Southern Natural Gas Company 2014 Outage Review Meeting Customer con call and Webex September 17, 2014 1.

Slides:



Advertisements
Similar presentations
System Operations Overview System Changes Physical Constraints Gas Distribution System 2003/2004 Scheduling Guidelines OFOs and Curtailment System Changes.
Advertisements

© 2009 The Williams Companies, Inc. All rights reserved. ______________ WECC November 12, 2012.
SR Lititz Pike Bridge Replacement Note: Dates indicated in this presentation are estimated based on the contractors current schedule and does.
Southern Natural Gas Company 2015 Outage Review Meeting Customer con call and Webex February 18,
Southern Natural Gas Company 2013 Outage Review Meeting Customer con call and Lync Online Meeting September 18,
Southern Natural Gas Company 2014 Outage Review Meeting Customer con call and Webex July 16,
D E P E N D A B L E N A T U R A L G A S Customer Webex July 25 th, 2013.
October 20-21,2009 Agenda Item 6a.. Ohio River CSO Communities Pennsylvania – 10 communities West Virginia – 10 communities Ohio – 10 communities Kentucky.
Importance of Processing Plant Information Gas Processors Association 88 th Annual Convention March 8-11, 2009 Barbara Mariner-Volpe
Hurricane Recovery Update MTAC November 2, HURRICANE RECOVERY TIME LINE OF EVENTS Hurricane Katrina Makes Landfall in Florida 6:30 P.M. Thursday,
2 Permian Basin Supply San Juan Basin Supply Washington Ranch Storage Waha Compressor Stations Gas Supplies Transport Flow Directions Pipelines Production.
I-95 Corridor Coalition Partners in Transportation Progress Capt. Tom Martin Operations Program Coordinator 2009 TIME Conference October 26-27, 2009 Lake.
Southern Natural Gas Company 2013 Outage Review Meeting Customer con call and Webex July 17,
Natural Gas STAR Partner Experiences Duke Energy Gas Transmission By: David Felcman Transmission Technology Transfer Workshop September 22, 2004 Houston,
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
Insert Photo Here And mark any obvious features in the photo that are discussed in the camera point description 342°
G 200 L 200 ISO NEW ENGLAND T H E P E O P L E B E H I N D N E W E N G L A N D ’ S P O W E R. COLD SNAP Overview of Proposed Options for Winter 2004/2005.
Insert Photo Here And mark any obvious features in the photo that are discussed in the camera point description.
Directions to Camera Point: From the parking lot, head south along the path until the three way intersection by the restrooms. Turn east and there will.
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
AUGUST 19, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
ColumbiaGrid Planning Update to PCC Marv Landauer October 7, 2014.
Southern Natural Gas Company 2014 Outage Review Meeting Customer con call and Webex June 18,
Southern Natural Gas Company 2015 Outage Review Meeting Customer con call and Webex March 18,
Parent Information 2 nd Grade Curriculum Night Mrs. Bouldin.
SMART METER TEXAS Status Update July 29, AGENDA Release 1 Smart Meter Texas Online Portal Update – SMT Solution Update – Registration Statistics.
®® QUESTAR GAS Transportation Balancing Susan Davis, Director, Account & Community Relations February 28, 2014 We develop, transport and deliver clean.
D E P E N D A B L E N A T U R A L G A S | NYSE:EP Customer Webex September 6, 2011.
Intermountain West Production -- Getting Gas to Market Jim Cleary El Paso Western Pipelines IPAA Mid-Year Meeting June 14, 2004.
