KING FAHD UNIVERSITY OF PETROLEUM & MINERALS DHAHRAN, SAUDI ARABIA Construction Engineering & Management CEM-520 CHANGE ORDERS IN CONSTRUCTION PROJECTS.

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

Construction Contracting
FACTORS AFFECTING CONSTRUCTION COSTS IN SAUDI ARABIA By Yaser Abdulla Al-Juwairah Presented by Shaikh Imran Abdul Qayyum Gani.
Project Procurement Management
Field Orders on Construction Contracts Guidance Document CLC-8 May 13, 2013.
ABC Change Orders College of Environmental Design
Presented by: Fouad Al-Malazi ID No.: Managing Construction Contracts By Robert D. Gilbreath Chapter 1 CONSTRUCTION CONTRACTS: Roles and Relationships.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
King Fahd University Of Petroleum and Minerals Construction Engineering and Management CEM520 Construction Contracting and Administration Term Paper Contract.
Joint Ventures in Construction Firms in Saudi Arabia By Kamal Khalil Khairaddin Abbasi A thesis paper summary Summarized by Mahdi Fida Al-Adel.
Presentation for Thesis of Master Degree Done by Ali Abdullah Al Salman CEM – 520 Term Project (Paper Presentation) Assessments of Risk Management Perception&
Marcy Mealy Procurement Specialist CDBG Program
Copyright Course Technology Chapter 11: Project Procurement Management.
Project Cost Management Estimation Budget Cost Control
Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007.
King Fahd University of Petroleum and Minerals Department of Construction Engineering and Management CEM Instructor: Dr. Soliman Al-Mohawis Important.
Determination of Construction Contract Duration for Public Projects in Saudi Arabia By: Ahmed Saleh Al-Sultan, June 1989 Presented by Sameh Elish January.
KFUPM, Department of Construction Engineering and Management CEM 520 LIABILITY ALLOCATION AMONG THE PARTIES TO FIXED-PRICE CONSTRUCTIN CONTRACTS IN SAUDI.
THE PROJECT TEAM TYPICAL REQUIREMENTS AND RESPONSIBILITIES OF THE PROJECT TEAM TRADITIONAL TEAM ORGANIZATION AND VARIATIONS THE OWNER’S TEAM THE DESIGN.
PROCEDURES FOR SELECTING THE CONTRACTOR
Chapter 3 Preparing and Evaluating a Research Plan Gay and Airasian
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
Abdallah M. Al-Mahasheer
Construction Engineering 221 Drawings and Specifications.
Chapter 2 A Strategy for the Appraisal of Public Sector Investments.
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
Construction Engineering 221 Cost Estimating and Bidding.
CONTRACT DOCUMENTS DISCREPANCY IN THE ROYAL COMMISSION BUILDING PROJECTS AT JUBAIL By: AHMAD SAID AE-KHAMIS CEM 520 Presented by Abdul-Mlik M Al-Saeed.
WELCOME TO THE PROCUREMENT SEMINAR Procurement and Contracts An Overview of Contract Administration.
Auditing Standards IFTA\IRP Audit Guidance Government Auditing Standards (GAO) Generally Accepted Auditing Standards (GAAS) International Standards on.
1 Construction Claims in Residential Houses in Saudi Arabia Presented by Adel Al Rabee.
CEM 520: Construction Contracting and Administration 03 June 2007
What is Business Analysis Planning & Monitoring?
Audit of Public Procurement
November, 2000 Slide 1 Project Services Division RISK MANAGEMENT Project Services Division Presentation By: Adam Malkhassian November, 2000.
An-Najah National University Graduating project II Delay in construction projects.
Technical Manager; Bechtel Oil, Gas & Chemicals.
1 MAINTENANCE EFFICIENCY THROUGH DIRECT LABOR OR MAINTENANCE CONTRACTS BY Al-Hammad, A., and Al-Otaibi, G. College of Environmental Design King Fahd University.
Delay In Construction Project In West Bank. Outline:  Background.  Research objective & methods.  Important factors that cause time and cost overrun.
Purchasing Policy and Procedures Chapter 3. The Term “Policy”  Refers to set of purposes, principles, and rules of action that guide an organization.
Chapter 12 Evaluating Products, Processes, and Resources.
King Fahd University of Petroleum & Minerals
CON 4003 CVE 4073/5073 Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Chapter 11: Project Procurement Management
CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.
1 CONTRACTING. 2 WHAT IS CONTRACTING ? CONTRACTING IS BASICALLY AN AGREEMENT BETWEEN TWO PARTIES, ONE CALLED THE CONTRACTING PARTY AND THE OTHER THE CONTRACTED.
CEM CEM – 520 Measuring the Effectiveness of Materials Management for Industrial Construction Projects in Saudi Arabia Thesis By Ali Al-Darweesh.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
OVERHEAD COSTS IN BUILDING CONSTRUCTION IN SAUDI ARABIA Author: Mohammad Al-Shahri (1997) Presented By Fawaz Al-Ghamdi January 1, 2005.
UNIVERSITY OF DAR ES SALAAM t Selection and Employment of Consultants Negotiations with Consultants; Monitoring Performance of Consultants; Resolving Disputes.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
Small Purchase of Professional Service Providers Administrative Rule R
Assistant Instructor Nian K. Ghafoor Feb Definition of Proposal Proposal is a plan for master’s thesis or doctoral dissertation which provides the.
PRE-PLANNING FOR CONSTRUCTION PROJECTS. OVERVIEW ASSESSING OWNER CAPABILITIES ANALYSIS OF RESOURCES REGULATORY REQUIREMENTS SITE DEVELOPMENT REVIEWING.
Contract Formulation and Administration
Faculty of Postgraduate Studies and Scientific Research German University in Cairo Modeling to Reduce Variation Order in Construction Projects in Egypt.
Particular Conditions of Contract & Appendix to Tender
12.2 Conduct Procurements The process of obtaining seller responses, selecting a seller and awarding the contract The team applies selection criteria.
(Additional materials)
Particular Conditions of Contract & Appendix to Tender
FIVE PROJECT PHASES 5C-3 Sun. 8:00-10:00am 21/ 2/2016.
Outsourcing: Managing Interorganizational Relations
PROJECT DELIVERY METHODS
Construction Contracts
‘ Causes of Delay During Construction Phase at Palestine ’
Directed Change Constructive Change
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

