The Design-Build Experience. I-95 Honda Interchange $ 8 million Wateree River $ 8 million Reedy & Enoree Bridge $ 3 million SC 170 Widening $100 million.

Slides:



Advertisements
Similar presentations
Right of Way Acquisition Process Jesse W. Smith Right of Way Manager.
Advertisements

Federal/State/Local Agency Partnership Under the Uniform Act Regulations, Roles and Responsibilities.
How to Build a Better Bus Garage: Mn/DOTs Facility Guidebook 18 th National Conference on Rural Public and Intercity Bus Transportation Gerry Weiss, State.
The South Carolina Design-Build Experience Presented by: Rocque L
SCDOT and Asset Management. Bridge Services Current Contract – – Asset Maintenance Contract for Arthur Ravenel Bridge System in Charleston and.
Monitoring Acquisition/relocation Projects William Von Klug, SR/WA, R/W-RAC January 13, 2009.
Route 29 Western Bypass: Background and Timeline May 13, 2014 John Lynch, P.E. Culpeper District Administrator.
Real Property Disposition Dudley Whyte and Tiffany Gallegos Region IV and Region VIII May 19-21, 2014.
FDOT R/W Guidelines Use of License Agreements
Construction Industry Advancement Program John T. Withers, P.E.,P.P. Supervising Engineer, Highways/Buildings - Design New Jersey Turnpike Authority Working.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION South Cascade Drive/Miller Road (Formerly Route 219)/ Cattaraugus Creek Design-Build Project (PIN ,
State Aid Design-Build Project Delivery for Minnesota Cities and Counties.
Alternative Project Delivery
Dulles Corridor Metrorail Project 23-mile new Metrorail line branching off the Orange Line after East Falls Church 11 new stations 5 in Phase 1: East Falls.
SCDOT’s Strategic Direction Janet Oakley Secretary of Transportation South Carolina Alliance to Fix Our Roads September 22, 2014 Janet Oakley Secretary.
Legal Perspective on NDOT Alternative Procurements Geoffrey S. Petrov, Nossaman LLP.
Greenfield District Utility/RR Engineer, INDOT
Understanding Right of Way Process Dawn Haecker - Training & Technical Support Supervisor INDOT Trent Newport - VP, CrossRoad Engineers.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Route 110 over Route 27 Design-Build Project (PIN , D900027) Town of Babylon, Suffolk County Request.
AGENDA  PROJECT HISTORY  NORTHERN SECTION UPDATE  SOUTHERN SECTION OVERVIEW  INTERCHANGES  PROJECT SCHEDULE  UPCOMING ACTIVITIES  OPEN DISCUSSION.
WELCOME TO THE PROCUREMENT SEMINAR Procurement and Contracts An Overview of Contract Administration.
W E L C O M E to the SB 1022 Real Estate Due Diligence Training SB 1022 Real Estate Due Diligence Training.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
Office (307) Toll Free Right-of-Way Program Right-of-Way Program 5300 Bishop Blvd., Cheyenne, WY
FEDERAL REQUIREMENTS FOR RIGHT OF WAY FHWA & The Uniform Act.
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
Right of Way Section Dee Jones State Right of Way Manager Richard Dunlap Operations Manager Joe Gray Region 5 Right of Way Manager
COMPLIANCE WITH GRANT IMPLEMENTATION PROCEDURES TxDot Grant Fund Project.
IDM Chapter 104 Utility Coordination Joe Gundersen Senior Utility Engineer, INDOT August 21, 2014.
1 Acquisition, Relocation and Displacement For Local Officials.
Partners in Progress Forming Bonds with GECs to Build Roads.
TH 2 – Wilton Bridge Replacement Design-Build Project S.P March 5, 2009 Todd Vonasek, P.E. Mn/DOT Project Manager PROJECT INFORMATIONAL MEETING.
Utility & Rail Coordination in Project Development Jennifer McCleve Utilities & Rail Branch Manager.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Region 9 Design-Build Project (PIN , D900020) Broome, Delaware,
