MAY 10, 2012 | NEPOOL MARKETS COMMITTEE WESTBOROUGH, MA Andrew Gillespie PRINCIPAL ANALYST | MARKET DEVELOPMENT Proposal Static De-List Bid Changes.

Slides:



Advertisements
Similar presentations
Proposal For Improvement to the Current ICAP Market Markets Committee October 12, 2004 Ken Bekman Con Edison Energy.
Advertisements

Proposal Routing, Review and Approval Module 9 1.
New Jersey Election Law Enforcement Commission June 2007 Fair and Clean Elections Pilot Project 2007.
Nodal Credit Limit Overview Credit Work Group May 28, 2008 Cheryl Yager.
Chapter 16 Sale and Lease of Goods McGraw-Hill/Irwin
1 WHY WE NEED AN ICAP MARKET IN NEW ENGLAND Presentation By: Dr. Richard A. Rosen Tellus Institute Boston, MA To: Massachusetts Electric Restructuring.
Update on Demand Resource Participation in New Englands Forward Capacity Market Henry Yoshimura Demand Resources Department ISO New England, Inc. Holyoke,
© 2013 Day Pitney LLP Overview and Update on the Ever-Evolving New England Wholesale Capacity Market presentation to Boston Bar Association May 23, 2013.
Brookfield Renewable Energy Group. Focusing on Renewable Power Generation and Transmission Conceptual discussion how to integrate renewable resources under.
Behind the Fence and Contract Change Stakeholder Update September 18, 2012.
DECEMBER 17, 2013 | WESTBOROUGH, MA Reliability Committee & Transmission Committee & Markets Committee Capacity Zone Modeling Al McBride MANAGER, AREA.
1 606 CMR 14.00: Criminal Offender and Other Background Record Checks - Emergency Regulations Policy and Research Committee Meeting November 4, 2013.
606 CMR 14.00: Criminal Offender and Other Background Record Checks - Emergency Regulations Policy and Research Committee Meeting December 2,
IOC SPICE - 3 Chair Report Rodica Nitu Brussels Oct 15, 2012.
2013 Auction between Spain and Portugal 23 rd IG meeting 19 th June 2013.
NTS Exit Capacity - Amending the DN Adjustment Window Transmission Workstream, 1 July 2010.
Allocation of capacities between Portugal and Spain Madrid 30 th April 2013.
NOVEMBER 18, 2013 | WESTBOROUGH, MA Administrative Pricing Rules for Forward Capacity Auction #8.
OCTOBER 8, 2014 Bob Laurita INTERNAL MARKET MONITORING New Import Capacity Resource FCM Market Power Mitigation Order to Show Cause Compliance Filing.
3/7/07 Pre - Auction Procedures Broadband PCS Auction (Auction No. 71) Lisa Stover Auctions Marketing Specialist FCC Wireless Telecommunications.
Duquesne Light Company Request For Proposal
AUGUST 7-9, 2013 | LENOX, MA Andrew Gillespie MARKET DEVELOPMENT (413) Review of Market Rule 1: Section.
Gene Shawcroft, P.E. Central Utah Water Conservancy District April 29-30, 2013.
Multi-Stage Bidding.
Integrity Management Program Special Permits (IMP-SP) Draft Administrative Plan 12/5/2007.
What Needs HSC Review? Staying compliant with Federal research regulations.
AQ Amendment: Relevant UNC obligations and additional Validations Applied 27 May 2010.
Review of NPRR586 CMWG 1/7/2014. Existing Credit Lock Process ERCOT calculates a “preliminary allocated CRR transaction limit” based on “eligible” CRRAHs.
CRITERIA FOR ELIGIBILITY. Clubs must have contributed to the Rotary Foundation during the Rotary year preceding the award of the grant: For purposes of.
NPRR514, Seasonal Generation Resource Wholesale Market Subcommittee April 12, 2013 Amanda Frazier.
IFTA DISPUTE RESOLUTION PROCESS AMENDMENT PROPOSALS Present by Rick LaRose, Chair Dispute Resolution Committee Annual IFTA Business Meeting July 18-19,
INTRA-DAY TRADING Modification Development 5 April 2011.
1 Australian Business Economists AOFM – Activities for Presentation by Neil Hyden Chief Executive Officer, AOFM 13 July 2005.
Hour Ahead Dispatchable Loads Applicable Updates to Procedures Presentation to the Market Operations Standing Committee April 23, 2003
Merger Control in Uruguay American Bar Association- South American Regional Conference Buenos Aires, March, 2007 Guyer & Regules Juan Manuel Mercant.
Pre - Auction Procedures 700 MHz Band (Auctions 73 and 76) Kathy Hostetter Deputy Division Chief FCC Wireless Telecommunications.
Demand Response: What It Is and Why It’s Important 2007 APPA National Conference San Antonio, Texas June 26, :00 a.m. to Noon Glenn M. Wilson Director.
1 Market Trials Congestion Revenue Rights Weekly Update September 3, 2010.
G 200 L 200 ISO NEW ENGLAND T H E P E O P L E B E H I N D N E W E N G L A N D ’ S P O W E R. Southwest Connecticut RFP Markets Committee November 14, 2003.
Nodal Readiness and Transformation Metrics Discussion June 22, 2009 NIT Meeting 06/18/2009 Brandon McElfresh Readiness and Transformation, Metrics Lead.
Overview of Governing Document for Weather-Sensitive ERS Pilot Project Stakeholder Workshop Mark Patterson, ERCOT Staff March 1, 2013.
12/6/2006 Pre - Auction Procedures FM Broadcast Auction (Auction No. 70) Linda Sanderson Auctions Marketing Specialist FCC Wireless.
1 User Pays Non-Code Services – Contract Change Process Summary A Contract Change Proposal (CCP) is submitted. The Contract Change Register (CCR) is updated.
Overview of Auction Process & FCC Automated Auction System February 23, 2005 Multiple Address Spectrum (MAS) Auction No. 59 Roy Knowles
August 11, 2008 TPTF EDS Sequence and Durations Discussion Daryl Cote.
Market Trials Congestion Revenue Rights
EMR Delivery Body Contract for Difference – December 2016.
Market Trials Open Market Participant Call
Massachusetts DOER Solar Credit Clearinghouse Auction 2017 Auction Bidder Webinar June 21, :00 – 3:00 PM ET.
Tender Evaluation and Award Process
Mod_06_12 Improved Efficiencies in LCF Process 31 January 2012
The Future of Demand Response in New England
General Grants Program Process
Marginal Cost Pricing: Why Is It Important? Have We Achieved It?
FERC Order in Devon Power LLC, et al. ER
Review & maintenance of IAEG Glossary
Lynne McNaughton – Specialist II National Carbon Reduction Unit
Summer Peak Energy Pricing in New England: The ISO-NE Response
ESC Use Case Review Joint OASIS Implementation Task Force Paul R
CMC_04_19 Finalisation of Exchange Rate in Auction Information Pack
What Does the Recent LICAP Settlement Mean for New England?
Capacity Market Code Modifications
The First FCA: Observations & Thoughts
Capacity Market Code Modifications
COR3007: UNC MOD 450B – Monthly revision of erroneous SSP AQs outside the User AQ Review Period Implementation UK Link Committee – May 2014.
Opt-outs – Getting an overview
Annual Quantity (AQ) 45.
Winter Reliability Program Updated
Capacity Market Code Modifications
Presentation transcript:

MAY 10, 2012 | NEPOOL MARKETS COMMITTEE WESTBOROUGH, MA Andrew Gillespie PRINCIPAL ANALYST | MARKET DEVELOPMENT Proposal Static De-List Bid Changes

Static De-List Bid – Current Process No later than 127 days before the auction, the ISO issues qualification determination notifications for qualified resources By this time, the Internal Market Monitor (IMM) will have reviewed all submitted Static De-List Bids and will indicate in each notification whether the IMM has: – Approved the submitted de-list bid, or – Rejected the submitted price, and consequently developed a different IMM-derived de-list bid 2

Current Process – IMM Approved If the IMM approved the submitted de-list price: The de-list bid is included in the auction The de-list bid cannot be withdrawn or modified by the participant 3

Current Process – IMM Rejected If the IMM rejected the submitted de-list price, the de-list bid is not included in the auction, unless The participant makes a filing with the Commission within 15 days of the ISOs submission of the informational filing (while also notifying the ISO) that: – The participant accepts the IMM derived price In this case, the IMM derived de-list bid will be included in the auction – The participant is challenging the IMM rejection of the de-list price In this case, the de-list will be included in the auction if and only as directed by the Commission 4

Problem The Static De-List Bid price is fixed when it is submitted during the Existing Capacity Qualification period Under steady-state timing of auctions – The Existing Capacity Qualification is in June – The Qualification Notification is 127 days prior to auction – The primary auction (FCA) is conducted in February 5

Static De-List Bid – Proposal No later than 127 days before the auction the ISO issues qualification determination notifications for qualified resources By this time, the Internal Market Monitor will have reviewed all submitted Static De-List Bids and will indicate in each notification whether the IMM has: – Approved the submitted de-list bid, or – Rejected the submitted de-list bid, and consequently developed a different IMM-derived de-list bid NEW – After the qualification determination notifications are issued, open a window (seven days) to allow participants to modify Static De-List Bids 6

Proposal – IMM Approved If the IMM approved the submitted de-list bid, a participant may: Submit a new price for the Static De-List Bid that is – Less than the submitted and IMM approved de-list bid, but – Greater than $1.00/kW-mo Withdraw the de-list bid If no action is taken during this window The submitted and approved de-list bid will be included in the auction 7

Proposal – IMM Rejected If the IMM rejected the submitted de-list bid, a participant may: Submit a new Static De-List Bid that is – Equal to or less than the IMM derived de-list bid, but – Greater than $1.00/kW-mo Indicate that the participant intends to challenge the IMM rejection of the de-list bid If no action is taken during this window The de-list bid will not be included in the auction Provided that no price has been submitted, a participant may still make a filing with the Commission to challenge the IMM-derived bid The de-list bid will be included in the auction if and as directed by the Commission 8

9