LECTURE 7 CLAIMS RELATED TO SUB-CONTRACTORS

Slides:



Advertisements
Similar presentations
A GIA is a contract between a surety company and a contractor (or subcontractor)/principal. A GIA is a standard, typical document in the construction.
Advertisements

ISTISNA’.
Contracts – important issues
Let’s Study Legal English Together!
REMEDIES FOR BREACH OF CONTRACT.
Funds administration, also referred to as funds control, funds disbursement, funds management, and escrow, is a method that sureties use to offset the.
INDEMNITY AND GUARANTEE.
Contracts of Indemnity & Guarantee
WHAT IS A CONTRACT ? Agreement enforceable by law
© 2007 Prentice Hall, Business Law, sixth edition, Henry R. Cheeseman Chapter 15: Third-Party Rights and Discharge.
BELÉN GARCÍA ÁLVAREZ ASSISTANT PROFESSOR OF COMMERCIAL LAW UNIVERSITY OF DEUSTO (SPAIN) ROTTERDAM SEPTEMBER OF 2014 VIII ECMLR.
CARLIN LAW GROUP, APC (619) Know Your Indemnity Obligation Know Your Risk Know Your Insurance Company by KEVIN R. CARLIN, ESQ.
Nabil dmaidi1 Miller Act H Enacted in 1935 H Federal Contracts over $25,000 H Contractor shall provide Bonds H Performance Bonds in the amount to protect.
Subcontractors بسم الله الرحمن الرحيم Islamic university in Gaza Collage of Engineering Postgraduate program Construction Management Prepared by: Eng.
Subcontracts 101 By Mitali Ravindrakumar USC Collaboration between Parties Perform Subcontractor Analysis Sponsor - Fund Project/Subcontr act Negotiate.
What Government Contractors Need to Know About Executive Order “Nondisplacement of Qualified Workers Under Service Contracts” Raymond L. Hogge, Jr.
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
Contract Rights and Duties
Business Law and the Regulation of Business Chapter 30: Relationship with Third Parties By Richard A. Mann & Barry S. Roberts.
Time for a new standard - AS General Conditions of Contract
Construction Contract Administration (ENGC 6363) ( FIDIC Chapter 15) EMPLOYER BY TERMINATION Presented by: Mustafa Al tayeb.
The Islamic University of Gaza Engineering Faculty
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT Defects Liability [Construction Contract Administration] Chapter 11.
An Act of Parliament to provide for compensation to employees for work related injuries and diseases contracted in the course of their employment and for.
LOGO October The Employer FIDIC 1999 dasdas Supervisor: Dr.Kamalain shaath Done by: Mahmoud Abu Kmail Construction Contract Administration ENGC.
Insurance provisions under JCT 1998 and JCT Standard Building Contract 2005 Brian Lewis – QBE CAR.
1 REMEDIES FOR BREACH OF CONTRACT. 2 When one of the parties to the contract makes a breach of the contract the following remedies are available to the.
PERFORMANCE OF CONTRACT.
Study Unit 4 Performing Contractual Obligations.  The outcomes for this learning unit are that you should be in a position to: ◦ Discuss Agency ◦ Discuss.
Project risk and control. Tender risk Programme and method – Tightness of completion LAD’s Extent of change – Construction method Temporary works Change.
Bailment “the transfer of possession, but not the title of personal property by one party to another, under agreement”
CONTROLLING TIME. ”Remember that time is money” Benjamin Franklin 1748.
Center of Islamic Finance COMSATS Institute of Information Technology Lahore Campus 1 Adopted from open source lecture of Meezan Bank. Customized for best.
Agency Law. “If you want something done right, do it yourself.” “Many hands make light work.” Anonymous folk sayings.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Performance of a contract A contract is said to be performed when the parties to a contract either perform or offer to perform their respective promises.
CONSTRUCTION CONTRACTS – MASTER CHART
1. Introduction Time is of essence in basically every construction project Yet, delays of some sort are general rule, rather than the exception Consequence:
Chapter 4.  When one party breaks the contract by refusing to perform his promise, the breach of contract take place. The following remedies are available.
General Condition THE EMPLOYER Construction Law Supervised By : Dr. Kamalain Shaath Prepared By : Eng. Fawzy El.farra.
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
FORMULATION & PRESENTATION OF EOT CLAIMS
7 Plant, Materials and Workmanship. 7.1Manner of Execution The Contractor shall carry out the manufacture of Plant, the production and manufacture of.
Presented By: A document prepared by promoters After the formation of company To take capital by issuing shares Data regarding Company’s policy.
Minimum Wages Act 1948.
1 中央大學營管所學分班 工程契約與文件管理 CHAPTER 16 TEST AFTER COMPLETION Silver Book, 2002 Clause 12. 授課教授 : 謝定亞 博士 學員 : 陳忠正 ( 研發中心管線組 )
LECTURE 5 FORMULATION & PRESENTATION OF OTHER CLAIMS
CONTINUATION SA REPORT NI TAHNEE. ELEMENTS OF CONTRACTS.
ENGINEER Engineer Duties: Carry out the duties assigned in the contract.Carry out the duties assigned in the contract. Engineer's staff shall include qualified.
Chapter 18.  A fiduciary relationship “which results from the manifestation of consent by one person to another that the other shall act in his behalf.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
McGraw-Hill/Irwin Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Chapter 10 Agency and Employment Relationships.
By Khalil T. Hasan Construction Solutions ( Joint Operation/Administration of multiple FIDIC Forms – A Case Study.
Kevin Kelly Government Construction Projects & Capital Spend Conference 2016 Wednesday 11th May 2016 Royal Marine Hotel, Dun Laoghaire, Co. Dublin.
INDEMNITY AND GUARANTEE.
Profession Practices (ECIV-5105)
Administration of a FIDIC Contract - Project Control
Administration of a FIDIC Contract - Commencement Date to + 28 Days -
Administration of a FIDIC Contract - Award to Commencement -
Performance of Contract
Extension of time and how it is granted to a contractor (Referencing JCT 2005)
Speaker: Sarah Chambers, Esq. Claims Counsel| Professional Liability
Certificates JCT 11 SBC allows for 10 different kinds of certificates.
Find the Problems with the Provisions May 11, 2016 Presented By:
STRUCTURE OF THE PRESENTATION
Construction Contract Administration
PARTNERSHIP 6/27/2019 7:14:13 AM.
Presentation transcript:

LECTURE 7 CLAIMS RELATED TO SUB-CONTRACTORS Reasons for Nominated Sub-contractors Contractor's right to object NSC Nominated Sub-contractor’s programs Extension of Time for completion of Nominated Sub-contract Works Extension of Time for NSC in HKSFSC Delay by Nominated Sub-contractors Architect’s consent to grant EOT to a NSC Design and Drawings provided by the NSC Variations to the Nominated Sub-contract Works Delay and Disruption Claims Loss & expenses claims by NSC

REASONS FOR NSC: The design of the sub-contractor's works should be in line with the design of the principal works Appointment of the sub-contractor before the main contractor due to long delivery periods for plant & equipment (e.g. lift) The sub-contract work is an extension of work done previously by a particular sub-contractor & the same equipment & standards are required to be used in the new works The sub-contract works are the main requirements of the employer and the building is secondary (e.g. in process plant) The employer has a particular preference for a subcontractor based on previous performance & standard of work

CONTRACTOR'S RIGHT TO OBJECT NSC IF: NSC refuses to enter into a sub-contract on terms, similar to that in the Main Contract, to indemnify the contractor against any claims due to default / negligence of the NSC NSC does not agree to complete the nominated sub-contract works in accordance with the reasonable directions of the contractor so that the obligations under the main contract can be discharged NSC does not agree to complete the nominated sub-contract works within the period specified in the proposed nominated sub-contract / suit main contractor's program Main contractor believes, with evidence, that the NSC is unsuitable or financially unsound

NOMINATED SUB-CONTRACTOR’S PROGRAMS Usually the nominated sub-contract works would not be awarded until just a few weeks before the commencement of them which may be long time after the award of the main contract. Sometimes the nominated sub-contractors are requested that their works should suit the programs of the Main Contract which show the completion date earlier than the award of the nominated sub-contracts works! !? In such case, the nominated sub-contractors may only be obliged to complete their works within a reasonable time which probably may not be within the contract period of the Main Contractor

EOT FOR COMPLETION OF NSC WORKS EOT for 2 classes of events: Delay for which the main contractor is entitled under the main contract Delay or fault on the part of the main contractor or persons for whom the main contractor is responsible  

EOT IN HKSFSC EOT may be granted to NSC under Clause 8 of the HKSFSC : By reason of any of the matters specified in clause 7(1) - variations, of the sub-contract By any act or omission of the main contractor, his sub-contractors, his or their respective servants or agents For any reason (except delay on the part of the sub-contractor) for which the main contractor could obtain an EOT for completion under the main contract   

DELAY BY NSCS Under clause 23(g) of the Main Contract, MC can obtain EOT for the delay by the NSC provided that the main contractor has taken all practical steps to avoid or reduce Under clause8 (b)(ii) of the Sub-contract, the sub-contractor will not have EOT granted for delay on his part Therefore, the Date for Completion of the Main Contract may be later than that of the Sub-contract The NSC may be held wholly liable for the L.D. amount

WHO GRANTS NSC EOT? It is the Main Contractor to grant EOT to the nominated sub-contractor, not the Architect However, the Main Contractor should obtain consent from the Architect before granting any EOT to the nominated sub-contractor If the Architect refuses to give consent to the Main Contractor to grant nominated sub-contractor EOT for qualifying events, the nominated sub-contractor may argue that the time for completion of the sub-contract works is time at large

DESIGN AND DRAWINGS PROVIDED BY THE NSC In contracts where the responsibility for design rests on the employer, any design of the nominated sub-contract works by the sub-contractor is deemed to be the employer's design. Delay in design by the NSC will be considered to be delay by the employer Some contracts attempt to place responsibility for co-ordination of design by nominated sub-contractors upon the main contractor or on various sub-contractors. However, it is usually a disaster and will almost certainly end up to be the responsibility of the employer.

VARIATIONS TO THE NSC WORKS Valuation of the variations of the NSC works is similar to that of the main contract works However, some instructions issued are variation to the main contractor but are not variation to the sub-contractor because the sub-contracts are often awarded some time after the main contracts. Before the award of any nominated sub-contracts, the programs of the nominated sub-contractors & that of the main contractor should be coordinated to make sure that they are consistent. Otherwise, either the main contractor will object the nomination or the sub-contractor will claim EOT & L&E.

DELAY AND DISRUPTION CLAIMS If it is the fault of the employer, then the contractor & the nominated sub-contractor should co-operate on keeping the records, giving notices and the means of formulating a claim. If it is the fault of the contractor or other sub-contractors, there will be some resistance to settle the claims especially the delay is concurrent to the delay by the employer from which the main contractor can claim under the main contract. In Clause 8 (c) of HKSFSC, if in the opinion of both the architect & main contractor that the sub-contractor is involved in direct loss /expense, then the architect should ascertain the amount.

LOSS & EXPENSES CLAIMS BY NSC No specific clauses in the HKSFSC. Clause 12 - NSC can have same rights or benefits (implied including loss and expense) of the main contractor under the main contract.