Johnson’s Rule Johnson’s rule: A procedure that minimizes makespan when scheduling a group of jobs on two workstations. Step 1. Find the shortest processing.
Advertisements

Scheduling.
Scheduling for Low-volume Operations Chapter 15 Operations Management by R. Dan Reid & Nada R. Sanders 2nd Edition © Wiley 2005 PowerPoint Presentation.
© The McGraw-Hill Companies, Inc., 1998 Irwin/McGraw-Hill Module 11 Operations Scheduling Chapter 16 (pp ) Work Center and definitions  Objectives.
Operations Management For Competitive Advantage 1 Operations Scheduling Operations Management For Competitive Advantage Chapter 15.
Operations Scheduling
Scheduling.
Operations Scheduling
PowerPoint presentation to accompany Operations Management, 6E (Heizer & Render) © 2001 by Prentice Hall, Inc., Upper Saddle River, N.J Operations.
1-1 McGraw-Hill/Irwin ©2009 The McGraw-Hill Companies, All Rights Reserved 1 Chapter 19 Operations Scheduling.
Operations Scheduling
Scheduling. Production Planning Process Process Planning Strategic Capacity Planning Aggregate Planning Master Production Scheduling Material Requirements.
Scheduling Chapter 19.
Operations Management
Scheduling. Characteristics of a “job” Constituent operations Constituent operations Due date Due date Time of arrival in shop Time of arrival in shop.
Order Processing and Information Systems 1 Chapter 5 Order processing and information systems The cost of providing timely and accurate information has.
Scheduling.
1 ISQA 459/559 Mellie Pullman Scheduling Shop Floor.
1 Chapter 15 Scheduling. 2 Scheduling: Establishing the timing of the use of equipment, facilities and human activities in an organization Answering “when”
Scheduling – Day 2. Production Planning Process Process Planning Strategic Capacity Planning Aggregate Planning Master Production Scheduling Material.
CHAPTER 19 Scheduling Operations Management, Eighth Edition, by William J. Stevenson Copyright © 2005 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 16: Learning Objectives
JIT and Lean Operations
Operations Scheduling. Scheduling in a Process-Focused Environment.
Industrial Systems Engineering Dept. İzmir University of Economics
Chapter 16 Scheduling McGraw-Hill/Irwin Copyright © 2012 by The McGraw-Hill Companies, Inc. All rights reserved.
1. Facility size 2. Equipment procurement Long-term
Copyright 2009, John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Scheduling Operations Management - 5 th Edition Chapter 17.
Scheduling.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 16 Scheduling.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 16 Scheduling.
15-1Scheduling William J. Stevenson Operations Management 8 th edition.
15-1Scheduling William J. Stevenson Operations Management 8 th edition.
15-1Scheduling Operations Scheduling Chapter Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 16 Scheduling.
1 1 Slide Short – Term Scheduling Professor Ahmadi.
Scheduling Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Scheduling Process and Production Management.
Topics To Be Covered 1. Tasks of a Shop Control Manager.
Operations Management Operations Scheduling
1 Slides used in class may be different from slides in student pack Chapter 19 Operations Scheduling  Work Center Defined  Typical Scheduling and Control.
Scheduling for Low-volume Operations Chapter 15 Operations Management by R. Dan Reid & Nada R. Sanders 2nd Edition © Wiley 2005 PowerPoint Presentation.
Chapter 17 Scheduling. Management 3620Chapter 17 Schedule17-2 Overview of Production Planning Hierarchy Capacity Planning 1. Facility size 2. Equipment.
1 Manufacturing Operations Scheduling B2 [ ] B2 [ ] E5 [ E5 [ P9 [---] P9 [---] D1 [ D1 [
Scheduling. Definition of scheduling Establishing the timing of the use of equipment, facilities and human activities in an organization In the decision-making.
Scheduling. Scheduling: The allocation of resources over time to accomplish specific tasks. Demand scheduling: A type of scheduling whereby customers.
Scheduling for Low-volume Operations
CHAPTER SEVENTEEN SCHEDULING Chapter 17 Scheduling.
Scheduling Seminar exercises Process and Production Management.
CHAPTER 4 : SCHEDULING Presented by: HAMKA BIN TAIP
Scheduling Operations IDS 605 Spring Data Collection for Scheduling l Jobs l Activities l Employees l Equipment l Facilities Transparency 18.1.
Chapter 16 & 9 Scheduling Work & Employees. Scheduling Outline What needs to be scheduled? –doctor’s office, restaurant, mfg. plant, hospital –employees.
Scheduling.
Scheduling Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill.
Chapter 16: Learning Objectives Instructor Slides You should be able to: 1.Explain what scheduling involves and the importance of good scheduling 2.Describe.
16 Scheduling (focus on sequencing; FCFS, SPT, EDD pages , and Johnson’s rule pages ) Homework; 6, 7, 11.
Chapter 5 Order Processing
Production Activity Control
Scheduling Operations
Chapter 15 Scheduling McGraw-Hill/Irwin
CHAPTER 8 Operations Scheduling
assemble-to-order (ATO) A system that produces standard modules to be
Production Activity Control
OPERATIONS SCHEDULING AND SEQUENCING
Short-Term Scheduling
Chap 11 Learning Objectives
8 Job Sequencing & Operations Scheduling CHAPTER Arranged by
Sequencing Sequencing: Determine the order in which jobs at a work center will be processed. Workstation: An area where one person works, usually with.
Production and Operations Management
Inputs and Outputs to Aggregate Production Planning
Presentation transcript:

Scheduling Seminar exercises 2010.10.14 Process and Production Management

Scheduling Estabilishing the timing of the use of equipment, facilities and human activities in an organization. High volume systems (characterized by standardized equipment and activities that provide identical or highly similar operations on products – autos, personnal computers, radios, TVs) Intermediate – volume systems (ouput fall between the standardized type of output of the high volume systems and made-to-order output of job shops. Work centers periodically shift from one product to another, but lot size relatively high. Low-volume systems (products are made to order, and orders differ in terms of processing requirements, materials needed, processing time.)

