February 25, 2011 Demand Side Working Group EILS Update Mark Patterson ERCOT, Manager Demand Integration.

Slides:



Advertisements
Similar presentations
GPA Renewable Energy Resource for Guam Power Authority
Advertisements

ERCOT Update on PUCT Posting changes DEWG Meeting 11/27/07 Matt Mereness.
ERS Update Presented to: Demand Side Working Group December 5, 2014.
Recent ERCOT Events Lessons Learned
ERCOT Emergency Load Response Sam Jones Paul Wattles Steve Krein PUC Demand Response Workshop Sept. 15, 2006.
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
Hurricane Rita. 2 ERCOT Preparation ERCOT started alerts to QSEs and TOs on 9/21 Did a site failover of EMMS system Austin Taylor Procured satellite voice.
Retail Market Subcommittee Update to TAC Kathy Scott April 24,
NPRRs NPRR680 Allow QSEs to Self-Arrange AS Quantities Greater Than Their AS Obligation. This Nodal Protocol Revision Request (NPRR) proposes to allow.
ERS Update for DSWG June 1, Agenda June – September 2012 Procurement XML Project Update Clearing Price discussion NPRR 451 Q & A.
H.B. “Trip” Doggett President and Chief Executive Officer Review of February 2, 2011 Energy Emergency Alert (EEA) Event Special Board of Directors Meeting.
ERS Procurement Methodology 09/04/2013 ERS Workshop Presented By: ERCOT Staff.
Presented By: Mark Patterson ERCOT Manager, Demand Integration November 29, Minute ERS Pilot update to TAC 1.
NPRR 365 Change in Resource Outage Approvals from 8 to 45 or 90 Days Woody Rickerson Director Grid Coordination
1 Welcome to Load Participation Orientation Elev MenWomen Phones Info Presentation and other Load Participation information will be posted at:
March 26, 2015 Technical Advisory Committee (TAC) Update to RMS Kathy Scott April 7, 2015 TAC Update to RMS 1.
NPRR514, Seasonal Generation Resource Wholesale Market Subcommittee April 12, 2013 Amanda Frazier.
EILS Update DSWG ERCOT Staff October 9, EILS Update to DSWGOctober 9, 2009 Contents Procurement results: Current & historical Price comparison:
Lead from the front Texas Nodal 1 Texas Nodal Load Frequency Control (LFC) EDS 3 Release 6 - Handbook EDS 3 Release 6 MP Planning.
Demand Integration Update to DSWG ERCOT Emergency Responsive Service (ERS) Report to the Public Utility Commission of Texas for the 2013 ERS Program Year.
Section 5.9 – added export language Each ERS Generator site must have an interconnection agreement with its TDSP prior to submitting an ERS offer and must.
Retail Market Subcommittee Update to COPS Kathy Scott May 13,
ERS Update Plus Revisions to Proposed Changes for ERS Time Periods Presented to: Demand Side Working Group November 5, 2014.
ERCOT Staff Demand Integration Update to DSWG 3/08/2013 DSWG Meeting.
Protocol Revision Subcommittee Sandy Morris November 3, 2011.
ERCOT Emergency Interruptible Load Program Paul Wattles Steve Krein WMS Oct. 13, 2006.
Weather Sensitive ERS Training Presenter: Carl Raish Weather Sensitive ERS Training Workshop April 5, 2013.
EECP External Communications ERCOT Governmental Relations & Communications COPS June 27, 2006.
ERCOT Emergency Interruptible Load Service Customer & Stakeholder Workshops July 2007.
Page 1 of 13 Texas Regional Entity ROS Presentation April 16, 2009 T EXAS RE ROS P RESENTATION A PRIL 2009.
Final Report Weather Sensitive Emergency Response Service (WS ERS) Pilot Project Carl Raish, ERCOT Technical Advisory Committee November 7, 2013.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee May 4, 2007.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
ERS Update – DSWG Presentation September 21, 2012.
