HL-LHC operations with LHCb at high luminosity

Slides:



Advertisements
Similar presentations
Simulation priorities for 2015 R. Bruce for task 5.2.
Advertisements

1 Accelerator Physics Aspects LHCb Accelerator Physics Aspects LHCb CERN SL/AP n Layout n Crossing Scheme n Luminosity n Collision.
Spectrometer compensation in IR2 and IR8 during the 450 GeV collision run September 11, 2006 LOC meeting Y. Papaphilippou Thanks to S. Fartoukh, W. Herr,
* IP5 IP1 IP2 IP8 vertical crossing angle at IP8 R. Bruce, W. Herr, B. Holzer Acknowledgement: S. Fartoukh, M. Giovannozzi, S. Redaelli, J. Wenninger.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Beam Commissioning Workshop, 19th January Luminosity Optimization S. White, H. Burkhardt.
1 Luminosity monitor and LHC operation H. Burkhardt AB/ABP, TAN integration workshop, 10/3/2006 Thanks for discussions and input from Enrico Bravin, Ralph.
Bernhard Holzer, CERN-LHC Parameter Space for HL-LHC IR8 * IP5 IP1 IP2 IP8 LEB Meeting.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
October 4-5, Electron Lens Beam Physics Overview Yun Luo for RHIC e-lens team October 4-5, 2010 Electron Lens.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Evian 2014 historical perspective run 1: 2010: L peak >10 32 cm -2 s -1  2x10 32 cm -2 s : produce >1 fb -1  delivered.
Flat-beam IR optics José L. Abelleira, PhD candidate EPFL, CERN BE-ABP Supervised by F. Zimmermann, CERN Beams dep. Thanks to: O.Domínguez. S Russenchuck,
With a lot of help from Reine Versteegen, John Jowett, Richard Jacobson, Burkhard Schmidt, Gilda Scioli, Werner Herr CERN-LHC * IP5 IP1 IP8 Spectrometer.
Beam-beam effects for round and flat optics: DA simulations D.Banfi, J.Barranco, T.Pieloni, A.Valishev Acknowledgement: R.DeMaria,M.Giovannozzi,
Shielding the 140 mm option F. Cerutti, L.S. Esposito on behalf of CERN FLUKA team.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 RHIC II – Ion Operation Wolfram Fischer RHIC II Workshop, BNL – Working Group: Equation of State 27 April 2005.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Criteria for dynamic aperture limits and impact of the multipolar errors: summary of the simulations with beam-beam for levelling scenarios at 5 and 7.5x10.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Francesco Cerutti ENERGY DEPOSITION ASPECTS FOR LHCb REQUEST 5th Joint HiLumi LHC - LARP Annual Meeting Oct 29, 2015 through L.S. Esposito’s work and essential.
Crossing Schemes Considerations and Beam-Beam Work plan T. Pieloni, J. Barranco, X. Buffat, W. Herr.
Plan for 500 GeV Development Vadim, Mei. Goals 1.Explore polarization transmission to the 500 Gev CM energy. 2. Inspect the luminosity aspects (with 2.
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
ENERGY DEPOSITION AND TAS DIAMETER
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Fabio Follin Delphine Jacquet For the LHC operation team
C. Bracco, R. Bruce, B. Goddard, C. Wiesner, A. Lechner, M. Frankl
Y.Papaphilippou Thanks to
Luminosity monitor and LHC operation
Operating IP8 at high luminosity in the HL-LHC era
Scenarios for 2017 and 2018 Thanks to Gianni, Fanouria, Gianluigi, Dario, Stephane, Elias, Michi, Jamie, Christoph, Rogelio, Mirko, Riccardo, Hannes,
Francesco Cerutti, Andrea Tsinganis WP10 Energy deposition & R2E
M.Fitterer, A.Patapenka, A.Valishev (FNAL)
Impact of running with LHCf and early Totem 90 m optics
Task 2. 5: Beam-beam studies D. Banfi, J. Barranco, T. Pieloni, A
HL-LHC Aperture Update
LHeC interaction region
Field quality update and recent tracking results
Emittance growth AT PS injection
Optimization of Triplet Field Quality in Collision
Spectrometer Operation in IP2 & 8
Follow-up of HL-LHC Annual meeting
Β*-reach in 2017 R. Bruce, S. Redaelli, R. De Maria, M. Giovannozzi, A. Mereghetti, D. Mirarchi Acknowledgement: collimation and optics teams, BE/ABP,
Field quality to achieve the required lifetime goals (single beam)
DEBRIS IMPACT IN THE TAS-TRIPLET-D1 REGION
WP3 meeting Aug 21, 2015 V1.1 RECAP Francesco Cerutti.
VELO detector and available aperture in IR8
Collision bump amplitudes for the 450 GeV run
Week 35 – Technical Stop and Restart
Collimation after LS1: cleaning and β* reach
Global aperture measurements at 450 GeV with 170 mrad crossing angle
Collimation margins and *
Collision bump amplitudes for the 450 GeV run
Revised estimates of heat loads and radiation damage in the IT and D1
Pushing the LHC nominal luminosity with flat beams
Thanks to S. Fartoukh, W. Herr, B. Jeanneret, M. Giovannozzi
Triplet corrector layout and strength specifications
LHC Morning Meeting - G. Arduini
JLEIC High-Energy Ion IR Design: Options and Performance
Fanglei Lin JLEIC R&D Meeting, August 4, 2016
Large emittance scenario for the Phase II Upgrade of the LHC
Optimization of JLEIC Integrated Luminosity Without On-Energy Cooling*
L. Gentini, M. Giovannozzi, M. Gonzalez, M. Krupa, H. Mainaud Durand,
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

