More on Estimation In general, effort estimation is based on several parameters and the model ( E= a + b*S**c ): Personnel Environment Quality Size or.

Slides:



Advertisements
Similar presentations
Estimation using COCOMO More Science, Less Art. COCOMO History COCOMO History Constructive Cost Model Dr. Barry Boehm TRW in 1970s COCOMO
Advertisements

Project Estimation: Metrics and Measurement
Software Cost Estimation Main issues:  What factors determine cost/effort?  How to relate effort to development time?
Project Risks and Feasibility Assessment Advanced Systems Analysis and Design.
Software project management (intro)
Ch8: Management of Software Engineering. 1 Management of software engineering  Traditional engineering practice is to define a project around the product.
1 COST ESTIMATION Basics, COCOMO, FP. 2 What is estimated? TIME MONEY TIME: –duration, chronological weeks, months, years –effort, person-month (man-month)
CSC 395 – Software Engineering
1 Cost Estimation CIS 375 Bruce R. Maxim UM-Dearborn.
Information System Economics Software Project Cost Estimation.
University of Toronto Department of Computer Science © 2001, Steve Easterbrook CSC444 Lec22 1 Lecture 22: Software Measurement Basics of software measurement.
© The McGraw-Hill Companies, Software Project Management 4th Edition Software effort estimation Chapter 5.
Cmpe 589 Spring Software Quality Metrics Product  product attributes –Size, complexity, design features, performance, quality level Process  Used.
1 ECE 453 – CS 447 – SE 465 Software Testing & Quality Assurance Lecture 22 Instructor Paulo Alencar.
COCOMO Models Ognian Kabranov SEG3300 A&B W2004 R.L. Probert.
Chapter 6 : Software Metrics
Project Management Estimation. LOC and FP Estimation –Lines of code and function points were described as basic data from which productivity metrics can.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 26 Slide 1 Software cost estimation 1.
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 23Slide 1 Chapter 23 Software Cost Estimation.
Function Point Analysis What is Function Point Analysis (FPA)? It is designed to estimate and measure the time, and thereby the cost, of developing new.
Quality Assurance vs. Quality Control Quality Assurance An overall management plan to guarantee the integrity of data (The “system”) Quality Control A.
Software cost estimation Predicting the resources required for a software development process 1.
T. E. Potok - University of Tennessee CS 594 Software Engineering Lecture 3 Dr. Thomas E. Potok
10/27/20151Ian Sommerville.  Fundamentals of software measurement, costing and pricing  Software productivity assessment  The principles of the COCOMO.
Cost Estimation. Problem Our ability to realistically plan and schedule projects depends on our ability to estimate project costs and development efforts.
Cost Estimation What is estimated? –resources (humans, components, tools) –cost (person-months) –schedule (months) Why? –Personnel allocation –Contract.
Project Estimation Model By Deepika Chaudhary. Factors for estimation Initial estimates may have to be made on the basis of a high level user requirements.
SEG3300 A&B W2004R.L. Probert1 COCOMO Models Ognian Kabranov.
©Ian Sommerville 2000Software Engineering, 7th edition. Chapter 26Slide 1 Software cost estimation l Predicting the resources required for a software development.
Software Project Estimation IMRAN ASHRAF
Effort Estimation Has been an “art” for a long time because
©Ian Sommerville, adapted by Werner Wild 2004Project Management Slide 1 Software cost estimation u Predicting the resources required for a software development.
Estimation using COCOMO
Function Points Synthetic measure of program size used to estimate size early in the project Easier (than lines of code) to calculate from requirements.
Estimating “Size” of Software There are many ways to estimate the volume or size of software. ( understanding requirements is key to this activity ) –We.
Effort Estimation In WBS,one can estimate effort (micro-level) but needed to know: –Size of the deliverable –Productivity of resource in producing that.
Rating Very Very Extra Cost Drivers Low Low Nominal High High High Product Attributes Required software reliability Database size.
FUNCTION POINT ANALYSIS & ESTIMATION
بشرا رجائی برآورد هزینه نرم افزار.
Estimation Questions How do you estimate? What are you going to estimate? Where do you start?
Cost23 1 Question of the Day u Which of the following things measure the “size” of the project in terms of the functionality that has to be provided in.
CS223: Software Engineering
THE FAMU-CIS ALUMNI SYSTEM
Chapter 33 Estimation for Software Projects
Project Cost Management
Software Estimating Technology: A Survey
Software Engineering: A Practitioner’s Approach, 6/e Chapter 23 Estimation for Software Projects copyright © 1996, 2001, 2005 R.S. Pressman & Associates,
Function Point Analysis
Software Project Estimation
Software Planning
Constructive Cost Model
Software Development & Project Management
COCOMO Model Basic.
Personal Software Process Software Estimation
Function Point.
Chapter 5: Software effort estimation- part 2
Software Metrics “How do we measure the software?”
Activities During SPP Size Estimation
COCOMO Models.
Cost Estimation Van Vliet, chapter 7 Glenn D. Blank.
Chapter 33 Estimation for Software Projects
Software Engineering: A Practitioner’s Approach, 6/e Chapter 23 Estimation for Software Projects copyright © 1996, 2001, 2005 R.S. Pressman & Associates,
Software Cost Estimation
Software Cost Estimation
Software Development Cost Estimation Chapter 5 in Software Engineering by Ian Summerville (7th edition) 4/7/2019.
COnstructive COst MOdel
Software Cost Estimation
Software Effort Estimation
Chapter 26 Estimation for Software Projects.
COCOMO MODEL.
Presentation transcript:

More on Estimation In general, effort estimation is based on several parameters and the model ( E= a + b*S**c ): Personnel Environment Quality Size or Volume of work Process where S is the Size and a, b, and c are constants estimated with other parameters Some popular Effort Estimation methodologies: Function Point COCOMO (Constructive Cost Model) E S

“simplified” Function Point Proposed by Albrecht of IBM as an alternative metric to lines of code count for S, “size/comlexity” of product. Based on 5 major areas and a complexity table of simple, average and complex set of weights as follows: simple average complex input 3 4 6 output 4 5 7 inquiry 3 4 6 master files 7 10 15 interfaces 5 7 10 The Unadjusted Function Point is : UFP = w*Inp + w2*Out + w3*Inq + w4*MastF +w5*Intf

Function Point (cont.) 14 technical complexity factors are included, each valued between 0 and 5: data communications distributed data performance criteria heavy hardware usage high transaction rates online data entry online updating complex computations ease of installation ease of operation portability maintainability end-user efficiency reusability

Function Point (cont.) The sum of 14 technical complexity factors can have values of 0 through 70. The Total Complexity Factor(TCF) is defined as: TCF = .65 + (.01 * Sum of 14 technical complexity factors) TCF may have values of 0.65 through 1.35. Finally, Function Point (FP) is defined as: FP = UFP * TCF For Cost and Productivity per FP, one may use “historical” data.

Simple Function Point Example Consider the previous POWER function project and use Simple weights from the table : 2 inputs, 1 output, 0 inquiry, 0 master file, and 0 interfaces UFP = 3* 2 + 4*1 + 3*0 + 7*0 + 5*0 = 10 consider the 14 complexity factors : 0-data comm; 0-distrib data; 0-perf criteria; 0-hardware usage; 0-transaction rate; 1-online data entry; 0-end user efficiency; 0-online update; 5-complex computation;0-reusability; 0-ease of install; 0-ease of operation; 0-portability; 1-maintainability: TCF = .65 + (.01 * 7 ) = .72 FP = UFP * TCF FP = 10 * .72 FP = 7.2 This is just the “size/complexity” (see next slide)

Function Point Example (cont.) What does 7.2 function points mean in terms of schedule and cost estimates ? One can receive guidance from IFPUG (International Function Point User Group) to get some of the $/FP or person-days/FP data. With “old IBM services division” data of 20 function points per person month to perform “complete” development, 7.2 FP translates to approximately .36 person months or (22days * .36 = 7.9 person days) of work. Assume $7k/person-month, .36 person months will cost about $2.5k.

Some Function Points Drawbacks Requires “trained” people to perform estimates of work volume or product size, especially the 14 technical complexity factors. While IFPUG may furnish some broader data, Cost and Productivity figures are different from organization to organization. e.g. the IBM data takes into account of lots of corporate “overhead” cost Some of the Complexity Factors are not that important or complex with today’s tools.

COCOMO Estimating Technique Developed by Barry Boehm in early 1980’s who had a long history with TRW and government projects (initially, LOC based ) Later modified into COCOMO II in the mid-1990’s (FP preferred but LOC is still used) Assumed process activities : Product Design Detailed Design Code and Unit Test Integration and Test Utilized by some but most of the software industry people still rely on experience and/or own company proprietary data. Note : Requirements not included!

