Interferometer Design for bKAGRA Phase 1 and Beyond

Slides:



Advertisements
Similar presentations
KAGRA ISC Electrical Components Layout Yuta Michimura Ando Group Department of Physics, University of Tokyo April 17, 2015.
Advertisements

LIGO- G05XXXX-00-R 40m meeting, May Experimental update from the 40m team 40m TAC meeting May 13, 2005 O. Miyakawa, Caltech and the 40m collaboration.
Design of Stable Power-Recycling Cavities University of Florida 10/05/2005 Volker Quetschke, Guido Mueller.
Amaldi conference, June Lock acquisition scheme for the Advanced LIGO optical configuration Amaldi conference June24, 2005 O. Miyakawa, Caltech.
LIGO- G R Sensing and control, SPIE conference, June Sensing and control of the Advanced LIGO optical configuration SPIE conference at.
Optical Levers Layout and Cabling Yuta Michimura, Yuya Kuwahara Ando Group Department of Physics, University of Tokyo November 19, 2015.
New iKAGRA Configuration Yuta Michimura Department of Physics, University of Tokyo 11th KAGRA F2F (University of Tokyo) Feb 6, 2015.
KAGRA ISC Electrical Components Layout Yuta Michimura Ando Group Department of Physics, University of Tokyo December 8, 2015.
Paolo La Penna ILIAS N5-WP1 meeting Commissioning Progress Hannover, July 2004 VIRGO commissioning progress report.
Monica VarvellaIEEE - GW Workshop Roma, October 21, M.Varvella Virgo LAL Orsay / LIGO CalTech Time-domain model for AdvLIGO Interferometer Gravitational.
LIGO-G Z 3) Current Status & Plan for Japan RSE -- Stabilization and Installation of PRC & Detuning -- LSC Livingston 2002 Kentaro Somiya.
Summary of iKAGRA Test Run Mar 25-31, 2016 Yuta Michimura Department of Physics, University of Tokyo April 12, 2016JGW-T
IKAGRA 初期アラインメント手順 Initial Alignment Procedure for iKAGRA Yuta Michimura Department of Physics, University of Tokyo July 5, 2016JGW-T
Current Status of Main Interferometer Design Yoichi Aso 2011/2/4, LCGT f2f Meeting.
Main Interferometer Subsystem
Input Mode Matching of LCGT 2012/1/5, Yoichi Aso.
bKAGRA PSL Design Study
Main Interferometer Subsystem
Main Interferometer Subsystem
Main Interferometer Meeting
Summary of iKAGRA Test Run Mar 25-31, 2016
Summary of iKAGRA Test Run Apr 11-25, 2016
Kazuhiro Yamamoto on behalf of KAGRA collaboration
Yuta Michimura Department of Physics, University of Tokyo
LCGT Main Interferometer Subsystem
KAGRA Control Room Appearance (tentative)
Yoichi Aso on behalf of the LCGT ISC Group
Vibration Isolation Systems
The Advanced LIGO Angular Control System (ASC) (Hanford edition)
Design of Stable Power-Recycling Cavities
Possibility of Upgrading KAGRA
Summary of the iKAGRA Run
Current Status of the 40m Detuned RSE Prototype
Interferometer Design for bKAGRA Phase 1 and Beyond
iKAGRA初期アラインメント手順 Initial Alignment Procedure for iKAGRA
Arm Length Stabilization Conceptual Configuration
Arm Length Stabilization Conceptual Configuration
Cartoon of the optical layout around IMC, IFI and IMM
40m Laboratory Upgrade Progress Report
Interferometer Design for bKAGRA Phase 1 and Beyond
Summary of iKAGRA Test Run Mar 25-31, 2016
Summary of iKAGRA Test Run Mar 25-31, 2016
Interferometer Design for bKAGRA Phase 1 and Beyond
bKAGRA PSL EOM Layout ~180W ? to IMC Laser EOM (fPMC, PM) PMC EOM
Interferometer Design for bKAGRA Phase 1 and Beyond
Commissioning Procedure for bKAGRA Phase 1 ( )
iKAGRA初期アラインメント手順 Initial Alignment Procedure for iKAGRA
Commissioning Procedure for bKAGRA Phase 1 ( )
Summary of the iKAGRA Run
Commissioning Procedure for bKAGRA Phase 1
Commissioning Procedure for bKAGRA Phase 1
Commissioning Procedure for bKAGRA Phase 1 ( )
iKAGRA初期アラインメント手順 Initial Alignment Procedure for iKAGRA
Yuta Michimura Department of Physics, University of Tokyo
Status of KAGRA Yuta Michimura on behalf of the KAGRA Collaboration
Commissioning Procedure for bKAGRA Phase 1
Status of KAGRA Yuta Michimura on behalf of the KAGRA Collaboration
Commissioning Procedure for bKAGRA Phase 1
Interferometer Design for bKAGRA Phase 1 and Beyond
Beam Propagation for bKAGRA Phase 1 with flat ETMs
iKAGRA初期アラインメント手順 Initial Alignment Procedure for iKAGRA
Summary of iKAGRA Test Run Mar 25-31, 2016
Intensity Stabilization Servo Plan
Interferometer Design for bKAGRA Phase 1
Intensity Stabilization Servo Plan
Arm Length Stabilization Conceptual Configuration
KAGRA ISC Electrical Components Layout
Yuta Michimura Department of Physics, University of Tokyo
KAGRA ISC Electrical Components Layout
Presentation transcript:

Interferometer Design for bKAGRA Phase 1 and Beyond JGW-T1605595 January 1, 2019 Interferometer Design for bKAGRA Phase 1 and Beyond Yuta Michimura Department of Physics, University of Tokyo for the MIF subgroup

bKAGRA Phase 1 (-2018.3) Goal: - Start observation run using 3km cryogenic interferometer by the end of March 2018 - TM temperature should be (close to) 20 K - No requirement for sensitivity Configuration: - 3 km cryogenic Michelson - minimum success: cryo Michelson with LSC - strict deadline (KAGRA will die if cannot make it) - concentrate on Michelson first (no power recycling before Michelson operation) Purpose: - Test cryopayload and cryogenic operation

bKAGRA 2018.4-6 Interferometer team will have time after Phase 1 until ITM cryopayload installation, which starts on July 2, 2018 Configuration: - 3 km cryogenic power-recycled Michelson - no strict deadline, but we have to finish it before ITM installation starts (try PRMI if it doesn’t delay the final bKAGRA) Purpose: - Test cryopayload and cryogenic operation - Try 3-km cavity locking, multi-DOF locking - Spatial mode check

Steps for Cryogenic MI and PRMI 2017.6.5 PRs installed -> ~1 month integration (-2017.7.6?) 2017.8.31 PSL+IMC ready Initial alignment to both ends, beam collimation (no PR2-PR3 length tuning if beam is collimated well enough) 2017.10.31 ETMY CRYp installed Return the beam from ETMY to BS (we don’t try PR-ETMY cavity) 2017.11.15 SR2 and SR3 installed -> ~1 month integration (-2017.12.19?) 2017.11.22- ETMY evacuation -> 2017.12.8 cool down starts 2018.2.2 ETMX CRYp installed Return the beam from ETMX to BS Lock room temperature Michelson 2018.2.13- ETMX evacuation -> 2018.3.2 cool down starts by 2018.3.31 Start observation run with 3-km cryogenic Michelson [AFTER WE MEET THE DEADLINE] Shorten PR2-PR3 length by 2.4 cm (at max) Re-alignment connect remaining bellows/ducts and evacuate central area Lock cryogenic PRMI if not possible, lock more cryogenic Michelson * PRMI could be unstable if PR2/3 RoC errors are the worst case