St. Joseph School Mrs. Fischer. Surviving the 4 th Grade Review your child’s agenda after school everyday. Sign the agenda after you have verified the.
El Paso Corporation Nominations and Scheduling Customer Advisory Group Update May 14, 2009 Colorado Interstate Gas Company Wyoming Interstate Company Cheyenne.
Southern Natural Gas Company 2015 Outage Review Meeting Customer con call and Webex September 16,
Southern Natural Gas Company 2015 Outage Review Meeting
1 Market Trials Outage Scheduling Weekly Update July 09, 2010.
Financial Impact of Drought March 5, 2008 Updated 3/17/08.
FERC Order No. 698 Procedures for Providing Hourly Consumption Data Spectra Energy Pipelines June 20, 2008.
Southern Natural Gas Company 2015 Outage Review Meeting Customer con call and Webex June 17,
Southern Natural Gas Company 2015 Outage Review Meeting Customer con call and Webex July 22,
OPTION 9 CO 2 PLANT PROCESSING Description: Operate the existing Castle Valley CO 2 plant to process the Price area coal-seam gas. Plant can processes.
Drought Monitoring, Prediction and Response - A View From Georgia - David Emory Stooksbury, Ph.D. State Climatologist and Associate Professor Engineering.
Southern Natural Gas Company 2013 Outage Review Meeting Customer con call and Webex May 22,
Southern Natural Gas Company 2013 Outage Review Meeting Customer con call and Webex March 14,
Southern Natural Gas Company 2014 Outage Review Meeting
Southern Natural Gas Company 2015 Outage Review Meeting Customer con call and Webex October 21,
OCTOBER 2, 2013 Maine 2013 Outage Coordination Redacted Copy.
Absolute Location: Where is your desk? Relative Location: Where is your desk? Cardinal Directions Relative Location of your Local Community using a Michigan.
Southern Natural Gas Company 2015 Outage Review Meeting Customer con call and Webex August 19,
NY/NJ/PHL Metropolitan Area Airspace Redesign Project and Implementation Update Presentation to: Congressional Staffers By: Steve Kelley, Airspace Redesign.
Southern Natural Gas Company 2014 Outage Review Meeting Customer con call and Webex August 20,
Southern Natural Gas Company 2014 Outage Review Meeting Customer con call and Webex April 16,
Lead from the front Texas Nodal 1 EDS Market Call Weekly Update Jan 30, 2009.
Understanding the Impacts of Incremental Gas Supply on the Flow Dynamics Across the North American Grid Canadian Institute Vancouver, BC November 20, 2006.
Southern Natural Gas Company 2016 Outage Review Meeting Customer con call and Webex March 16,
Summer 2000 – Present in California
June 5, 2017.
Southern Natural Gas Company 2015 Outage Review Meeting
TGP Outages Remainder of the Year (Sept. thru Dec.)
Florida Gas Transmission Mainline Hydrostatic Test
To Buy Hunting Land For Sale
Florida Gas Transmission Mainline Hydrostatic Test
Southern Natural Gas Customer Working Group Meeting
Florida Gas Transmission Mainline Hydrostatic Test
Florida Gas Transmission Mainline Hydrostatic Test
projects update ATLANTA district
H64:02 Clear River East & West Hills Sept 8/99 (mvc-019f)
Southern Natural Gas Company 2018 Outage Review Meeting
GRP Progress & Plans The GRP project was established to deliver an updated design utilising fully supported hardware and software for Gemini. GRP is replacing.
System Operational Update and Review December 4, 2018
New Construction Program
Presentation transcript:

Southern Natural Gas Company 2014 Outage Review Meeting Customer con call and Webex September 17,

Welcome 2

Agenda Review Unscheduled Outages Review of Upcoming Outages – September/October and November North System South System South Louisiana – Outages for the remainder of 2014 North System South System South Louisiana Contacts 3

Disclaimers Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time). Scheduled dates are subject to change. Projects may be added, altered, delayed or cancelled. SNG will provide notice of such additions or changes via SoNet Premier postings. Dates as posted on SoNet should be deemed correct in the event of conflicts between SoNet posted dates and dates within this presentation. 4

Color Key for Maps Green – No Impact Anticipated Yellow – Restrictions are possible – With extended duration, restrictions could be necessary from time to time – Meter(s) affected are noted with (M) Red – Restrictions are probable 5

Southern Natural Gas Pipeline LA MS AL GA FL Enterprise White Castle Bear Creek Muldon Chattanooga Atlanta Thomaston Albany Elba SC Aiken Elba Express North System South Louisiana South System 6 Compressor Station Storage Field LNG Compressor Station Storage Field LNG Pearl River Franklinton Gwinville

Southern Natural Gas Pipeline Unscheduled Outage Update LA MS AL GA FL Enterprise White Castle Bear Creek Muldon Chattanooga Atlanta Thomaston Albany Elba SC Aiken Elba Express 7 Compressor Station Storage Field LNG Compressor Station Storage Field LNG Pearl River Franklinton Gwinville Toca 8” West Point Line outage. Auburn Franklinton compressor station unit outage Return to service around March of 2015 Riceboro Brookman Ocmulgee Hall Gate Wrens Onward Pickens Louisville Reform McConnells Providence Tarrant Pell City Rome York Gallion Selma Bay Springs Elmore Holy Trinity Riceboro compressor station unit outage Repair plan being developed Ellerslie Ellerslie unit outage return to service White Castle compressor station unit outage Return to service around October 1, 2014

SNG North System Maint. Review Sept. thru November LA MS AL GA Logansport Bienville Bear Creek Storage Onward Pickens Rankin Louisville Muldon Storage Reform McConnells Providence Tarrant Pell City DeArmanville Bell Mills Rome Compressor Station Storage Field Compressor Station Storage Field Huntsville Chattanooga Atlanta 8 Southern will be conducting other general maintenance during this period AL Remediation on 24” North Main Loop line to Pipeline remediation 24” North Main 2 nd Loop line thru Capacity reduced as much as 95 MMcf/d Bear Creek Fall Shut-in Test 10/21/14 thru 10/27/14 DIQ and DWQ allocated 64% Muldon Fall Shut-in Test 10/7/14 thru 10/13/14 DIQ and DWQ allocated 36% Muldon unit maintenance Two weeks in the fall Maintenance on 18” Atlanta –Austell line- October-stopple by-pass

SNG South System Maint. Review Sept. thru November MS AL GA Enterprise Gwinville Selma Auburn Ellerslie Thomaston Ocmulgee Hallgate Wrens Elmore York Gallion Bay Springs Compressor Station Storage Field LNG Compressor Station Storage Field LNG Atlanta Elba Hartwell Elba Express Aiken Holy Trinity Albany Pavo 9 Brookman Riceboro Southern will be conducting other general maintenance during this period Pipeline replacement on the 30” South Main 2 nd Loop line thru 10/20/14 Capacity reduced up to 240 MMcf/d Enterprise unit maintenance-August 26 th thru October Maintenance 4” Fitzgerald Line –October- stopple by-pass Auburn unit maintenance October Enterprise station and Rose Hill three day outage end of September first of October timeframe Ellerslie units 8 & 9 outage to

SNG South La. System Maint. Review Sept. thru November Shadyside White Castle Franklinton Toca Gwinville LA MS Compressor Station Storage Field Compressor Station Storage Field West Leg East Leg 10 Pearl River Southern will be conducting other general maintenance during this period White Castle, Shadyside Unit Maintenance Mid September - October West Leg Capacity impact up to 150 MMcf/d

SNG North System Maintenance Review remainder of 2014 LA MS AL GA Logansport Bienville Bear Creek Storage Onward Pickens Rankin Louisville Muldon Storage Reform McConnells Providence Tarrant Pell City DeArmanville Bell Mills Rome Compressor Station Storage Field Compressor Station Storage Field Huntsville Chattanooga Atlanta 11 Southern will be conducting other general maintenance during this period

SNG South System Maintenance Review remainder of 2014 MS AL GA Enterprise Gwinville Selma Auburn Ellerslie Thomaston Ocmulgee Hallgate Wrens Elmore York Gallion Bay Springs Compressor Station Storage Field LNG Compressor Station Storage Field LNG Atlanta Elba Hartwell Elba Express Aiken Holy Trinity Albany Pavo 12 Brookman Riceboro Southern will be conducting other general maintenance during this period

SNG South Louisiana System Maintenance Review remainder of 2014 Shadyside White Castle Franklinton Toca Gwinville LA MS Compressor Station Storage Field Compressor Station Storage Field West Leg East Leg 13 Pearl River Southern will be conducting other general maintenance during this period

Gas Control Contacts Adam Krustchinsky – Manager (713) – 420 – 3265 (office) (713) – (cell) Kal Dankovich – Outage Coordinator (713) – 420 – 7522 (office) (205) – 420 – 7305 (Gas Control) Jimmy Reese – Lead Controller (713) – 420 – 7310 (office) (205) – 420 – 7305 (Gas Control) Daniel Mitchell – Lead Controller (205) – 420 – 5874 (office) (205) – 420 – 7305 (Gas Control) 14

Questions? 15