Freeleansite.com The Lean Enterprise Set-up Reduction/ Quick Changeover Lean Foundations Continuous Improvement Training Lean Foundations Continuous Improvement.

Slides:



Advertisements
Similar presentations
Chapter 8 Setup Reduction.
Advertisements

Setup reduction / quick changeover
Introduction to Lean. Benefits of Lean Why go Lean? Improvements in: –Customer service –Quality and efficiency –Staff morale –Internal communication and.
SMED principles applied to Formula 1 racing
Use of Physical Simulation, Computer Simulation and a Common Product in a Series of Courses to Illustrate Industrial and Manufacturing Engineering Technology.
Chapter 3 Planning for Production. Objectives Product oriented manufacturing systems versus people oriented manufacturing systems. Manufacturing smaller.
Lean Manufacturing Cellular Manufacturing One Piece Flow for Workteams
Making your Portable Restroom business Lean and mean – How to boost productivity and increase your bottom line.
An-najah National University
 2000, QualityToolBox.com, LLC, all rights reserved 1 A STRATEGY FOR PERFORMANCE EXCELLENCE ( One Step Setup) Set-up and changeover reductions for equipment,
Just-in-Time and Lean Systems
Just-In-Time “Eliminate Waste”.
Setup Time Reduction Using: Single Minute Exchange of Die G.V. Clarke Lean Quality Assoc., LLC 7/20/20151Copyright-Lean Quality Associates, all rights.
Benefits of Lean Manufacturing: To benefit from Lean Manufacturing, the processes must be maintained consistently and correctly. Everyone involved must.
© ABSL Power Solutions 2007 © STM Quality Limited STM Quality Limited Introduction to Lean Manufacturing TOTAL QUALITY MANAGEMENT Lean Manufacturing.
SETUP IMPROVEMENT. Setup: Definition The setup includes everything, all elements and time from the last good piece of the previous job until the first.
How to Effectively Implement Set-up Reduction in Any Organization.
Setup Reduction Module
Manufacturing Processes Copyright © Texas Education Agency, All rights reserved.
© 2005 Wiley1 Total Quality Management Chapter 5.
Quick Changeovers & SMED
Visual Workplace - A Prerequisite To Becoming World Class
1 Employability skills (a) Employers value people who: fit well into their team and workplace use initiative to solve routine problems work productively.
Chapter 8 Setup Reduction.
Just-in-Time (JIT) and Lean Systems Chapter 7. MGMT 326 Foundations of Operations Introduction Strategy Quality Assurance Facilities Planning & Control.
Value Analysis/ Flow Analysis
Lean Basics Dewey Warden.
JIT and Lean Operations
Single Minute Exchange of Dies
Chapter 4 Process Design.
Quick Changeover Basics This material is provided by Industrial Solutions, Inc. and is intended for internal use only. Any reproduction or re-use outside.
Drill Press 09 Setup Reduction Kaizen Blitz September , 2002 Casey Backyard ProductsDrill Press 09 Setup Reduction Kaizen Blitz.
Single Minute Exchange of Die OR Quick Changeover
Visual Management Quick Review
Lean Manufacturing Chapter 15 pp June 29, 2012.
McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights Reserved. 1 LEAN SYSTEMS TOOLS AND PROCEDURES.
Companies must provide customers with world-class quality, delivery and service. Customers won’t accept anything less. The globalization of markets means.
Yellow Belt Training 10 Step Kaizen Process
“Without the Cost of Waste …”
Lean Training Quick Changeover.
Kaizen Eventing: The process of observation and the elimination of waste in a process.
 Discussion 40 minutes  Break 10 minutes  Discussion 40 minutes  Will understand what Standard Work is, and is not  Will be able to study and understand.
5S and Visual We consider 5S and Visual Controls to be the foundation of Lean Manufacturing systems. 5S and Visual Controls are workplace organizational.
MH...CH LECT-021 SYSTEMS CONCEPT Adopting a materials handling systems from overall optimization point of view. Adopting a materials handling systems.
Top lean six sigma consulting strategies for businesses Lean Six Sigma Manufacturing Consulting By: Group50.com.
LESSON 4 Process Improvement – Lean
Introduction to Motion and Time Study
Mel Wendell – Mountain Pointe High School
Lean Manufacturing Series
Lean operations and JIT
SMED ( One Step Setup) A STRATEGY FOR PERFORMANCE EXCELLENCE
Quick Changeover Single Minute Exchange of Dies
Lean Manufacturing Basic Overview XYZ Company.
Pull Manufacturing and Just In Time
Introduction to Lean Emily Varnado.
Quick Changeover.
Welcome to my presentation
Total Productive Maintenance and Quick Changeover
PLEASE NOTE: freeleansite
SMED ( One Step Setup) A STRATEGY FOR PERFORMANCE EXCELLENCE
Setup Reduction -- Creating More Production Time Dr. Richard A
Quick Changeovers Definitions Analysis and Methods GEOP 4316.
PROJECT SCOPE Scope : SMT Machine in both plant I and plant III.
LEAN IMPLEMENTATION Training SUMMARY OF RESULTS
Work Measurement and Lean Application
Quick Changeover Techniques
SMED ( One Step Setup) A STRATEGY FOR PERFORMANCE EXCELLENCE
Quick Set-Up Technique
Quick Set-Up Technique
Presentation transcript:

