LHC Injection and Dump Protection

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

LHC 18 & 19 April 2015 At 450 GeV with bumps, no increased MUFO activity. Beam screen 15R8 warming up to 80 K, ongoing for the day 09:00: Orbit studies.
SECTOR TEST PREPARATION W. Bartmann, C. Bracco, J. Uythoven LIBD Meeting, 10-Feb-2015.
Day ● 09:00-14:00: Collimation setup 3.5 TeV – Slowed down by losses induced by tune hump. – 48 collimators set up. – Beam dumped by ATLAS during.
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
Injection and Extraction Losses W. Bartmann with many inputs from: R. Appleby, R. Assmann, P. Baudrenghien, V. Boccone, C. Bracco, B. Dehning, E. Gianfelice,
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Evian LHC BC workshop January LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
BLM update procedure: - Updated the RT software - Updated the BLETC firmware (ver _A) - Changed the firware version in the MASTER tables and generated.
MKI failure event 17-April-11 Recall from logbook: MKI D (1st one seen by the beam) had a real flashover between the two sets of 36b during the 3rd 72b.
Transfer Line Test preparation meeting V. Kain, R. Alemany.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Injection status W. Bartmann, C. Bracco, B. Goddard, V. Kain, A. Macpherson, M. Meddahi, S. Redaelli, J. Uythoven, J. Wenninger LIBD Meeting, 20 th Sept.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
HL-LHC WP14 2 nd meeting: Intercepting devices and failure cases to be studied Anton Lechner, Jan Uythoven.
MPP Workshop: Injection System C. Bracco on behalf of ABT Acknowledgments: STI, ABP, BI,LHC and SPS OP.
V. Kain AB/OP1Chamonix XV What is required to safely fill the LHC? V.Kain AB/OP Input from: B.Goddard, M.Jonker, Y.Kadi, R.Losito, V.Mertens, B.Puccio,
Aperture measurements during LHC commissioning 2017
C. Bracco, R. Bruce, B. Goddard, C. Wiesner, A. Lechner, M. Frankl
Use of a Diamond BLM System in the LHC Ring
The TV Beam Observation system - BTV
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Use of a Diamond BLM System in the LHC Ring
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
SPS extraction, transfer lines, injection
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Jan Uythoven For discussion
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
LHC injection W. Bartmann, M.J. Barnes, C. Bracco, F. Burkart, E. Carlier, B. Goddard, V. Kain, R. Steerenberg, L. Stoel, F. Velotti, C. Wiesner, C. Xu.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday 14th March Second fill with pilot + 3 nominal bunches
Safe Injection into the LHC V.Kain AB/CO
FCC-hh injection group 7
Safe Injection into the LHC V.Kain AB/CO
Thursday morning – optics correction
CNGS Primary Beam Results 2010
Monday – recovery from MKI flashover
LHC commissioning Week 38
Lost at 12:05 to power converter (RTQX2.R1) problem
Objects Capable of Touching the Beams
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 35 – Technical Stop and Restart
Planning at 5 o’clock meeting Friday
Yesterday morning Held 1647 for a while – SPS kicker problem
Wednesday 03/11 – The Plan Finish electron-cloud program:
(on behalf of the LHC team)
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Chamonix Workshop XIV CERN - 17th-21st January 2005
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Wednesday 13th 9:30 Stable Beams… with 1 pilot and 2 nominals
Machine protection and closed orbit
Programme for Friday 9 July
Machine Protection Issues for LHCb
Plan for 1 m b* J. Uythoven & J. Wenninger
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Beam Stability of the LHC Beam Transfer Line TI 8
Presentation transcript:

LHC Injection and Dump Protection W. Bartmann on behalf of the ABT team LHC Beam Commissioning Workshop Evian, 19-20 Jan 2010

Commissioning Plan: Injection Protection Calibration of BLMs   Centering/beam size of TCDIs and setting to 4.5 σ     Check phase space coverage Check local MSI protection   TDI/TCLI centering/beam size and setting to ~7 σ TDI/TCLI check against MKI failure 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

TCDI set-up transfer line collimation Centering OK for TI2 and TI8 TCDIs Beam size: measured only for TCDIs upstream the TED, i.e. 2/6 per TL Problems: normalization to intensity difficult because of poor BCT resolution in TL saturation of BLMs with fastest integration time scale crosstalk between BLMs Set TCDIs to 4.5 σ: DONE for all TCDIs, but theoretical σ taken Check phase space coverage: NOT done Check local MSI protection: NOT done 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

TDI and TCL set-up (I) vertical passive injection protection system Set-up no major problem: Beam edge defined at 5.7 σ by collimation system few mm jaw asymmetry to understand for B2, beam well centered on adjacent BTVs TDI already protected LHC from overinjection or missing injection kick. Beam size at TDI NOT measured upper jaw: +6 mm lower jaw: -2 mm 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