HL-LHC operations with LHCb at high luminosity R. De Maria, N. Karastathis Thanks to G. Arduini, F. Cerutti, I. Efthymiopoulos, S. Fartoukh, M. Giovannozzi LHCb Meeting 21/3/2018

Peak luminosity Minimum β* is constrained by optics flexibility. 𝐿= 𝑁 𝑏 2 𝑓 𝑟𝑒𝑣 𝑘 𝑏 4𝜋𝜖 𝛽 × ∗ 𝛽 ∥ ∗ ⋅ 1 1+ Φ 𝑝 2 Protons per bunch 𝑁 𝑏 2.2 1011 Number of Bunches 𝑘 𝑏 2572(2374) R.M.S. bunch length 𝜎 𝑠 7.61(9.0) cm +/- Polarity By<0 / By>0 Φ 𝑝 = 𝜎 𝑠 𝜎 × ⋅ 𝜃 × 2 = 𝜎 𝑠 𝛽 × ∗ ⋅ bb sep 2 𝜃 external , 𝛽* at constant luminosity 𝜃 × = 𝜃 external ± 𝜃 spectrometer cos 𝛼 plane 1 1034 cm-2s-1 baseline Minimum β* is constrained by optics flexibility. Maximum crossing angle limited by orbit corrector strength For a given β*: Aperture constrains maximum crossing angle. Beam-beam effects (i.e. beam lifetime) constrains minimum crossing angle. Beam-beam effects Orbit corrector limitations Aperture limitations 2 1034 cm-2s-1 Optics limitations

Beam-beam limitations at collision DA margins at the end of Atlas/CMS levelling as a function of IR8 horizontal half external angle for a scenario with 1 1034 cm-2s-1. -250 μrad, Neg. -200 μrad, Neg. -180 μrad, Neg. -150 μrad, Neg. N. Karastathis

Beam-beam limitations at collision DA margins at the end of Atlas/CMS levelling as a function of IR8 horizontal half external angle for a scenario with 1 1034 cm-2s-1. -200 μrad “Bad”(Neg) Polarity -150 μrad “Good”(Pos.) Polarity N. Karastathis Spectrometer polarity has an impact of minimum external crossing angle. Tentative IR8 external half crossing angle with horizontal crossing: -200 μrad with Neg. polarity (-65 μrad half crossing angle) -150 μrad with Pos. polarity (-285 μrad half crossing angle) Not fully validated, full cycle simulation needed. A vertical external half crossing angle of 160 μrad is expected to behave in between the two horizontal options (210 μrad half crossing angle)