freeleansite.com The Lean Enterprise Set-up Reduction/ Quick Changeover Lean Foundations Continuous Improvement Training Lean Foundations Continuous Improvement Training

Introduction to Set-up Reduction / Quick Changeover Concepts based on a technique commonly called ‘SMED’ - Single Minute Exchange of Die

freeleansite.com Understand the concepts and principles of Set- up Reduction. Share some ideas and understand the benefits of Set-up Reduction. Apply the concepts, principles and techniques of SMED to accomplish Quick Changeovers !! Objectives Objectives

freeleansite.com Team Beliefs F Safety comes first F Quality and superior customer satisfaction is our ultimate goal F People are our most valued resource F Blameless environment F Continuous improvement is a way of life F Teamwork (customer, supplier, associates) F Integrity is never compromised F We manage by facts (with data)

freeleansite.com ? What is SMED? SMED stands for: Single Minute Exchange of Die Ideally, set-up time should be anything less than 10 minutes … Decreased set-up time;  reduces the need for inventory,  provides more flexibility and capacity,  enables us to better serve our customer!

freeleansite.com Benefits of Quick Changeover Less adjustments means less chance for errors Elimination of trial processing reduces material waste Preparation of operating conditions in advance helps stabilize product quality Increases scheduling flexibility/capacity Reduces need for on-hand inventory Improved service levels for customers Smaller runs means less likelihood of large scale defect problems in inventory

freeleansite.com Set-up Time Dies Tools Materials First Good Piece Last Good Piece Total elapsed Time Fixtures

freeleansite.com Set-up Time any set-up time can be reduced by 59/60ths! Shigeo Shingo (wrote the book on SMED…) believed that:

freeleansite.com Set-up Time There are two types of setup time: Internal Set-up: Those activities that must be performed while the machine is shut down. (Work content done in addition to Machine Time.) Example: Removing dies and tooling External Set-up: Those activities that are performed while the machine is operating. Example: Preparing tooling for the next set-up

freeleansite.com Set-up Reduction Process 1.Observe and document the current set-up. 2.Separate Internal and External elements. 3.Improve each element. 4.Observe and document the new set-up process. 5.Standardize the new set-up procedure. 6.Celebrate your success!!

freeleansite.com Observe and Document the Current Set Up A.Select a specific set-up for improvement B.Identify a set-up “kaizen” team. C.Observe the set-up process: Video Record the set-up process Complete the Set-up Operations Analysis chart (before Kaizen). D.Prepare a Pareto chart for each time category.

Record and Recommend During this phase we: Observe and document the existing set-up procedure using Time Observation and Video Recording techniques - Analyze all work efforts - Identify short-term solutions that can be implemented with procedural changes, modifications to existing fixtures and minor investment in tooling

Video Recording Tips  Collect background data  Select regular production “Parts”  Determine equipment and operation  Prepare/Evaluate site  Where does operator stand?  Where is the best position for the camera?  Is there adequate lighting?  Narrate  Describe what is happening when the operator blocks the camera or leaves the area.

Analyze the Time Observation & Video  Review Time Observation and Video with the team  Identify opportunities  Internal vs. External  Value Added Vs Non-Value Added  Normal vs. Abnormal  Seven Types of Waste  Automatic, Manual, Walking,  and Waiting times  Solicit ideas for countermeasures / improvements

freeleansite.com Observe and Document the Current Set Up

freeleansite.com Observe and Document the Current Set-up Searching - Looking for tools, jigs, fixtures, etc. Fixture Change - Replacing one fixture with another Tool Change - Replacing existing tooling Programming - Making adjustments or changes to a CNC program in order to accommodate the new set-up Walk time - The time an operator must walk to retrieve a fixture, tools etc. 1st Piece - The time required to produce a good unit after the initial set-up Gage - The time required to qualify the 1st piece

freeleansite.com Pareto Analysis on each Time Category

freeleansite.com Separate the Elements Internal: Those activities that must be performed while the machine is shut down. Example: Removing dies and tooling External: Those activities that are performed while the machine is operating. Example: Acquire fixture/tools for next set-up Both types of actions must be separated. Once the machine is stopped, the associate should never depart to perform any part of the external set up.

