04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
● Main goals for week 33: – Luminosity production; – First 150 ns bunch train attempts; – Roman Pots: check movement at 3.5 TeV, with 1b; – Off momentum.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
● Morning: Physics fill with 25 bunches: – 07:00: Injection; – 07:25: Start ramp; – 09:00: End of squeeze and stable beams; – Emittances:  x1 = 3.0 
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Saturday ● 06:00: Physics fill from the night shift ● 15:00: End stable beam mode: – problems with incorporation of settings for the squeeze ● 16:40:
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday
Last 24 hours RQ4.L1 Lost going into collision Test ramp Storm
Machine Coordinators: G. Arduini, J. Wenninger
Saturday 24 March 2012.
Friday 15th June 01:11 Injection.
Wednesday September 14th
Friday 18/03 07:15 Test ramp with pilot after the test of dynamic FIDEL correction. Ramp was OK, but fill was stopped due to the trip of several RQTFs.
Wed :55 Fill 2653 stable beams 1.40e11 ppb, cm-2s-1peak lumi, 11.6 pb-1 total lumi delivered. 09:31 Dumped by collimator interlock:
Monday 11/07: Recovery Plenty of accesses.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
LHC Morning Meeting - G. Arduini
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Summary week 31 Week 31 G. Arduini & O. Brüning
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Summary of Week 11: 14 – 21 March
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary week 30 Week 30 R. Bailey & J. Wenninger
Wednesday 31 October: Morning
Summary of Week 16 G. Arduini, J. Wenninger
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
LHC Morning Meeting - G. Arduini
Thursday 10th May - morning
Week 36 plan Todo’s: And also: 12+b injection.
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Sunday morning Recovering from 400 kV disturbance.
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Friday Morning 7:30 injection for fill 2908
Yesterday morning Held 1647 for a while – SPS kicker problem
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday Ramp single nominal bunches for loss maps
Aims for the week Recover from technical stop and precycle at 10A/s
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Saturday Nov Stop proton operation. Switch back to ions
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
07/08/2010 Fill #1264 dump at 02:14:38.
Polarity inversion 07:00 ALICE solenoid and dipole polarity switched to positive External Crossing angle polarity unchanged at injection/ramp & squeeze.
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Saturday 26 November 2011.
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Mon 8/8 – Tue 9/8 Stable beams #2009
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1

05/08/2010 Go to adjust mode for end of coast study Swap H/V tunes for B2 (crossing coupling resonance) in order to investigate the feasibility of working point with similar to RHIC in collision. Damper can stand the tune swap but not completely transparent (dip in lifetime and tiny losses)

05/08/2010 Loss in B1 observed a few minutes after during “gentle” scan to test new version of the lumi scan application Preliminary conclusion: working point with swapped tunes for one of the beam not an option yet

05/08/2010 14:30 Start injection for test fill for ramp and squeeze optimization (2 on 2 bunches) Problem with the OFB stuck in the vertical plane for B! and B2: managed to get through the ramp (we had low intensity) with no losses thanks to previous incorporations  Ralph working on this issue already observed in a few occasions 20:00 RQ10.B2 power converter trip (water fault again)  Beam dump Incorporate Q and Orbit FB feed forward into ramp. ✔ Establish better end-squeeze to collision sequence/settings. ✔ Clean orbit in stable beams (ALICE H plane,..). ✔ Check TCTs. Not yet done Collimator loss maps. Not yet done Beam dump validation (Dump with RF OFF) Not yet done

05/08/2010 New beam process for collision (Mike): All went smoothly ! Non-closure of the knobs 30 microns in V, 60 microns in H. OK !  To be implemented in the sequence

05/08/2010 Orbit clean-up (Joerg): Before After Beam offset at TCTs now much better in ALICE (H) and CMS (V). The large offsets of around 2 sigma have been cleaned up. Before After

05/08/2010 Access request from CMS to fix serious problem on their detector Profited of the access for CMS to fix: problem on MKB (vacuum interlock configuration) Module replacement for fixing the spurious interlocks on Q10.R8 Accesses finished by 22:45 Tedious injection process because of an intermittent problem with an 80 MHz cavity in the PS (experts are still working)

05/08/2010 Stable beams at 03:53. Peak luminosity~2.7x1030 cm-2s-1 Initial luminosity ~10% lower than yesterday (only ½ of it explained by lower intensity. Emittances? Not clear from the available measurements

05/08/2010 Equal tunes for both beams (+0.002 wrt nominal collision tunes). Similar initial lifetimes wrt previous physics fill

Programme Keep this fill and put another one in the evening For the week-end: Physics fills with some short interleaved injection studies: Hump investigation (1.5 h) Damper tests (0.5 h)

Pending Tests: Requiring access: New BLM Firmware tests Delay of the PM trigger of the BLM system to be set back  BLM team ready only next week Loss maps, orbit clean-up and TCT verifications Requiring access: Repair COD MCBH.18R7.B2 CV need to replace a motorisation of the water valve of the sector 56 - not urgent Time estimate ~3 hours Access team to replace oxydized connectors for PAD-PX24 in case of stop (3 hours) Magnetic probes in the machine for the studies related to the hump - access in point 5 (GA, LW) – 3 hours

Open issues Open Issues: Clogging of CMS cryo filters not yet understood Vacuum pumps near dilution kicker. QPS boards: several boards had to switch from channel A to B 80 MHz cavities in the PS