Priority rules Select the order in which job will be processed First come first served (FCFS) – jobs are processed in the order which they arrive at a machine or work center Shortest processing time (SPD) – according to processing time, shortest job first Earliest due date (EDD) – according to due date, earliest due date first. Critical ratio (CR) – smallest ratio of time remaining until due date to processing time remaining.

Assumptions The set of jobs is known Setup time is independent of processing sequence Setup time is deterministic Process time are deterministic There will be no interruptions in processing such as machine breakdowns, accidents, or workes illness.

Processing time (days) Example 1 Determine the sequence of jobs/products Determine average flow time Determine average tardiness Determine average number of jobs at the workcenter Job/ product Processing time (days) Due date (days) A 2 7 B 8 16 C 4 D 10 17 E 5 15 F 12 18

Job flow time – the length of time a job is at a particular workstation or work center. (it includes not only procesing time, but waiting time, transportation time) Average flow time = total flow time /number of jobs Job lateness – length of time the job completion date is exceed the date the job was due to promised to the customer Average tardiness=total lateness/number of products Makespan – is the total time needed to complete a group of jobs (time between start the first and completion of the last one) Average number of jobs=total flow time/makespan (it reflects the average work-in-process inventory if the jobs represent equal amount of inventory)

FCFS ABCDEF Aft=120/6=20 days At=54/6=9 days Job/ product Processin time (days) Due date (days) (2) Flow time (3) Days tardy (0 if negative) (3)-(2) A 2 7 2-7=-50 B 8 16 2+8=10 10-16=-60 C 4 10+4=14 14-4=10 D 10 17 14+10=24 25-17=7 E 5 15 24+5=29 29-15=14 F 12 18 29+12=41 41-18=23 41 120 54 Aft=120/6=20 days At=54/6=9 days M=41  Aj=120/41=2,93 pieces

 ACEBDF SPT Aft=108/6=18 days At=40/6=6,67 days Aj=108/41=2,63 pieces Job/ product Processin time (days) Due date (days) (2) Flow time (3) Days tardy (0 if negative) (3)-(2) A 2 7 2-7=-50 C 4 2+4=6 6-4=2 E 5 15 5+6=11 11-15=-40 B 8 16 11+8=19 19-16=3 D 10 17 19+10=29 29-17=12 F 12 18 29+12=41 41-18=23 41 108 40 Aft=108/6=18 days At=40/6=6,67 days Aj=108/41=2,63 pieces

EDD CAEBDF Aft=110/6=18,33 days At=38/6=6,33 days Job/ product Processin time (days) Due date (days) (2) Flow time (3) Days tardy (0 if negative) (3)-(2) C 4 4-4=0 A 2 7 4+2=6 6-7=-10 E 5 15 5+6=11 11-15=-40 B 8 16 11+8=19 19-16=3 D 10 17 19+10=29 29-17=12 F 12 18 29+12=41 41-18=23 41 110 38 Aft=110/6=18,33 days At=38/6=6,33 days Aj=110/41=2,68 pieces

CR ??? Job/ product Processin time (days) Due date (days) (2) CR0 A 2 Remaining time untill due to dat (on the 0th day) Job/ product Processin time (days) Due date (days) (2) CR0 A 2 7 (7-0)/2=3,5 B 8 16 (16-0)/8=2 C 4 (4-0)/4=1 D 10 17 (17-0)10=1,7 E 5 15 (15-0)/5=3 F 12 18 (18-0)/12=1,5 41 CR4 (7-4)/2=1,5 (16-4)/8=1,5 ------- (17-4)/10=1,3 (15-4)/5=2,2 (18-4)/12=1,17 1. 2.

Job/ product CR16 A (7-16)/2=-4,5 B (16-16)/8=0 C ------- D (17-16)/10=0,1 E (15-16)/5=-0,2 F ----- CR23 -------- (16-23)/8=-0,875 ------- (17-23)/10=-0,6 --------- CR18 -------- (16-18)/8=-0,25 ------- (17-18)/10=-0,1 (15-18)/5=-0,6 --------- 3. 4. 1. 5. 4. 2.

CRCFAEBD Aft=133/6=22,16 days At=58/6=9,66 days Aj=133/41=3,24 pieces Job/ product Processin time (days) Due date (days) (2) C 4 F 12 18 A 2 7 E 5 15 B 8 16 D 10 17 41 Flow time (3) 4 4+12=16 16+2=18 18+5=23 23+8=31 31+10=41 133 Days tardy (0 if negative) (3)-(2) 4-4=0 16-18=-20 18-7=11 23-15=8 31-16=15 41-17=24 58 Aft=133/6=22,16 days At=58/6=9,66 days Aj=133/41=3,24 pieces

Sequencing Jobs through two Work Center Job time is known and constant Job time is independent of job sequence All job must follow the same two-step job sequence Job priorities cannot be used All units must be completed at the first work center before moving on to the second work center

Example 2 E C F A B D Select the job with the shortest time. If the shortest time at first wc, schedule that job first. If the time at the 2nd wc, schedule the work last. Eliminate the job and its time from further consideration Repeat steps Job/ product #1 #2 A 5 B 4 3 C 8 9 D 2 7 E 6 F 12 15 E C F A B D

Chart 2 8 16 28 33 37 #1 D E C F A B #2 D E C F A B 2 9 17 26 28 43 48 51 Idle time Flow time: 51 hours