Configuration Every detection port listed here has both PD and QPDs (for ASC), and placed on output optics tables in air Green lasers are also installed (but not necessary for Phase 1) No requirement for vacuum level invac fixed BRT (could be on isolated table; GPT is on output optics table in air) TRY IMC: Type-C with WFS ETMs: Type-A + ~20 K CRYp (CRYp not final ones) POP PRM misaligned when Michelson IMMT: Type-C TRX PSL IFI IMMT1T 2 W final PMC high power EOM fIMC = 13.78 MHz f1 = 16.88 MHz frequency stabilized with RefCav/IMC/(PRCL) intensity stabilized with PMCT and IMMT1T BS, SRs: Type-B REFL PRs: Type-Bp invac fixed BRT invac fixed STM AS

Layout Adjust layout slightly to compensate ITM wedge Move PR2 and PR3 to stabilize mode of PR cavity (after Michelson operation) see JGW-G1605199 for more detail move PR2 by 1.2 cm BS angle slightly changed (by 0.0187 deg) move PR3 by 1.2 cm beam spot on PR3 5mm off the center in –Y direction

Length Sensing and Control Only use f1 sidebands Sensing matrix for PRMI: [W/m] MICH PRCL REFL_I +9.92e-01 -7.48e+07 REFL_Q +6.61e+04 -3.52e+07 AS_I +8.97e+02 -2.23e-01 AS_Q -1.67e+06 +4.16e+02

Alignment Sensing and Control Only use f1 sidebands (and TRX/Y DC) Sensing matrix for PRMI: [W/rad] COMM DIFF BS PRM PR2’ PR3’ REFLA_I +4.98e+02 +2.36e-01 -4.16e+02 -8.13e+01 -2.08e-01 -1.21e+03 REFLB_I -7.01e-01 -2.91e+00 -1.93e+00 -2.10e+01 -1.70e-03 +3.47e+00 ASA_Q +9.80e-01 +1.87e+02 +1.56e+02 -1.39e-01 +1.31e-03 -2.27e+00 POPA_DC +4.04e+01 +1.49e+01 -2.41e+01 +3.91e+02 +8.07e+02 -1.57e+01 TRXA_DC +2.30e+01 +1.71e-01 +1.93e+01 -1.23e-01 -5.66e-03 -6.51e-01 TRYA_DC -2.30e+01 +1.71e-01 -1.91e+01 -1.17e-01 -3.25e-03 -6.36e-01 See JGW-G1605541 and JGW-T1605362 for more detail

Transverse Mode Spacing for PRMI g-factor 0.8750 in pitch 0.8958 in yaw (with designed RoCs & lengths, PR2-PR3 length shortened by 2.4 cm) See JGW-G1605541 JGW-T1605362 for more detail how to measure: LIGO-G080467

Commissioning Schedule FY2017 BS ready (4.13) PSL+IMC ready (8.31) PR2-3 duct connected (9.8) PRs ready (7.6) connect after start of ETMY CRYp installation IMMT to PR3 (9.11-9.15) EYT installed (8.24) ETMY install (9.1-10.31) EXT after EYT for safety PR3 to Xend (9.18-9.22) EXT installed (11.24) BS to Yend (9.25-9.29) EXT BRT invac (11.27-12.1) EYT BRT invac (11.1-11.7) collimation (10.2-10.27) TRX table (12.4-12.8) TRY table (11.8-11.14) ETMY to REFL (11.1-11.7) SR2 and SR3 ready (12.19) POP invac (11.8-11.14) connect bellows/ducts in the central area if there are any chances BS to SR3 (12.20-12.26) REFL table (11.8-11.14) POP table (11.15-11.21) 1 week for preparation AS invac (12.27-1.2) EY evacuation ready EY evacuation 11.22-12.8 EY cooling start 12.8 AS table (1.3-1.10) ETMX install (1.8-2.2) ETMX to REFL (2.5-2.9) central area cannot be evacuated before SRM completion (3.2) Michelson LSC (2.12-2.16) [AFTER THE DEADLINE (2018.4-6)] PR2-PR3 length adjust PRMI alignment, locking connect remaining bellows/ducts evacuate central area 1 week for preparation EX evacuation ready EX evacuation 2.23-3.2 EX cooling start 3.2 Cryogenic Michelson Operation (3.2-3.31)