Outage Scheduler Transition Plan Kenneth Ragsdale NATF.
Emergency and Other Event Communications ERCOT Board of Directors Richard Gruber, Director of Market Services Paul Wattles, Manager, Governmental Relations.
1 EILS Technical Workshop 2.0 February 16, Agenda  Introduction  June – September 2010 Procurement Schedule  EILS Submission Form  Review.
PRR 705 ERCOT Emergency Interruptible Load Service PRS January 22, 2007.
Overview of Governing Document for Weather-Sensitive ERS Pilot Project Stakeholder Workshop Mark Patterson, ERCOT Staff March 1, 2013.
DSWG Update to WMS 2/9/2011. EILS Procurement Results from 1/31 Business Hours 1 HE 0900 through 1300, Monday thru Friday except ERCOT Holidays; 425 hours.
RMS Update to TAC November 1, RMS Activity Summary RMGRR057, Competitive Metering Working Group Name Change (VOTE) Update on RMS Working Group and.
Lead from the front Texas Nodal 1 High-Level Overview of draft NPRR implementing PUCT Rule Posting Requirements January 8,
Operations Update ERCOT Board Meeting March 18, 2003.
Profiling Working Group 1 PWG Update Report By Ernie Podraza of Direct Energy ERCOT PWG Chair Ed Echols Of Oncor ERCOT PWG Vice Chair for COPS Meeting.
ERCOT Update on Day-Ahead Extract and other PUCT Posting changes DEWG Meeting 10/29/07 Matt Mereness.
Emergency Interruptible Load Service Paul Wattles ROS Subgroup Feb. 7, 2006.
Operations Update Kent Saathoff TAC Meeting March 6, 2003.
Update: 30-Minute Emergency Response Service (ERS) Pilot Project Mark Patterson, ERCOT October 7, 2013.
Current Stakeholder Timelines for Emergency Issues May 6, 2008 TPTF.
H.B. “Trip” Doggett President and Chief Executive Officer Review of February 2, 2011 Energy Emergency Alert (EEA) Event Emergency Event Coordination Workshop.
Transition Plan Network Operations Model Change Requests 5/26/2010.
June 26 and July 31, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott August 5, 2014 TAC Update to RMS 1.
1 TAC Report to the ERCOT Board July 18, TAC Summary 4 PRRs for approval (3 unanimous) 4 PRRs for approval (3 unanimous) 5 Nodal PRRs for approval.
July 15, 2011 Reliability Deployments Task Force Meeting ERCOT Studies and Proposal on Reliability Energy Pricing John Dumas Director Wholesale Market.
NPRRs 705NPRR Provides Consistency for References to the End Date of the Generation Interconnection Process. In the Resource Interconnection Handbook,
Energy Emergency Alert (EEA) UPDATE F EBRUARY 8, 2011.
TPTF Update Trip Doggett TAC March 9, TPTF Update Meetings February 6 & 7, February 20 Attendance approximately 40 Completed review of ERCOT’s clarification.
1 Market Trials Update NATF January 5, 2010.
Weather-Sensitive ERS Pilot Project Proposal March 7, 2013 TAC Meeting.
Draft NPRR Weather Sensitive ERS Loads December 2012.
February 26, 2015 Technical Advisory Committee (TAC) Update to RMS Kathy Scott March 3, 2015 TAC Update to RMS 1.
Texas Nodal Program ERCOT Readiness & Transition (ERT) Supplemental Information TPTF January 12, 2009 Kevin Frankeny.
Technical Advisory Committee Commercial Operations Subcommittee Update to TAC Debbie McKeever COPs Chair 2011.
EILS Update Paul Wattles, ERCOT Staff DSWG Meeting April 29, 2011.
ME 3.0 to ME 5.0 ME3.0 review scheduled during the Joint NDSWG/NATF meeting in July. There were approximately 180 comments on the ME3.0 paper. Deadline.
UFLS Survey Explanation
Hurricane Rita.
Pilot Project Concept 30-Minute Emergency Response Service (ERS)
Pilot Project Concept 30-Minute Emergency Response Service (ERS)
CEO Report Thomas F. Schrader ERCOT Board of Directors May 17, 2005
Presentation transcript:

February 25, 2011 Demand Side Working Group EILS Update Mark Patterson ERCOT, Manager Demand Integration

Demand Side Working GroupFebruary 25, 2011 February through May 2011 Procurement

February 2011 Business Hours 1

February 2011 Business Hours 2

February 2011 Business Hours 3

February 2011 Non-Business Hours

Procurement Trends (no. & avg. size of EILS Loads) EILS Loads include individual Loads and aggregations February 2011

Individual Site Participation Cumulative number of unique sites in EILS ID process February 2011

Demand Side Working GroupFebruary 25, 2011 February 2, 2011 Event

3:00am5:08am5:17am 5:43am9:05am ERCOT experienced communications challenges due to the rapidly-unfolding events J AN 31 F EB 1F EB 2 Issued OCN and Advisory Severe Weather Reserves below 3000 MW PUCT 3:21am Issued Watch Reserves Below 2500 MW Sent to Grid Alert List Issued OCN Winter Storm Warning PUCT a.m. Issued EEA Level 2A Reserves Below 1750 MW Sent to Grid Emergency List Issued EEA Level 3 Rotating Outages Sent to Grid Emergency List PUCT 6:05am 2:45am Issued Advisory Freezing Temperatures PUCT Report 3:05p.m. Issued OCN Operating Condition Notice Expected Freezing Temperatures PUCT OCN and Watch also include: Qualified Scheduling Entity Hotline Call Transmission Owner Hotline Call Postings on the Market Information System and ERCOT website

5:20am5:08am 7:15pm 1,804 MW Non-Spin deployed Restored 500 MW Restoration Complete A timeline of the emergency steps that were taken leading to rotating outages in ERCOT F EB 2 F EB 3, 10 AM EEA 2A ENDS & EILS RECALLED Issued Watch Reserves below 2,500 MW Issued EEA 2A Reserves below 1,750 MW Load Resources deployed Issued EEA 3 EILS deployed Firm Load Shed 1,000 MW 7:57am Restored 500 MW (3,500 MW out) 8:22am Restored 500 MW (3,000 MW out) 9:25am Restored 500 MW (2,500 MW out) 5:43am 6:04am Firm load shed 1,000 MW (2,000 MW total) 6:05am Frequency Hz 6:23am Firm Load Shed 2,000 MW (4,000 MW total) 6:59am Media Appeal issued Move to EEA 2B From EEA 3 New winter Peak Record 56,480 MW 2:01pm 11:39am Restored 500 MW (2,000 MW out) 12:04pm Restored 500 MW (1,500 MW out) 12:25pm Restored 500 MW (1,000 MW out) 12:49pm Restored 500 MW (500 MW out) Load Resources Recalled Move to EEA 2A From EEA 2B 3:14pm 4:30am1:07pm 1:57pm

The ERCOT System responded as expected

Demand Side Working GroupFebruary 25, 2011 New EILS Contract Period (RFP)

Demand Side Working GroupFebruary 25, 2011 New EILS RFP Today ERCOT will be filing a Petition for Emergency Rulemaking with the Public Utility Commission Subst. R (a)(2): – (2)Notwithstanding the foregoing, ERCOT may restructure the contract periods to facilitate additional load participation in EILS. ERCOT must publicly announce any changes to the contract period schedule described above at least 90 days prior to the next contract period start date. Petition will seek to remove the 90-day advance notice requirement

Demand Side Working GroupFebruary 25, 2011 This EILS RFP is provisional and this procurement may be cancelled by ERCOT at any step in the process prior to notification of awards. A decision by ERCOT to proceed with the procurement will be contingent on factors including but not limited to the following: – Approval by the Public Utility Commission of Texas (PUCT) of a change to PUCT Substantive Rule § (a)(2), – May require Approval by the ERCOT Board of Directors of a waiver of Nodal Protocols Section (2), – EILS MW capacity offers that are determined by ERCOT to be both sufficient to provide a viable operational tool for ERCOT to deploy in an Energy Emergency Alert and priced consistent with the reasonableness criteria