Aperture limitations in collision Maximum half external crossing angle as function of β* β* [m] H1 [µrad] H2 [µrad] V3 [µrad] V1,4 [µrad] 1 -165 -220 ±115 ±220 1.5 -225 -275 ±165 ±235 2 -265 -310 ±205 ±270 3 ±250 ±310 1 with present TCDDM 2 without present TCDDM 3 crossing plane can be rotated during the ramp (difficult to setup) 4 if beam screen is rotated, introducing strong limitations during the ramp Aperture in the triplet is not symmetric (H=57.8 mm, V=48 mm) and cannot be rotated easily. TCDDM needed for D1 protection Present aperture bottleneck for Beam 2 H and Beam 1 V. H crossing V crossing H crossing V crossing Compatible with previous scenarios and still aperture margin for β*//. Beam screen rotation not needed so far in V crossing, and, if it would, the issues are at injection…

Constraints at injection Baseline Horizontal crossing. Pos. Spec., 450 GeV -170 µrad, +3.5 mm As the LHC, but with double the intensity in HL-LHC. This needs to be still validated, no margin expected.

Constraints at injection Baseline Horizontal crossing. Neg. Spec., 450 GeV -170 µrad, +3.5 mm As the LHC, but with double the intensity in HL-LHC. This needs to be still validated, no margins expected.

Constraints at injection Vertical crossing and rotated beam screen with critical issues Neg. Spec., 450 GeV -170 µrad, +3.5 mm 2σ Additional close encounters, in particular close to the IP. Not compatible with different ion species runs (e.g. p – lead). Not compatible with present orbit tolerance specifications for p-p.

Constraints at injection Horizontal crossing and rotated beam screen with critical issues Neg. Spec., 450 GeV -170 µrad, +3.5 mm 2σ Not enough aperture for the crossing angle in the H plane. Reducing crossing angle and increasing parallel separation not trivial.

Tentative scenarios β* [m] Ext. Crossing /Spec. Polarity Peak Luminosity [1034] 1.5 H/±200 /- 2.16 H/±150/+ 1.59 (implies operation overhead) V/±160/+ or - 1.8 (not simulated with DA) β* [m] X Int. Lumi [1034/year] 1.5 H 43 52 V 51 Assuming same ∫L in both polarities, to be verified with more realistic luminosity models Not significant advantage of designing the detector for 2 1034 cm-2s-1. 43 fb-1 sufficient to reach a target of 300fb-1 (triplet lifetime) in RunV, RunVI (~6 years of operations). Beam screen rotation not needed for these configurations, small crossing angle also better for dose at constant luminosity.

Example of Luminosity evolution Case with LHCb virtual luminosity of 2.16 1034 cm-2s-1 with three levelling scenarios. Simple model used for illustration only and not for quantitative estimates. Atlas/CMS Atlas/CMS LHCb LHCb Atlas/CMS Machine LHCb

Example of Luminosity evolution Case with LHCb virtual luminosity of 1.8 1034 cm-2s-1 with three levelling scenarios. Simple model used for illustration only and not for quantitative estimates. Atlas/CMS Atlas/CMS LHCb LHCb Atlas/CMS Machine LHCb

Example of Luminosity evolution Case with LHCb virtual luminosity of 1.59 1034 cm-2s-1 with three levelling scenarios. Simple model used for illustration only and not for quantitative estimates. Atlas/CMS Atlas/CMS LHCb LHCb Atlas/CMS Machine LHCb

Open points Validate the new tentative configurations for LHCb at high luminosity: Evaluate commissioning overhead of two external crossing angles depending on the polarity. Complete beam-beam simulations, in particular for the whole cycle and with vertical crossing (ongoing). Perform energy deposition studies for the cycle for different crossing scenarios. Assess feasibility and cost of protecting devices such as: TAS, TAN, TCDDM, TCL. A study group is going to be put in place to provide information concerning the impact on HW and costs. Asses realistic dose considering no TAS before RunIV and large crossing angle. If operational margins exist one can consider the options: Flat beams (e.g. β*// < β*X) which gives more luminosity at constant aperture but with additional beam-beam effects to be evaluated. In H crossing smaller β*X for Pos. Polarity at the cost of additional operational overhead to be quantified. In parallel one would need to state what performance impact is acceptable for Atlas and CMS.