LHC Beam Commissioning WS, Evian 2010 TDI and TCL set-up (II) Losses and scraping studied, also with Beam Condition Monitors from LHCb and ALICE Problem: overinjection– now works for B1 but not B2 (losses on MQXA (Q3) R8 which triggers BLMs) 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

Injection of 1 pilot bunch with TCDIs.. … at nominal 4.5 σ settings with losses from tails (no SPS scraper): Already close to BLM interlock limit for 40 μs integration time! Beam 1 Beam 2 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

LHC Beam Commissioning WS, Evian 2010 Tail Scan with TCDIs Tail Scan in TI2 Intensity: 1.2e11 Jaws set around derived beam centre Jaw opening increased in steps Very significant exponential beam tails… Scraping necessary?!? 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

Injection with higher intensity 2e10 protons, with SPS scraping, 6 σ horizontal and 4.5 σ vertical collimator settings very clean for B2 B1 has larger losses Beam 1 Beam 2 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

Commissioning Plan: Dump Protection Correct orbit in point 6 TCDQ – check SW interlock on beam position wrt TCDQ position   Set up TCDQ/TCS jaws Check of TCDQ protection Calibration of beam loss signal and protons lost at TCDQ Aperture in P6 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

TCDQ/TCSG (I) protects Q4 and downstream elements …in case of asynchronous beam dump or asynch. firing of MKD kickers where part of beam is not absorbed by TCDS TCDS (fixed) – 6 m long diluter protects extraction septum TCDQ/TCS (mobile) – 7 m long diluter kept at about 7-8 s from the beam, at all times 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

LHC Beam Commissioning WS, Evian 2010 TCDQ/TCSG set-up (II) Centering of TCSG and TCDQ: DONE Problems: movement sense inversion for B2  solved (Mechanical inversion in tank) setting resolution of 0.1 mm, but change of 0.11 mm in setting was necessary? position reading problem  solved by mechanical fix to reduce the friction of the spring on LVDT change to potentiometer to avoid transducer problems  being considered Beam size and jaw tilts: NOT measured Set to nominal protect settings: DONE (theor. σ retraction) Relative setting of TCDQ to TCSG: DONE 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

TCDQ/TCSG set-up (III) Check of TCDQ protection (dump of debunched beam): Losses concentrated on dump protection devices, with 0.1% on collimators Beam1 losses Beam2 losses TCDS TCDQ TCP IR7 Asynchronous dump tests: 4 bunches, B2 Sweep shape on BTVDD as expected 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

LHC Beam Commissioning WS, Evian 2010 How far did we get… Injection Protection Dump Protection Calibration of BLMs  Centering/beam size of TCDIs  Set TCDIs to 4.5 σ  Check phase space coverage  Check local MSI protection  TDI/TCLI centering/beam size with circulating beam Set TDI/TCLI to ~7 σ TDI/TCLI check against MKI failure Correct orbit in point 6 TCDQ – check SW interlock on beam position wrt TCDQ position Set up TCDQ/TCS jaws Check of TCDQ protection Calibration of beam loss signal and protons lost at TCDQ Aperture in P6 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

BLM: threshold/losses Problem Summary TCDI set up: losses in the ring already close to BLM interlock limit for pilot bunch…scraping in the SPS Ratio of one pilot bunch to one nominal SPS batch: 6.4e3 BLM saturation and dump thresholds for fastest integration time scale – general issue for fast loss BLM crosstalk while set-up TCDIs at.. BLM: threshold/losses B1/B2 5e9 (B1/B2) 1.6e10 Nominal 4.5 σ hor/vert 10/20 1·10-3/2·10-3 6.0 σ hor / 4.5 σ vert 30/60 3·10-3/6·10-3 6.0 σ hor / 4.5 σ vert + SPS scraping 103/105 10-1/10 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

LHC Beam Commissioning WS, Evian 2010 Problem Summary (II) TDI asymmetry 2mm offset in P8, to be understood, tank opening required TCDQ reading problem  fix in shutdown 7 mm misaligned for B1, being checked by experts Overinjection B2: losses at MQXA (P8) to be solved… 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

LHC Beam Commissioning WS, Evian 2010 3.5 TeV? Higher intensity? NOT ready Injection protection needs to be fully operational for maximum intensity of 1e12 per injection Needs adequate setting-up time TCDQ system should be tested for different β* squeeze steps TCDQ system needs to be operational for stable beam 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010

LHC Beam Commissioning WS, Evian 2010 2010 Strategy Refine procedure in view of what we learnt Need to solve the issues listed Get adequate commissioning time 20-Jan 2010 LHC Beam Commissioning WS, Evian 2010