1 CERC Terms and Conditions of Tariff This presentation will only highlight the relevant financial principles and operation norms. APERC would like to.

Slides:



Advertisements
Similar presentations
Financing Wind Transactions Financing Wind Power The Future of Energy IPED Conference July 25-27, 2007.
Advertisements

Regional Seminar on Developing a Programme for the Implementation of the 2008 SNA and Supporting Statistics January 30-February 1, 2013 Kingston, Jamaica.
Revolving Infrastructure Funds. Learning from the SW RDA and West of England experience. Antony Corfield (
Financing Essentials for Public-Private Partnerships United Nations SU/SSC Training Course September 19, 2006.
Ratio Analysis Ratio Analysis: A ‘Ratio: is defined as an arithmetical/quantitative/numerical relationship between two numbers. Ratio analysis is a very.
Cross-Border Infrastructure: A Toolkit Tariff and Rate Setting Session on Regulation & Accountability Max Bradford Castalia The views expressed here are.
Investment in long term assets is referred as capital expenditure Firm decision to invest its current funds efficiently in long term assets in anticipation.
Investme nt. What is Investment? Money you earn is partly spent and the rest saved for meeting futures expenses.
1 Presentation on Indian Power Sector : Key Issues By R.V. SHAHI Secretary (Power), Government of India November 16, 2006 Power Ministers’ Conference on.
Eng. K A Noel Priyantha Chief Engineer (Renewable Energy) Ceylon Electricity Board 21 October, 2007 Pricing policy for renewable energy - Cost Based Technology.
Overview of tariff revision process under Regulatory Commission Prayas - EGI Skill-share workshop for Tajikistan and Kyrgyzstan Delegates November 16-18,
1 TARIFF DESIGN for GENERATING STATIONS -- Bhanu Bhushan -- Feb 2011.
It “Pays” to be Environment Friendly Renewable Energy Certificates: IPP Perspective.
Regulatory framework in the Energy Sector Chairman Ph.D. Tserenpurev Tudev Energy Regulatory Commission of Mongolia Energy Mongolia-2012 Ulaanbaatar Mongolia.
How to read a FINANCIAL REPORT
Managing for Today and Tomorrow
Madhya Pradesh Electricity Regulatory Commission Terms and Conditions of Tariff MPERC Comments on CERC Discussion Paper.
Financial Statement Analysis of Pakistan Hotels Developers Limited and Pakistan Services Limited.
1 Georgian National Energy and Water Supply Regulatory Commission Tariff Regulation Gocha Shonia Department of Methodology and informational provision.
Incentive Regulation Topics Scott A. Struck, CPA Financial Analysis Division Public Utilities Bureau Illinois Commerce Commission.
PROF. HARNESH MAKHIJA Project Cash Flows. Content Elements of cash flow streams Principles of cash flow estimation Cash flow illustrations Cash flow for.
Generation Expansion Daniel Kirschen 1 © 2011 D. Kirschen and the University of Washington.
Financing Urban Public Infrastructure
Doctorate of Business Administration
1 THE INDIA ELECTRICITY MARKET TIME LINE REAL TIME 15 MT BLOCKS LONG TERM LOAD FORECAST FUND MOBILISATION 10-5 YEARS POWER PURCHASE AGREEMENTS CAPACITY.
Cash Flow - Dr. varadraj Bapat, IIT Mumbai1 Module 6 Cash Flow.
Steve Paulone Facilitator Financial Management Decisions The financial manager is concerned with three primary categories of financial decisions:  1.Capital.
IAS 12 : Income Taxes The Institute of Chartered Accountants of India (Set up by an Act of Parliament)
Business Analysis Types of Business Analysis  Credit Analysis  Equity Analysis  Business Environment and strategy Analysis  Financial Analysis  Prospective.
1 United States Agency for International Development (USAID) National Association of Regulatory Utility Commissioners (NARUC) Sponsored.