freeleansite.com Separate the Elements

freeleansite.com Develop Improvement Plan 5S +1 (6S) discipline is the key to quick changeover! Every minute spent looking for tools, fixtures, drawings, dies, jigs or other materials adds to the set-up time. A strong 5S foundation, with a ‘point-of-use’ (POU) methodology, will ensure that all required materials are in place when needed, are clean, and in working condition.

freeleansite.com Develop Improvement Plan Remember the ‘Wastes’ ? (refer to the 7W’s)  Defects  Over-Production (inventory)  Transportation  Waiting  Inspection (mass)  Motion  Processing, itself  + “Unused Creativity” Storage area for Dies Tool Cart Punch Press Tool Room

freeleansite.com Develop Improvement Plan Specifically: A.Convert as much of the internal set up to the external set up. B.Eliminate or reduce the internal and external set up. C.Eliminate the adjustment process. Ultimate Goal: Eliminate Set-up!

freeleansite.com Steps: Reduce internal work gradually – eliminate unecessary work measureseparatereduce/eliminate convert internal external (repeat)

freeleansite.com Employ Improvement Initiatives Once as much of the internal set-up has been converted to external set-up and waste has been eliminated: –standardize the external set-up actions –utilize quick fasteners –use supplementary tools – at the ‘point of use’ (POU)

freeleansite.com Employ Improvement Initiatives Developing the Improvement Plan: What must be done while the machine is shut down?  What can be done while the machine is running?  Challenge every element in the set-up !  Establish a sound 6S (5S+1) foundation.

freeleansite.com Improvement Checklist – an example  Station tools, jigs, dies, etc. near the machine. (POU)  Assure that all jigs, gauges, dies, tools, etc. function before the set-up begins.  Perform as many External elements as possible prior to the set-up.  Two people working together may reduce net set-up time  Use functional clamps: One turn/ One motion  Use visual control to eliminate adjustments.

Application Best Practices 1)Make minor modification to the existing fixtures. 2)Implement Point-of-Use (POU) techniques. 3)Identify additional tooling to remove attachment from internal to external. 4)Adopt standardized tooling. 5) Document time savings.

Application Best Practices - Continued For example:  Slots in fixture and T-Bolts reduce attachment time.  A new part holder reduced the time required to load and unload parts to fixture. Swing hook eliminated the need to remove nut from bolt.  Extra set slides allow detach to be completed on external time.

freeleansite.com Other ideas 1. Quick Changeover begins and ends with the 5S’s. 2.Change the Internal set-up into External, then improve the remaining Internal set-up time. 3. Bolts are our Enemies. 4.If you have to use your hands make sure your feet stay put. 5.Don’t rely on Special Fine-tuning skills. 6.Standards are standard: they are NOT flexible. 7.Standardize all SMED Operations

freeleansite.com Ideas The die heights of a punch press or molding machine can be standardized by using the liner (spacer) so that stroke adjustment will be unnecessary. Source: Toyota Production System - Yasuhiro Minden

freeleansite.com Ideas Examples of Quick Fasteners Usually a bolt is the most popular fastening tool. But because a bolt fastens at the final turning of the nut can loosen at the first turn, a convenient fastening tool that would allow only a single turning of the nut should be devised. Source: Toyota Production System - Yasuhiro Minden

freeleansite.com Ideas

Ideas

For example:  A slide clamp reduced the time required to load and unload parts to fixture.  2 hold-down clamps eliminated the need to tape parts during a glue-up operation.  Set slide allows quick (temporary) alignment of 2 parts. Ideas

freeleansite.com Document the New Set-up A. List each element on the Set-up Operations Standard Chart (after Kaizen) B. Video tape the new set-up procedure. C.Record the set-up time for each element D.Note areas for future improvement.

freeleansite.com Standardize the New Procedure

freeleansite.com Standardize the New Procedure The Set-up Operations Standard chart will become the basis for the new set-up procedure. Prepare the appropriate detail and work instructions that will be included on the Set- up Operations Standard chart. Assure that all appropriate personnel are trained in the new procedure.

freeleansite.com The Lean Enterprise Set-up Reduction/ Quick Changeover Lean Foundations Continuous Improvement Training Lean Foundations Continuous Improvement Training