Cryomodule Assembly Plan

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

ATD Assembly. ATD Assembly #1 Dewar Assembly #1 Status: Dewar has been completely assembled and vacuum tested. No vacuum leaks were detected on the outer.
1.  Preparation of larger parts in a Clean room Class (ISO7)  Preparation of smaller parts in a “baldaquin” annex  Assembly in a clean-room Class.
Elvin Harms, Tom Peterson, Yuriy Orlov, Frank McConoloque.
Progress and Plan for Superconducting RF Cavity RF Group.
AMS-02 Cryosystem Phase III Flight Safety Review January 12, 2010 Phil Mott.
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009.
CRYO PIPING & INTER-MODULE CONNECTIONS Yun He, Daniel Sabol, Joe Conway External Review of MLC Daniel Sabol, MLC External Review 10/3/2012.
Internal Cryomodule Instrumentation Sensors, Actuators, Heaters, and Wiring ERL Main Linac Cryomodule 9/5/2012 Peter Quigley Internal Design Review.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
Assembly, Installation and Interfaces Steve Virostek Lawrence Berkeley National Lab RFCC Module Design Review October 21, 2008.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
LCLS-II cryomodule alignment. 2 Wednesday meeting, 6/17/2015 Topics Alignment of Components inside the CM Tunnel Network Tolerances LCLS-II cryomodule.
FNAL Cavities for S1 Global Jim Kerby ALCPG 09. FNAL Deliverables Discussed in meetings 15/16 July and 10/11 Sept, and Webex and s 9/30/20092FNAL.
Refurbished Booster RF John Reid October 24, 2012.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
56 MHz SRF Cavity Thermal Analysis and Vacuum Chamber Strength C. Pai
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
Installation of the T600 at Fermilab CSN2, September 22,
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
CM2 Repair Status 8/13/2012 Tug Arkan 1. Latest Status After the warm end couplers were disassembled, it was decided to disassemble all the lower aluminum.
Cryomodule Assembly Facility (CAF) at Fermilab Tug Arkan (FNAL) FNAL-LBNL joint meeting on SRF Cavities and Cryomodules March 15, 2012.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Ralf Eichhorn CLASSE, Cornell University. I will not talk about: Cavities (Nick and Sam did this) HOM absorbers (did that yesterday) Power couplers (see.
Cryomodule Assembly Facility Fermilab Cleanroom: Assembly/Disassembly Tools Tug Arkan 1.
FNAL Cryomodule Assembly and Installation Plans Tug Arkan May 22, 2015.
MICE Coupling Coil Fabrication Steps to Complete Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe 3/7/
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
F LESEIGNEUR / G OLIVIER LUND January 9th, ESS HIGH BETA CRYOMODULE ESS CRYOMODULE STATUS MEETING HIGH BETA CRYOMODULE LUND JANUARY 9TH, 2013 Unité.
HIE ISOLDE Linac Short Technical Description W. Venturini Delsolaro Material from: L. Alberty, J. Bauche, Y. Leclerq, R. Mompo, D. Valuch, D. Voulot, P.
12 GeV Project Status Glenn R. Young 12 GeV Project Status
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
TDR guideline discussion on Cavity Integration
CERN – Zanon discussions
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
Overview of Mechanical Design
LARP Vertical Test Facility
The 11T cryo-assembly: summary of design and integration aspects
KEK injector cryomodule
IMP Cryomodule Assembly and Alignment
Alignment of Main Linac Cryomodule (MLC)
SNS PPU Cryomodule Instrumentation
CEPC-650MHz Cavity Cryomodule
SNS PPU Helium Vessel Design and Assembly
CRYOMODULE FINAL ASSEMBLY
SNS PPU Cryomodule Thermal Shield
SNS PPU Cryomodule Vacuum Vessel
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Magnetic Shields
SNS PPU Cryomodule Instrumentation
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Thermal Shield & MLI
SNS PPU CRYOMODULE FDR Magnetic Shields Gary Cheng June 10, 2019.
SC1R Cold Box PDR Assembly Sequence
SNS PPU Cryomodule Design Overview
CRYOMODULE FINAL ASSEMBLY
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

Cryomodule Assembly Plan SNS PPU CRYOMODULE PDR Cryomodule Assembly Plan Kurt Macha Mark Wiseman Wednesday, February 27, 2019