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
WELCOME TO UNB. MARK McGEEHAN Assistant Manager, Procurement Services 3 plus years with UNB 28 years in Healthcare Procurement Current member of APPA.
Offsite Detour analysis. Calculation of detour length Distance along SR = Distance along SR
IDM Chapter 104 Utility Coordination Gail Lee Utility and Railroad Engineer, INDOT June 10, 2015.
Procurement Authority Representative Roles and Responsibilities Amanda Price, Program Development Coordinator, Planning and Programming, Transportation.
Florida Department of Transportation District One Presented By: American Acquisition Group, LLC District Wide Acquisition and Relocation Services.
Project Planning and Progress August 2, 2011 Michelle Page | Design Build Engineer.
Preparing a Right of Way Clearance Certification Request Missouri Local Programs How to complete right of way clearance certification-No new property rights.
2015 NW Region Right of Way Conference Oversight Expectations after the Consultant is Hired Presented by: Grant Casebeer, Reg. 1 ROW Project Manager October.
Northwest Regional Right of Way Conference The Hilton, Vancouver, Washington October 27, 2015 Lynn Peterson Secretary of Transportation Oversight Expectations.
D.d. delivers district department of transportation d.d. delivers FAISAL HAMEED RONALDO T. NICHOLSON. P.E. Innovative Project Delivery Processes Innovative.
ARRA Design-Build in Minnesota Jay Hietpas - Mn/DOT.
PROJECT MANAGEMENT TRACKING SCHEDULES Audrey Demeter, PE,PM Casey Unrath, EIT.
Transportation Projects City Council Workshop May 14, 2013.
Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director Real Estate Overview Matt Kouskouris, Division.
Coordination of Right of Way on Design-Build Contracts By- Richard Bennett State Right of Way Director Virginia DOT.
HOOSIER HEARTLAND HIGHWAY SR25 Segment Four Cass County Public Information Meeting December 10, 2009 Design Consultant – United Consulting Engineers.
Metric to English Conversion California Bridge Construction Forum March 8, 2006 Mark Leja, Chief, Division of Design California Department of Transportation.
CENTRAL FLORIDA EXPRESSWAY AUTHORITY FY Five Year Work Plan December 10, 2015 Presented by: Jeanette Maldonado-Ambler, PE Atkins.
Project Delivery Performance Improvement Report to the Oregon Transportation Commission Hal Gard, Technical Services, Geo-Environmental Dee Jones, Technical.
Purchasing Cards. What is a Purchasing Card? It is a type of commercial credit card, used by organizations for payment of goods and services. This tool.
The Right Things to Know about Right- of-Way April 8, 2016 Tammy M. Keeley Realty Officer FHWA – AL Divisi on.
Louisiana State University. IT GOVERNANCE LOUISIANA CONSTITUTION (allows us to purchase with state funds) LA REVISED STATUTES (provides the laws that.
Western Area Power Administration Land Acquisition Discussion May 11, 2016.
May 4, 2011 Jenefer Youngfield Utah State Office of Education Utah K-12 Public School Construction Education and Training.
Welcome. Contents: 1.Organization’s Policies & Procedure 2.Internal Controls 3.Manager’s Financial Role 4.Procurement Process 5.Monthly Financial Report.
R/W LAP PROJECTS Presented by Ron Crew.
Essential Requirements of the Uniform Act for Local Public Agencies
Construction Oversight
Right of Way Process INTRODUCTION of subject and presenter.
Preparing a Right of Way Clearance Certification Request
I-85 Widening Project MM Cherokee County Public Hearing March 14, 2017.
I-85 Widening Project MM Cherokee County Public Hearing March 14, 2017.
Right-of-Way the right way
Right of Way Certification
Presentation transcript:

The Design-Build Experience

I-95 Honda Interchange $ 8 million Wateree River $ 8 million Reedy & Enoree Bridge $ 3 million SC 170 Widening $100 million Cooper River Bridges $ 531 million Conway Bypass $ 386 million Southern Connector $ 206 million Carolina Bays Parkway $232 million

Reedy River Bridge Enoree River Bridge First Design-Build Bridge Replacement in SC First Design-Build Project to Start Construction in SC 1996 RFP Process Two Bridge Replacements $ 3 million Designer Wilbur Smith Associates

Cost Summary Cost Summary n Estimate for Design-Bid-Build$ 3,222,000 n Design-Build Price$ 3,125,000 Time Summary Estimated Design-Bid-Build 628 Days Design-Build581 Days

Wateree River Bridge Bridge Replacement $ 8 million RFP Process Designer Ralph Whitehead & Assoc.

Wateree Cost Summary n Estimated Design-Bid-Build $ 9,162,000 n Design-Build Price $ 7,956,000 * * Includes $50,000 for SCDOT Preliminary Engineering & $50,000 for Construction Monitoring $50,000 for Construction Monitoring Wateree Time Summary n Estimated Design-Bid-Build967 Days n Design-Build457 Days

HONDA INTERCHANGE New Interchange Bridge Replacement $ 8 million RFP Process Designer Consoer Townsend Envirodyne Total Timeframe – 11 Months

HONDA INTERCHANGE Total Tracts – 1 Condemnation Rate – 0%

CONWAY BYPASS New Location Freeway 28 Miles in Length Fluor Daniel $386 Million 39 Months RFP Process Contract Signed

Conway Bypass Total Parcels – 233 Condemnation Rate – 49%

SOUTHERN CONNECTOR Greenville County, SC New Location Toll Road 16 Miles in Length Interwest Carolina Group $206 Million 45 Months Maintenance by SCDOT Toll Collection/Operation by Interwest RFP Process Contract Signed

SOUTHERN CONNECTOR Total Parcels – 160 Condemnation Rate – 46%

SC 170 Widening Beaufort County, SC 12.5 mile widening 2 miles of bridges Includes Right of Way Acquisition $80 million RFQ – RFP Process Designer Lawrie & Associates

SC 170 Widening Total Parcels – 129 Condemnation Rate – 23% Total Timeframe – 36 Months

Carolina Bays Parkway Horry County, SC New Location Freeway 22 miles in Length Includes Right of Way Acquisition $232 million RFQ – RFP Process

Carolina Bays Parkway Total Parcels – 74 Condemnation Rate – 46%

Cooper River Bridge Two Bridge Replacements - $ 531 million Charleston, SC

Total Parcels – 93 Condemnation Rate – 19% Timeframe – 60 Months

Accelerated project completion. PROS OF DESIGN BUILD Generally, final cost less than initial cost estimate. Benefit of having facility available to public. Positive public perception.

Reduced timeline for Right of Way acquisition. CONS OF DESIGN BUILD Increased condemnation perception.

R/W acquired and cleared in accordance with Uniform Relocation Assistance and Real Property Policies Act of 1970, as amended, and state R/W procedures. FHWA Requirements R/W certification must be submitted to and approved by FHWA prior to work commencing on individual tracts or entire project.

FHWA Requirements Request for R/W services must be included in request for proposals. Design/Builder must submit written acquisition and relocation procedures to STD for approval; should contain appraisal, acquisition, and relocation strategy.

Role of SCDOT Develop a concise RFP. Provide an on-sight R/W Project Manager as single point of contact with authority to approve all settlements and provide tract certification. Provide constant oversight to insure all federal guidelines are adhered to.

Lessons Learned Assign Project Manager and authorize to approve just compensation, appraisals, relocation, administrative adjustments, etc. Establish “critical path” for construction and stage R/W and relocation accordingly. Identify new methods to handle R/W issues; i.e., purchase of improved property without appraisal including establishment of total benefits to landowner, use of auction company for disposal of 14 homes (less than 3 years old).

Questions