KING FAHD UNIVERSITY OF PETROLEUM & MINERALS DHAHRAN, SAUDI ARABIA Construction Engineering & Management CEM-520 CHANGE ORDERS IN CONSTRUCTION PROJECTS IN SAUDI ARABIA BY Abdulghafoor Habib Al-Dubaisi Represented By Ali Al-Malki Abdulwahid Al-Zahrani Deyab Al-Jubran Mohammed Al-Shammari May 27,2007

OUTLINE 1- INTRODUCTION 2- OBJECTIVE 3- LITERATURE REVIEW 4- CAUSES, EFFECTS AND CONTROLS 5- SURVEY QUESTIONAIRE 6- RESULTS AND FINDINGS 7- CONCLUSIONS 8- RECOMMENDATION 9- QUESTIONS AND ANSWERS

1- INTRODUCTION Saudi Arabia has in the last thirty years experienced a huge volume of work in the field of construction. This is because the wealth created by the oil which resulted in a very rapid grow and transformations during the period. Large and complex projects have been built, attracting contractors and construction companies from all over the world. Most of those contractors and their companies lack sufficient understanding of the social, cultural and physical environment of Saudi Arabia. This situation coupled with inexperienced owners led to inadequate design resulting in many changes to plans, specifications, and contract terms which we call it change order. A change order is a written order to the contractor, signed by the owner, and issued after execution of the contract, authorizing a change in the work or an adjustment in the contract sum or the contract time.

This study will assist both owners and contractors to plan effectively before starting a project and during the design phase to minimize and control changes and change effects. This study will also lay foundation for further research on the subject. The study will be limited to large building construction projects (projects costing over 50 million Saudi Riyals) in the Eastern Province of Saudi Arabia.

2- OBJECTIVE The main objectives of this research study are to: 1- Identify the main causes of construction change orders in Saudi Arabia. 2- Identify the severity of those causes. 3- Test the hypothesis that consultants and contractors disagree on the severity of causes.

3- LITERATURE REVIEW Introduction This review is by no means a comprehensive one, it covers most important articles and subjects and can open the door for further research on the subject of changes.

The literature review section is divided in four parts. The first part defines the basics of changes and their terminology. The first part defines the basics of changes and their terminology. The second part covers the legal aspects of changes in literature. The second part covers the legal aspects of changes in literature. The third part covers the evaluation and cost aspects. The third part covers the evaluation and cost aspects. The fourth part concentrates on control, administration of changes. The fourth part concentrates on control, administration of changes.