Demand Side Working GroupFebruary 25, 2011

Demand Side Working GroupFebruary 25, 2011 The Change Control process for the Technical Requirements and Scope of Work for the new Contract Period will be modified as follows: – the Market Participant review period for changes to the document will be less than 14 days. Otherwise the Change Control process will not change. GUIDELINES FOR New EILS PROCUREMENT

Demand Side Working GroupFebruary 25, 2011 QSEs may submit new EILS Loads or reconfigured aggregated EILS Loads to ERCOT for consideration using the EILS Load Identification (ELID) process as defined and adhering to the ELID deadlines set forth in the procurement schedule. GUIDELINES FOR New EILS PROCUREMENT (Cont’)

Demand Side Working GroupFebruary 25, 2011 QSEs may submit offers for the following: – EILS Loads assigned an ELID number through the process described in No. 2, above. – EILS Loads with valid, numbered ELIDs and baseline assignments from the original Feb.-May 2011 Contract Period procurement cycle. – EILS Loads with valid Reinstatement ELIDs that have successfully completed their reinstatement test and for which the suspension period has expired or will expire prior to April 1, Standard parameters relating to reinstatement offers apply. – Substituting EILS Loads that were providing EILS at the time of the Feb. 2-3 EILS deployment event. GUIDELINES FOR New EILS PROCUREMENT (Cont’)

Demand Side Working GroupFebruary 25, 2011 GUIDELINES FOR New EILS PROCUREMENT (Cont’) Availability and event performance will be evaluated independently of the original Feb.-May Contract Period.

February 25, 2011Demand Side Working Group Draft2 PROCUREMENT SCHEDULE Contract Period: April 1, 2011 through May 31, 2011 All deadlines are close of business U.S. Central Prevailing Time. DateAction Fri., Feb. 25, 2011 RFP ISSUED: ERCOT issues EILS Request for Proposal. Draft Technical Requirements & Scope of Work posted to EILS web page. EILS Load ID process begins — submittal of Resources for baseline assignment & capacity pre-screening Fri., Mar. 4, 2011ELID process closes (last day to submit ELIDs for new Loads. Mon., March 7, 2011Online meeting review of Technical Requirements comments (if requested). Fri., March 11, 2011 ERCOT communicates to QSEs completed baseline assignment and capacity pre- screening information for prospective EILS Loads. Mon., March 14, 2011 QSEs opting for EILS Self-Provision submit the EILS Notification of Self-Provision Form to ERCOT. Fri., March 18, 2011 OFFERS DUE: QSEs submit EILS Submission Forms with completed competitive Offers and/or Self-Provision Offers. ERCOT notifies Self-Providing QSEs of options for adjusted commitment levels. Tue., March 22, 2011 Self-Providing QSEs provide ERCOT with final Self-Provision commitment (this must occur within two Business Days of the communication to the QSE from ERCOT). Wed., March 24, 2011 ERCOT notifies awarded QSEs of EILS awards. ERCOT issues Market Notice with summary of EILS awards. Standard Form Supplements to QSE Agreements distributed to awarded QSEs. Wed., March 30, 2011Deadline for signed contracts to be returned to ERCOT. Fri., April 1, 2011First day of operation in the Contract Period. Tue., May 31, 2011Last day of Contract Period Tue., July 5, 2011Deadline for submitting NOIE or non-TDSP interval meter data to ERCOT Fri., July 15, 2011ERCOT provides unofficial availability and event performance data to QSEs Mon., July 25, 2011Deadline for QSEs to identify any discrepancies with ERCOT’s unofficial data Tue., Aug. 9, 2011Approximate Settlement statement posting date for this Contract Period