Conclusion Tentative scenarios identified with levelled luminosity of 1·1034 cm-2s-1 and similar performance: Horizontal crossing with two external angles Time lost at each polarity change Vertical crossing with rotation of the crossing plane at flat top Time lost in commissioning the crossing plane rotations (it gave several problems during Run I) Beam screen rotation: is not needed in the present scenarios taking into account triplet lifetime, present options and further optimizations that could be attempted is not feasible option unless: it is possible to reduce orbit tolerances AND disable LHCb during p-Ion runs OR it is possible inject with very large separation. proven feasible for radiation issues. compatible with cost and schedule (in-situ coating developed to avoid intervening on the triplet). Flat beams in LHCb: Can improve luminosity at constant aperture and beam-beam separation in the triplet, with potential detrimental effects on lifetime compared to round at constant aperture (e.g. beam-beam effects). Will be explored after round scenarios are fully validated.

Backup

Flat optics

Constraints at injection Vertical crossing with critical issues Neg. Spec., 1000 GeV Rotated beam screen -170 µrad, +3.5 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

Constraints at injection Vertical crossing with critical issues Neg. Spec., 1000 GeV Rotated beam screen -200 µrad, +2.0 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

Constraints at injection Vertical crossing with critical issues Neg. Spec., 3000 GeV Rotated beam screen -200 µrad, +1 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

Constraints at injection Vertical crossing with ramped spectrometer Neg. Spec., 450 GeV Rotated beam screen and ramped spectrometer Vertical crossing is straightforward if spectrometer could be ramped with energy.

Constraints at injection Horizontal crossing with extreme conditions Pos. spec., 450 GeV Rotated beam screen -120 µrad, +7.0 mm 80 µrad (bias) 1.5 mm offset This solution is more robust at injection, but uses about 3 times the typical orbit corrector at injection. As energy increase separation, offset and bias would need to be reduced quickly. Needs validation from injection protection issues.

Constraints at injection Baseline Horizontal crossing. Pos. Spec., 450 GeV -170 µrad, +3.5 mm As the LHC, but with double the intensity in HL-LHC This needs to be still validated.

Constraints at injection Baseline Horizontal crossing. Neg. Spec., 450 GeV -170 µrad, +3.5 mm As the LHC, but with double the intensity in HL-LHC This needs to be still validated.

Constraints at injection Vertical crossing with critical issues Neg. Spec., 450 GeV Rotated beam screen -170 µrad, +3.5 mm Additional close encounters, in particular close to the IP. Not compatible with different ion species runs (e.g. Lead – Ion). Not compatible with present orbit tolerance specifications for p-p.

Constraints at injection Vertical crossing with critical issues Neg. Spec., 1000 GeV Rotated beam screen -170 µrad, +3.5 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

Constraints at injection Vertical crossing with critical issues Neg. Spec., 1000 GeV Rotated beam screen -200 µrad, +1 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

Constraints at injection Vertical crossing with critical issues Neg. Spec., 3000 GeV Rotated beam screen -200 µrad, +1 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

Constraints at injection Vertical crossing with ramped spectrometer Vertical crossing, - 450 GeV Rotated beam screen and ramped spectrometer Vertical crossing is straightforward if spectrometer could be ramped with energy.

Constraints at injection Horizontal crossing with extreme conditions Neg. Spec., 450 GeV Rotated beam screen -120 µrad, +7.0 mm 80 µrad (bias) 1.5 mm offset This solution is more robust at injection, but uses about 3 times the typical orbit corrector at injection. As energy increase separation, offset and bias would need to be reduced quickly. Do we need this?