Tuesday 20 September 2011.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday
Machine Coordinators: G. Arduini, J. Wenninger
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Wednesday September 14th
Monday :00 Stable beams 9_6_6_6 13:40 Access.
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
Monday fill with 1092 bunches (6 h stable beams)
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
LHC Morning Meeting - G. Arduini
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Monday 6th August & night
Summary of Week 11: 14 – 21 March
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary of Week 13 G. Arduini, B. Holzer
Summary of Week 16 G. Arduini, J. Wenninger
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Coordination by E. B. Holzer & J. Wenninger Production
Friday 31st August & night
Thursday 10th May - morning
Saturday 2/4/ :00-09:00 Problems with SPS:
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Week 35 – Technical Stop and Restart
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Finally.... We had to wait a long time.... We had many problems....
Tuesday 22 November 2011.
Friday Morning 7:30 injection for fill 2908
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Sunday
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
LHC Morning Meeting - G. Arduini
Programme for Saturday 10 July
Monday – Morning Fill 3265 stable beams since 1:31
LHC Morning Meeting - G. Arduini
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Thursday – Morning Energy matching at injection with H CODs
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Thursday 22 September 2011.
Polarity inversion 07:00 ALICE solenoid and dipole polarity switched to positive External Crossing angle polarity unchanged at injection/ramp & squeeze.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Tuesday In the morning test cycle with probe for Q’ measurement.
Sat 15/10 New record bunch population profiting of the scrubbing period on Friday. Nb~1.42x1011p/bunch  110 MJ at 3.5 TeV. Filling slowed down by ZS sparking.
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
Thursday 30th September De-bunching test
Saturday 24 September 2011.
Mon 2/4 08:00-13:00: Access for: Experiments Power converters BBQ
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Monday 27th August & night
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Friday During the night from Thursday to Friday: by mistake, SPS longitudinal blow-up was not active  Smaller transverse emittance from the.
Saturday 26 November 2011.
Thursday 10:00 Fill 1986 in stable beams.
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Tuesday
Presentation transcript:

Tuesday 20 September 2011

Fill # 2129 Stable beams: 10:05 – 20:27 (RF trip of Line 2B1 – probably noise on a sensor) Peak lumi: 3.25 1033 cm-2s Delivered Lumi: 78 pb-1 Test of e-cloud solenoid installed last week at recombination area right of IP2: The test of the changes in current are inconclusive (no significant pressure change observed) Either the solenoid has no effect, or the field was not strong enough to give a noticeable effect ( ie if it is a threshold issue)  The situation is to be followed up by the vacuum team

RF Intervention (Monday) P. Baudrenghien: “We have solved the problem with klystron 5B2 that was pushed close to saturation power (> 200 kW) at the start of flat top. The problem was with the circulator: we fine-tuned the regulation of the ferrite current with temperature. We have also fine-adjusted the cavity tune. After that, the power was reduced to ~ 160 kW. Klystron 5B2 output power and beam2 intensity for the last fills that made it thru ramping. The peak power is reduced from 220 kW (Fill 2124, before intervention) to 170 kW (fills 2126-2129, after intervention).

Issues MKI data missing for 1 injection of B1 MKI point 8 kicker fall time – to be checked by experts Problem with B2 tune measurement on the ‘continuous’ system Investigation ongoing Tune feedback B1 switched itself off and tune feedback B2 was switched off during for the squeeze from 1.5m to 1m (horizontal tunes manually adjusted by -0.005 for both beams) BLMs > 30% of dump level at > 5s integration times: MQX in IP1 and IP5 threshold increase pending Alice background problems (vacuum)

Vacuum left of IP2

Vacuum stabilizing (14:30) at ~2E-8 mbar Left of IP2 Right of IP8

Debunching – abort gap population – beam losses P. Baudrenghien: “Yesterday we access UX45 and replaced the RF modulator card on Cav1B1. (This module had a problem 9 days ago – Friday 7 th – that was traced to a bad cable but we wanted to make sure that it was not the module’s connector). Being in a hurry we did not adjust the phasing of the clocks carefully enough and this placed one of the LLRF loop close to instability. The “klystron polar loop” became unstable ~ 12:00 to-day, showing very large effect on voltage (dropped from 1.5 MV to below 1 MV), activity on phase loop, detuning of the cavity but barely any effect on the lifetime as the noise frequency was outside the Beam response (see attached fig). When we tried to cure it around 14:00, we restored the cavity field/tune but moved the noise spectrum close to the beam response, resulting in large debunching ~14:00 (1.2E11 p in abort gap corresponding to ~ 3.6E12 unbunched beam). The loss were stopped after opening the offending LLRF loop. Notice that the loss B1 resulted in very similar (although ~ twice smaller) loss in B2. There is no hardware coupling. We then worked parasitically to solve the problem with the Klystron Polar Loop and have now restored it to normal state. Nothing special to be done for next fill.”

Beam Losses of the unbunched beam TCTs right of IP1 and left of IP5 and right of IP8 getting close to dump level (up to 65%)  Problematic as we got close to dumping the beam with the abort gap still heavily populated

Losses TCT R8, R1 and L5 Losses TCP IP3 Losses TCP IP7 Losses TCT R8 Losses TCT R1 and L5

Night Tuesday to Wednesday Fill # 2130 and # 2131 dumped by vacuum left of IP2 (average bunch intensity 1.41E11)

 solenoid current 4L2 increased to 5A Fill # 2132: 30 minutes scrubbing at 450 GeV (amplitude of spikes going down)

Average bunch Intensity reduced to 1.3E11 Fill # 2133 and # 2134 dumped by vacuum spike left of IP2