COCOMO I Basic Form for Effort Effort = A * B * (size ** C) Effort = person months A = scaling coefficient B = coefficient based on 15 parameters C = a scaling factor for process Size = delivered source (K) lines of code

COCOMO I Basic form for Time Time = D * (Effort ** E) Time = total number of calendar months D = A constant scaling factor for schedule E = a coefficient to describe the potential parallelism in managing software development

Originally based on 56 projects Reflecting 3 modes of projects COCOMO I Originally based on 56 projects Reflecting 3 modes of projects Organic : less complex and flexible process Semidetached : average project Embedded : complex, real-time defense projects

3 Modes are Based on 8 Characteristics Team’s understanding of the project objective 2. Team’s experience with similar or related project 3. Project’s needs to conform with established requirements 4. Project’s needs to conform with established interfaces 5. Project developed with “new” operational environments 6. Project’s need for new technology, architecture, etc. 7. Project’s need for schedule integrity 8. Project’s size range

COCOMO I For the basic forms: Effort = A * B *(size ** C) Time = D * (Effort ** E) Organic : A = 3.2 ; C = 1.05 ; D= 2.5; E = .38 Semidetached : A = 3.0 ; C= 1.12 ; D= 2.5; E = .35 Embedded : A = 2.8 ; C = 1.2 ; D= 2.5; E = .32

Coefficient B Coefficient B is an effort adjustment factor based on 15 parameters which varied from very low, low, nominal, high, very high to extra high B = “multiplicative product” of (15 parameters) Product attributes: Required Software Reliability : .75 ; .88; 1.00; 1.15; 1.40; Database Size : ; .94; 1.00; 1.08; 1.16; Product Complexity : .70 ; .85; 1.00; 1.15; 1.30; 1.65 Computer Attributes Execution Time Constraints : ; ; 1.00; 1.11; 1.30; 1.66 Main Storage Constraints : ; ; 1.00; 1.06; 1.21; 1.56 Virtual Machine Volatility : ; .87; 1.00; 1.15; 1.30; Computer Turnaround time : ; .87; 1.00; 1.07; 1.15;

Coefficient B (cont.) Personnel attributes Project attributes Analyst Capabilities : 1.46 ; 1.19; 1.00; .86; .71; Application Experience : 1.29; 1.13; 1.00; .91; .82; Programmer Capability : 1.42; 1.17; 1.00; .86; .70; Virtual Machine Experience : 1.21; 1.10; 1.00; .90; ; Programming lang. Exper. : 1.14; 1.07; 1.00; .95; ; Project attributes Use of Modern Practices : 1.24; 1.10; 1.00; .91; .82; Use of Software Tools : 1.24; 1.10; 1.00; .91; .83; Required Develop schedule : 1.23; 1.08; 1.00; 1.04; 1.10;

An example Consider an average project of 10Kloc: Effort = 3.0 * B * (10** 1.12) = 3 * 1 * 13.2 = 39.6 pm Where B = 1.0 (all nominal) Time = 2.5 *( 39.6 **.35) = 2.5 * 3.6 = 9 months This requires an additional 8% more effort and 36% more schedule time for product plan and requirements: Effort = 39.6 + (39.6 * .o8) = 39.6 + 3.16 = 42.76 pm Time = 9 + (9 * .36) = 9 +3.24 = 12.34 months I am cheating here!

Try the POWER Function Example POWER function was assumed to be 100 loc of C++ code, fairly simple (or Organic), and nominal for B factor: Effort = 3.2 * 1 * ( .1 ** 1.05) = appr. 0.3 person- month Time = 2.5 * ( .3 ** .38) = appr. 1.5 months Note that while it takes only (.3 * 22 person days = 6.7 person days of effort), the total project duration will be 1.5 months.

Some COCOMO I concerns Is our initial loc estimate accurate enough ? Are we interpreting each parameter the same way ? Do we have a consistent way to assess the range of values for each of the 15 parameters ?

COCOMO II Effort performed at USC with many industrial corporations participating (still guided by Boehm) Has a database of over 80 some projects Early estimate, preferred to use Function Point instead of LOC for size; later estimate may use LOC for size. Coefficient B based on 15 parameters for early estimate is “rolled” up to 7 parameters, and for late estimates use 17 parameters. Now coefficient B is further expanded to 29 “factor”

Let’s look at Our 3 Estimates for “POWER” Work Breakdown Structure and personal experience: Effort : 5 person days Time : 3 calendars (done in parallel) Function Point and using IBM service division data: Effort : 7.9 person days Time : 7.9 calendar days (done with 1 person) COCOMO I and using Organic, 100 loc, and nominal for all B factors: Effort : 6.7 person days Time : 1.5 calendar months

Other Estimation Models There are many tools and models , but none seem to have dominated the software field. Many practicing professionals still depend on personal and proprietary data. Some other early models : Walston-Felix SLIM (commercial-proprietary)