Basics of Change A change is any modification to the contractual guidance provided to the contractor by the owner or owner's representative. This includes changes to plans, specifications or any other contract document. Changes in constructions are caused by design, construction, fabrication, transportation or constructions.

There are three categories for design changes: Design changes caused by improvement through design process. Design changes caused by improvement through design process. Design changes originated by owner. Design changes originated by owner. Design changes initiated by Engineer or consultant. Design changes initiated by Engineer or consultant. Changes can be classified by the procedure used to introduce them Changes can be classified by the procedure used to introduce them Changes can be classified in terms of net effect on scope Changes can be classified in terms of net effect on scope

The Legal Aspects The Major Legal Aspects are Selecting the best delivery system (contract format) Selecting the best delivery system (contract format) Drafting and interpreting change clauses. Drafting and interpreting change clauses. Documenting change orders to be ready in case of litigation. Documenting change orders to be ready in case of litigation.

 Certainly not all types of contracts are equally sensitive to changes.  If contracts are classified as either cost reimbursable or fixed cost, the latter will be the most sensitive to changes.

Cost Aspects  The cost impact of a change is greatly affected by the timing of the change.  A change issued before construction has limited effects as compared to a change issued after construction has already started and material have been procured.

The impacts of a change are classified in the literature as follows:  Direct cost impact.  Direct schedule impact.  Indirect or consequential Impacts

Management Aspects The following actions will help in controlling changes: Owner should define his needs and project objectives early in the project life. Owner should define his needs and project objectives early in the project life. Owner must be committed to change control. Owner must be committed to change control. A team effort by owner, Engineer and contractor to promote recognition, reporting and resolution of a change is required throughout the life of the project. A team effort by owner, Engineer and contractor to promote recognition, reporting and resolution of a change is required throughout the life of the project. All changes must be justified from a cost point of view. All changes must be justified from a cost point of view.

Owner should provide people who posses the following skills: 1. Negotiation skills. 2. Estimating skills. 3. Engineering design and layout skills. 4. Communication skills.

4- CAUSES, EFFECTS AND CONTROLS CAUSES: CAUSES: By Owner. By Owner. By Contractor. By Contractor. By Designer or Consultant. By Designer or Consultant. By all three parties combined. By all three parties combined. By an outside reason. By an outside reason.

EFFECTS: EFFECTS: On efficiency. On efficiency. On time. On time. On cost. On cost. On relation between owner and contractor. On relation between owner and contractor.

CONTROLS: CONTROLS: Conducting efficient change order procedures. Conducting efficient change order procedures. Effective planning of change orders. Effective planning of change orders. Following legal and formal procedure. Following legal and formal procedure. Assessing changes and administrating them. Assessing changes and administrating them. Implementing team work and effort. Implementing team work and effort.

5- SURVEY QUESTIONAIRE CONTENTS: CONTENTS: Six sections. Six sections. SAMPLE RESTRICTIONS: SAMPLE RESTRICTIONS: Total qualified participants were: Total qualified participants were: 42 contractors. 42 contractors. 41 consultants. 41 consultants. SAMPLE SIZE: SAMPLE SIZE: Statistical principles resulted in choosing 16 responses. Statistical principles resulted in choosing 16 responses. 17 responses were chosen by the researcher. 17 responses were chosen by the researcher.

SCORING: SCORING: Ordinal scale was used and transformed into an interval scale. Ordinal scale was used and transformed into an interval scale. 'never' to 'very often' = zero to 100. 'never' to 'very often' = zero to 100. Using the following equation: Using the following equation: Importance, Prevalence, and Utilization Indices were calculated. Importance, Prevalence, and Utilization Indices were calculated.

6- RESULTS AND FINDINGS 1. The discussion of the results from the sections on general information. 2. The analysis of data on causes of change order. 3. The analysis of data on the effects of change orders. 4. The analysis of data on controls of change orders. 5. Correlation and hypothesis testing.

