HiLumi P1/P5, Cryogenic interfaces for sc links, DFX 2nd review

Slides:



Advertisements
Similar presentations
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Advertisements

RHIC CRYOGENICS SYSTEM Time meeting /28/20141TIME MEETING RUN 14 –CRYOGENIC.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Internal Cryomodule Instrumentation ERL Main Linac Cryomodule 10/10/2015 Peter Quigley, MLC Design Review.
Cryomodule Helium Vessel Pressure -- a Few Additional Comments Tom Peterson 18 November 2007.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
1 HIGH ENERGY ACCELERATOR RESEARCH ORGANIZATION KEKB Review Committee/ NAKAI Hirotaka KEK Crab Cavity - Cryogenics - KEKB Crab Cavity Group - presented.
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Performance analysis of cryogenic system and cryomodules for the complete superconducting linear accelerator at IUAC, New Delhi. T S Datta ( On behalf.
1 ESS Cryogenic regulation loops proposal  Thermal shield  Power Couplers double-wall  CM cool down  Stand by and nominal operation  CM warm up Bertrand.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
The cryogenic system of the HIE-ISOLDE project and its related hazards for persons N. Delruelle on behalf of the TE/CRG group HIE-ISOLDE Safety Review.
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Rossana Bonomi R. Bonomi TE-MSC-CMI SPL Seminar 2012.
Cryogenic Summary - K. C. Wu Testing D2L102 in MAGCOOLJune, 02 Difference between D2L102 and D2L101 Operating Summary Cooldown to 100 K and 6 K Test Condition.
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
The SPL Short Cryo-module: Status Report V.Parma, CERN, TE-MSC On bahalf of the Cryomodule development team SPL seminar December 2012, 6-7 December 2012,
Crab cavities – cryogenics for SPS and LHC LHC-CC13, 6 th LHC Crab Cavity Workshop – CERN, Geneva, Switzerland 9-11 December 2013 K. Brodzinski on behalf.
Page 1 CRYOMODULE 650 (TESLA Style) Stand Alone Tom Peterson and Yuriy Orlov Collaboration Meeting 25 Jan 2011.
Ralf Eichhorn CLASSE, Cornell University. I will not talk about: Cavities (Nick and Sam did this) HOM absorbers (did that yesterday) Power couplers (see.
LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved.
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Overview of elliptical cryomodules vacuum system Vacuum Equipment Standardization meeting February 2014 P. Bosland – C. Darve – N. Elias.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
ESS | Helium Distribution | | Torsten Koettig Linac – Helium distribution 1.
Teleconf ACS – FREIA 28th March 2017
SPL RF coupler: integration aspects
CERN – Zanon discussions
Crab cavities Cryogenics progress for the SPS
HL-LHC IT STRING and Series test of SC link
IT-4189 Supply and installation of a cryogenic distribution system
T5.2: Harmonization - Material and Component Reference
HFM Test Station Main Cryostat
Innovative He cycle Francois Millet.
Feasibility and implication of installation of the string test in SM18 with a slope M. Bajko WP16.
Status of cryostat integration and conceptual design
SPS cryogenic proximity equipment and SM18 validation
S. Claudet, Daniel Berkowitz & A. Perin (TE-CRG)
Functional interfaces
Cryogenics for sc links, a short update
Hollow e- lens, Cryogenic aspects
CERN Cryomodule Requirements for Crab Cavities
The HIE—ISOLDE Cryogenic System, its Infrastructure and Considerations for Phase 3 O. Pirotte (TE/CRG)
Cryostat design Mechanical design: Thermal screens: Specifications:
Operation experience of cryogenic system and cryomodules for the superconducting linear accelerator at IUAC, New Delhi. T S Datta ( On behalf of Cryogenics.
ESS elliptical cryomodule
SNS PPU Cryomodule Instrumentation
Cryomodules Challenges for PERLE
CEPC-650MHz Cavity Cryomodule
WP11: CDS-SL CDR Overview
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Summary post TCC#54_02Aug’18
DFX safety aspects in the LHC tunnel
Burst Disc Experiences at CEA Test Stand
HL-LHC New MS optimisation WP9, Preliminary cost estimates
J. Fleiter, S. C. Hopkins, A. Ballarino
HL-LHC Post MSO optimisation, Complementary considerations for Q4
Presentation transcript:

HiLumi P1/P5, Cryogenic interfaces for sc links, DFX 2nd review S. Claudet / A. Perin, 20Jun’19 With contribution from: Michele Sisti, Jos Metselaar

Content Presentation limited to what has changed for Cryogenics since Review held in January 2019 Double concentric bath system LHe level gauges required for both bath (Delta P for internal, supra for outer) + position of electrical heaters and thermometers on LHe vessel clarified (low point + LHe nominal interface) No more thermal shield in DFX, but E-F required for “GHe heater” Jumper vacuum jacket could be reduced w.r.t 380mm standard LHC jumpers, DN200/250 should do the job - Mechanical interface being defined and integrated Recently Identified “Low” design pressure, with global Delta P to be looked at from DFX to WRL. Particular attention to choice of overpressure protection. All these points are considered in following talks and presentations SC/APe - 20Jun'19 HiLumi P1/P5, Cryo interfaces for sc links, DFX

HiLumi P1/P5, Cryo interfaces for sc links, DFX IT nominal 1.9 K Actuators: JT valves Outlet CVs for shield and beam screen Sensors: TT phase separators EH cold mass TT outlet shield and beam screen Updated P & F diagram, considered here for nominal operation mode SC/APe - 20Jun'19 HiLumi P1/P5, Cryo interfaces for sc links, DFX

Summary Since January 2019, continued team effort to properly define and assess LHe volumes, => OK by now Interface with QXL jumper as last mechanical interface to be finalised together, with concept identified (above QXL) Operational pressure range now identified, possibly as small as present LHC RF cryomodules, => it works but it is very sensitive to pressure fluctuations Thank you for your attention ! SC/APe - 20Jun'19 HiLumi P1/P5, Cryo interfaces for sc links, DFX