CERC DISCUSSION PAPER ON TERMS AND CONDITIONS FOR TARIFF FROM WARM WELCOME TO THE PRESENTATION BY NEYVELI LIGNITE CORPORATION LTD., NEYVELI.
Types of bank credit! Akramova D. Bank Credit: The borrowing capacity provided to an individual by the banking system, in the form of credit or a loan.
Wilderness Rim Association Water Rate and Reserve Study Board Meeting April 23, 2014 Presented By: Chris Gonzalez, Project Manager.
Presentation on CERC Discussion Paper on Tariff Norms By powergrid.
1 27 March 2013 MYPD3 Briefing Session – Portfolio Committee on Energy.
BALANCE OF PAYMENTS PROBLEMS. Current Account Deficit Current Account Deficit= net outflows on current account greater than net inflows. Made up on the.
IAS 7: Cash Flow Statements. Agenda 1.Objective and Scope 2.Definitions 3.Direct and Indirect method 4.Operating activities, Investing activities, Financing.
GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.
THE USE OF ADMINISTRATIVE BANKING AND INSURANCE DATA 1 Presented by Hazel Corbin Statistics Adviser, ECCB Palm Haven Hotel Saint Lucia 3 to 7 February,
Liberalization of Electricity Market in Taiwan Su, Jin-sheng Energy Commission Ministry of Economic Affairs August 8, 2001.
PRESENTATION On National Hydroelectric Power Corporation Ltd. ( A Govt. of India Enterprise) Sector – 33, Faridabad (Haryana), INDIA “Comments on Discussion.
Chapter 10 Choices Involving Time Copyright © 2014 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written.
1 Electricity Industry – Municipal Tariff Issues and NERSA Approval Processes Compiled by Nhlanhla Ngidi.
1 Analysis of OPTCL’s ARR and Transmission tariff for FY By: World Institute of Sustainable Energy, Pune (Consumer Counsel) 4 th February, 2011.
Analysis of ARR & Tariff Proposal of OHPC World Institute of Sustainable Energy Consumer Counsel.
Power Trading By P.S.Bami President – India Energy Forum & Former Chairman & Managing Director, NTPC 1.
Financial Accounting Fundamentals
Presentation to Select Committee on Economic Development
Philippine Feed-In Tariff System Implementation 1.
Renewable Energy Act of 2008
GOVERNMENT OF THE KINGDOM OF LESOTHO Water and Sewerage Company (WASCO) Greater Maseru Water Supply Feasibility Study & Preliminary Design Results of Financial.
1 Accounting Concepts and Principles. 2 Introduction Actually there are a number of accounting concepts and principles based on which we prepare our accounts.
Finanacial Statements Balance Sheet & Profit and Loss Account.
Derivatives in ALM. Financial Derivatives Swaps Hedge Contracts Forward Rate Agreements Futures Options Caps, Floors and Collars.
上海金融学院 1-1 Lecture 3 Investment Banking Basics: The Financial Statements.
City of Fernley, Nevada – 164 th Ave. NE, Suite 300, Redmond, WA April 18, 2007 Rate Study Findings Water and Sewer Utility Rates.
Preparation and Analysis of Project Report. What is a Project Report?  A Project Report is a detailed description of the Project  The Project Report.
Ratio Analysis…. Types of ratios…  Performance Ratios: Return on capital employed. (Income Statement and Balance Sheet) Gross profit margin (Income Statement)
City of Fernley, Nevada – 164 th Ave. NE, Suite 300, Redmond, WA April 18, 2007 Rate Study Findings Water and Sewer Utility Rates.
1 Accounting Concepts and Principles Dr. Clive Vlieland-Boddy.
SALARY: Taxation, Exemptions & Rebates Presented By: Asif Zafar 22 August 2016.
TARIFF DETERMINATION: GENERATION AND TRANSMISSION
Experience of R & M from Regulatory Perspective
FINANCIAL STATEMENT ANALYSIS
Solar Power Project –Viability
Rate-of-Return Regulation
GRID STATUS – PRE - ABT Very wide Frequency fluctuations
HARAMAYA UNIVERSITY SCHOOL OF AGRI ECONOMICS AND AGRI BUSINESS DEPARTMENT OF AGRICULTURAL ECONOMICS (MSc) PRESENTATION ON CASH FLOW STATEMENT AND ITS ANALYSIS.
Presentation transcript:

1 CERC Terms and Conditions of Tariff This presentation will only highlight the relevant financial principles and operation norms. APERC would like to put forward for the consideration of CERC in the Policy paper to be issued on Terms & Conditions of Tariff Written response was sent to the Commission vide letter APERC/SECY/D.No. CERC-3/ The norms are based on the experience of APERC, however ERCs are open to improve these norms

2 Clarification on Intervening Transmission facilities View of CERC is sought on intervening transmission facility and why a separate treatment has been provided for in the Act when there is open access.

3 Financial Principles

4 Tariff Setting Financial Principles Advocates forward looking principles The rate of return must be commensurate the risks involved in the business and the macro economic environment. Moving forward is critical Compensate the developer for the risks incurred by allowing a margin over and above the current bank rate. The margin be open for negotiation. The consumer to benefit from prevailing falling interest rate regime.

5 Tariff Setting Financial Principles Cost of Capital CERC to determine the rate base (either debt or equity or both) for computing returns Interest shall be benchmarked to Prime Lending Rate plus debt margin to reflect credit worthiness Return on Equity shall be pegged at Bank Rate plus a margin to reflect the investment risk in the power sector Foreign Exchange Risk Variation Foreign component may be converted into rupee terms at the Commissioning date

6 Tariff Setting Financial Principles APERC accepts the suggestion of CERC that ROCE can be evolved by bench marking the debt equity ratio. Debt to be pegged at PLR + margin Equity to be pegged at Bank Rate + margin The return should recognize the concept of time value of money and it should be ensured that only the approved return (IRR) should be permitted to the investor on annual basis This should be applied uniformly for existing and new generation projects.

7 Tariff Setting Financial Principles Depreciation Depreciation rate should be linked to the life of the asset To avoid front loading of tariffs by way of advance against depreciation, benchmarking the term of debt (12 yrs as followed earlier by CERC) could be considered, irrespective of tenure of debt. The current practice of Short-Term Loans being utilised for funding the assets needs a re-look. To explore Rolling of Debt by way of Call and Put options should be encouraged. Treatment of Tax Post Tax return shall be provided to protect the investors from changes in the law of land However, adjustments shall be made in the revenue requirement to reflect actual outflow of taxes paid.

8 Tariff Setting Financial Principles –response to specific suggestions CERC Suggestions 1.Aggregated rate base v/s disaggregated Rate Base 2.Initial capital expenditure will be the capital cost 3.Norms on capitalized initial spares as a percentage of approved project costs or actual expenditure whichever is lower. APERC Response 1.Aggregated rate base total Fixed assets as per the balance sheet, less assets not related regulated business. 2.Initial capital expenditure will be the capital cost. But preferable to to include township rather than take it as additional capital expenditure. – Maintenance of Asset Register should be mandatory. 3.Capitalizing of initial spares should be allowed on recommendations by the expert group

9 Tariff Setting O & M For new projects, the current CERC norm of O&M be capped at 2.5% (Thermal) and 1.5% (Hydro) of the approved project cost at the start of a control period may be continued. The same may be reviewed at the end of the control period to check if the level of O & M expenses. For existing projects the O&M cost for the first year of control period should be based on the average annual actual expenditure (excluding abnormal expenses) for the past five years. The existing formula for escalation (60% WPI and 40% CPI) be continued for the generation sector. For transmission sector the CPI weight age may be increased. Benchmarking the O&M expenditure to the approved project cost and in a situation of the project being awarded through competitive bidding route reduces the risk of over capitalisation. O&M being computed based on macro numbers like RS Crs per MW etc will not provide a true reflection of the project cost and instead might involve many assumptions like separate numbers based on the fuel type, type of hydro project etc.

10 Tariff Setting Working Capital Continue with the existing arrangement. Some of the Electricity Boards made have made the point that working capital should not include one months O&M expenses. But the existing procedure of offering rebate of 2.5% for payment through LC and 1% for payment within the due date addressed this issue.

11 Tariff Setting Development Surcharge There is no linkage between development surcharge and depreciation as the latter is meant to compensate for the wear and tear of existing projects and at best the repayment of loans. Whereas the development surcharge is intended to be used for setting up Central Generating Projects in future. In future with the liberalisation of the generation sector (and consequent availability from IPPs and state generation) the requirement of power from Central Generating Stations may be reduced. Hence blocking the funds through such contributions will further deteriorate the financial health of the Utilities.

12 Tariff Setting Control Period The tariff period may be kept as five years with a provision for review of the norms during the period to reflect improvements in technology and general macro economic environment. However any changes in the norms must only be done with prospective effect. The tariff for generation should be station specific.

13 Tariff Setting Availability Based Tariff The implementation of separate tariffs for peak and off peak generation will be contingent upon the metering infrastructure, the ability of the constituents to manage their respective demand and also its co- ordination with ABT regime. Given the nascent stage of implementation of the ABT regime it is advised to have time differentiated generation tariffs at a later date. The capacity should be declared ex-bus in MW terms The auxiliary energy consumption should not include the supply for construction power and residential townships and must be computed station wise.

14 THANK You