Outline Four major assembly steps Clean Room Assembly (earlier talk by K. Wilson) Cold Mass Assembly Thermal Shield/Space Frame Assembly Cryomodule Final assembly Will go through each of the assemblies showing a combination of old photos and CAD images Current assembly plan is based on the original SNS CM build plan Will highlight planned changes from the original plan with new tooling requirements

Cavity string transfer to cryomodule assembly Maintain and monitor the cavity vacuum via an ion pump Warm to cold beam-pipe bellows will be included in the clean room assembly

Cold mass assembly Cryogenic piping and leak testing 2K circuit 5K FPC 4K piping to HX Tuner installation Liquid level & Heaters Wiring & 2k heat stationing Diodes Mounting & 2k heat stationing Primary magnetic shielding Install coupler bellows & leak test 2k insulation

2K circuit welding Where possible orbital welding may be used Increased quality of welds Saves production time Reduces risk of leaks

Spaceframe/ thermal shield assembly Transfer the cavity string into the spaceframe and remove the lollipop tooling

Preparation for string transfer to spaceframe Install the shield into the spaceframe Assemble the spaceframe/ shield onto the rail tooling Support in proper locations and observe deflections for alignment concerns Leak test the thermal shield Insulate the 50k shield Axial restraint rods get inserted loosely Slide the spaceframe over the cavity string assembly Use caution around the couplers, the interferences will need attention Ensure the coupler ceramic windows are protected Protect the coupler bellows Spaceframe tooling

Transfer of the string load to the spaceframe Install the axial and radial nitronic rods Carefully tension the nitronic rods to ensure minimal beam-line movement during load transfer Remove the lollipops Track the beamline movement with dial indicators Install the lower spaceframe ring ties

Cavity string alignment Align the cavity string One arm alignment arms mounted on the cavity flange and leveled using a precision level Target at the and of the arm will have a target that can be sighted for adjustment into position Alignment Arm

Routing and heat stationing of instrumentation The RF cables require routing from the 50k shield out of the insulation Diode wiring will be routed Heater and liquid level wiring will be staged at the ends for further routing Instrumentation verification check TDR checks for the RF cables Diodes will receive meter verification to ensure no shorts

Final spaceframe assembly Install the bottom thermal shield panels and MLI patches Run and weld the coupler exhaust connections Inspect and leak test connections Install the outer magnetic shield onto the spaceframe Test fit spaceframe lockdowns Ensure proper clearances around the couplers

Vacuum vessel / end can assembly Install the vacuum vessel onto carriage assemblies and stage next to the spaceframe Vacuum Vessel Tooling Portable Rail Cart

Spaceframe insertion into the vacuum vessel Roll the spaceframe into the vacuum vessel

Alignment of the spaceframe into the vacuum vessel Center BL Flange To Vacuum Vessel Flange Align the spaceframe in the center of the vacuum vessel Investigating differential screws for fine adjustment Install and secure all lockdowns Final welding and leak test of the 5K coupler circuit Fiducialize the vacuum vessel to reference beam center Crane the vacuum vessel assembly to a new work center, install saddles and set the assembly on concrete blocks

End can installation Secure each end can to the vacuum vessel New tooling will hold and adjust the end cans to the vacuum vessel until secured Bayonets will be properly positioned allowing the bellows, rotatable flange and interface block to give compliance The vacuum vessel end plates will remain off to allow installation of 2k, 4k and shield piping. After the piping is welded and leak tested, the end cap thermal, Mu shielding and MLI will be installed. Install the top-hats Supply End Can Return End Can

Beamline assembly Install the end can plates to seal the ends of the vacuum vessel Install the final beam line sections using portable clean room work spaces Extra precautions to ensure reduced particulate. Slow pump and slow backfills will be done using improved equipment and procedures

Vacuum vessel final Final wiring and instrumentation check Test run stepper motors Install the JT actuators and test Final Alignment verification Close all vacuum vessel ports Vacuum vessel evacuation and leak test Pressure test the inner circuits as part of the final leak test (Leak detector on insulating vacuum)

Conclusion New tooling will be needed for end can installation Kurt Macha Mark Wiseman Conclusion New tooling will be needed for end can installation Most procedures are in place from the original build Main difference is the end can installation and end sections of the vacuum vessel The alignment of the spaceframe is more critical due to no beamline adjustment at the ends