 2030 Rate = 1,045

6 % Emission Reduction Goals for States in SPP *Includes Future States with IS Generation in SPP (N. Dakota, S. Dakota, Montana, and Wyoming) Total CO 2 Emission Reduction Goals (%) Average of SPP States = 38.5%

7 NGCC Capacity Factors (For SPP and Select Neighboring States)

8 EPA’s Renewable Energy Assumptions (For SPP and Select Neighboring States)

Initial analysis requested by SPP’s Strategic Planning Committee –Reliability analysis –Use existing ITP 2024 models –Model EPA’s projected EGU retirements –Replace retired EGUs with a combination of increased output from existing CCs, new CCs, Energy Efficiency, and increased renewables (with input from member utility experts) –Assessment underway, initial results expected week of August 18 th SPP’s Regional State Committee requested analysis comparing both individual state and regional approaches –Will discuss approach during their August 25 th conference call 9 SPP’s CPP Impact Assessments

10 EPA Projected EGU Retirements (For SPP and Select Neighboring States) *Extracted from EPA IPM data **THESE RETIREMENTS ARE ASSUMED BY EPA – NOT SPP!

11 EPA’s Projected EGU Retirements (For SPP and Select Neighboring States) *Excludes committed retirements prior to 2016 **Extracted from EPA IPM data ***THESE RETIREMENTS ARE ASSUMED BY EPA – NOT SPP!

Before considering the impacts of contingencies, preliminary results indicate increased thermal overloads and low voltages due to EPA’s assumed retirements Summer peak cases are not solving under single contingency Indicative of significant low voltages due to lack of reactive support Remaining steps to be taken Continue to take steps to get all cases to solve and note what steps were required Determine the amount of reactive support required to maintain reliable voltages Identify the number and significance of overloads and low voltages that would have to be solved to comply with NERC Standards 12 SPP Reliability Impact Assessment Results

Used current load forecasts supplied by SPP members, currently planned generator retirements, currently planned new generator capacity with GIAs, and EPA’s assumed retirements SPP’s minimum required reserve margin is 13.6% By 2020, SPP’s anticipated reserve margin would be 5.0%, representing a capacity margin deficiency of approximately 4,500 MW By 2024, SPP’s anticipated reserve margin would be -3.8%, representing a capacity margin deficiency of approximately 10,000 MW Out of 14 load serving members assessed, 9 would be deficient by 2020 and 10 by SPP Reserve Margin Assessment

SPP is responsible to FERC and NERC –Required to ensure reliability and perform in accordance with tariff –Rules, behavior, pricing, and revenue distribution are subject to FERC approval –Penalties may be levied by FERC/NERC for failure to comply (up to $1 MM/day/violation) SPP operates regional security-constrained, economically dispatched markets –Considers both reliability and economics –Generation dispatch provides reliable and economic solutions to needs over a multi-state area SPP plans and directs regional transmission construction –Addresses expected reliability, economic, and public policy needs –Generator interconnection and transmission service must be requested of SPP and processed by SPP –Takes up to 8.5 years to perform applicable planning processes and construct transmission upgrades 14 State Plans Need to Consider the Following

Transmission Build Cycle 15 GI Study (12 mo.) NTC Process (3-12 mo.) Construction (2-6 yr.) Construction (2-6 yr.) Planning Study (12-18 mo.) TS Study (6 mo.) NTC Process (3-12 mo.) Construction (2-6 yr.) Construction (2-6 yr.) 3 ¼ yr.8 ½ yr. 3 ½ yr. 8 ½ yr. Transmission Planning Process GI and Transmission Service Process

Lanny Nickell Vice President, Engineering