General Information Contractors are larger in size (number of employees) than consultants Contractors are larger in size (number of employees) than consultants Most consultants companies (70%) are less than 200 employees whereas only 35% of the contractors are smaller than 200 employees Most consultants companies (70%) are less than 200 employees whereas only 35% of the contractors are smaller than 200 employees None of the contractors and consultants participated in the survey has experience of less than 5 years None of the contractors and consultants participated in the survey has experience of less than 5 years

Distribution of contractors and consultants over the type of construction contract format Distribution of contractors and consultants over the type of construction contract format  65% lump sum turnkey type.  18% lump sum excluding material.  None of the respondents reported design and build (D&B) type contract

Causes of Change Orders 1. Change of plan by owner 2. Owner financial problem 3. Owner change of schedule 4. The objective of project is not well define 5. Substitution of materials or product 6. Conflict between contact documents 7. Change in design by consultant 8. The scope of work for the contractor is not well defined 9. Errors and omissions in design 10. The lack of coordination between Contractor and consultant 11. Value engineering 12. Technology changes 13. Differing site condition 14. Contractor desire to improve his financial situation 15. The contractor financial difficulties 16. The required labor skills are not available 17. The required equipment and tools are not available 18. Workmanship or material not meeting the specifications 19. Safety consideration 20. Weather conditions 21. New government regulations

Contractors and Consultants ConsultantsContractors Change of plans by owner 1 Substitution of materials and procedures Substitution of materials or procedures Errors and omissions in design 2 Owner's financial problems Change in design by consultant 3 Owner financial problems Owner change of schedule Substitution of materials or procedures. 4 Change in design by consultant Lack of coordination between contractor and consultant. Owner's financial problems and conflict between contract documents. 5

Effects of Change Orders 1. Decrease in productivity 2. Delay in completion schedule 3. Dispute between owner and contractor 4. Decrease in quality of work 5. Increase in project cost 6. Additional revenue for contractor 7. Delay of material and tools 8. Hold on work in other areas 9. Increase in contractor's overhead 10. Delay in payment to contractor 11. Demolition and re-work Contractors and Consultants Increase in project cost Delay in completion schedule Additional revenue for contractors Demolition and re-work Increase in contractor's overhead

Controls of Change Orders 1. Early setting of change order handling procedures 2. Timely approval of change order 3. Negotiation by knowledgeable people 4. Appropriate approval in writing 5. Clarity of scope of change 6. Giving consideration to indirect effects in change order pricing 7. Checking and review of design changes for feasibility 8. Review of gray areas in contract documents 9. Freeze of design 10. Team effort between parties 11. Work-break down structure

Correlation and Hypothesis Testing Correlation exists between the amount of change order generated and company size, owner involvement, years of experience, relation of principal parties, amount of increase in schedule and use of controls are studied in this chapter. The hypothesis testing is used by using T-test statistics and the same hypothesis testing technique is used to test for contractors - consultant's agreement or disagreement on the prevalence of effects and the utilization of controls. Conclusion correlation calculations failed to prove any relation between the variables considered and the percent increase in project cost due to change orders. Conclusion Test for the degree of agreement or disagreement between the consultants and contractors on the causes, effects, and controls of change orders show agreement.

7- CONCLUSION The causes of change orders, and their effects on projects cost and schedule are complex and influenced by numerous interrelated factors. The risk and uncertainties associated with project changes make predictions and planning for changes a difficult task. The research tested the level of agreement between contractors and consultants over the causes, effects, and controls and found a large degree of agreement. The research showed also that over 60% of changes are civil or architectural in nature. The research indicate that owner is the major cause of change orders in large building projects. Increase of project cost and schedule are the main effects as expected. Clarity of scope of work is the most utilized control against change order problems.

8- RECOMMENDATIONS Based on the findings of this research study and the literature search, the following recommendation are made: 1- The research indicates that owner is the major source of change orders in large building construction. It is recommended to get a project management consultant firm (PMC) to supervise both the design and construction activities to insure that owners need and expectations are met by the design. 2- Substitution of materials or procedures came as the second source of change orders and normally originated by owner. It is recommended to have the Engineer to specify the material for the building in a detailed manner to eliminate the possibility of changes later.

4- The utilization for the review of contract documents is very low. Contractors should expend more effort prior to contract award to review contract document. 5- Contractors should consider using Work Breakdown Structure or other tracking system more often than it used now. Many contractors indicate they are not using any type of structuring system for their construction activities and this may lead to inability to tracing effects of change orders on the rest of the project.

9- QUESTIONS AND ANSWERS Question # 1 Question # 1 What are the three most common causes of change What are the three most common causes of change orders from the contractor's and consultants point of orders from the contractor's and consultants point of view? view? Answer # 1 Answer # 1 1. Change of plans by owner 2. Substitution of materials and procedures 3. Errors and omissions in design

Question #2 True or false 1. The cost impact of a change is greatly affected by the timing of the change. (True) 2. All types of contracts are equally sensitive to changes. (False)

THANK YOU