Contracts, Change Order Administration and Claims Management

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

PROJECT MANAGEMENT 2 Chu Eu Ho Dept. of Civil and Environmental Engineering Massachusetts Institute of Technology.
Construction Engineering 221
1.1Definition of Construction:. Is the process by which material, equipment, machinery are assembled into a permanent facility. Is the process by which.
Construction Contracting
Managing Construction Risks
Project Procurement Management
Construction Management. Players Owner – owns project upon completion of construction –Private – owner owns land and pays for construction of facility.
Advanced Project Management Project Procurement/Contract Management Ghazala Amin.
Fixed price contract: A contract that provides a price for each procurement item obtained under the contract.
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
Procurement Management
AACEI Contingency Forum Contingency Management
NEC - Engineering and Construction Contract (ECC)
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
Construction Cost Estimating Class #2: Bidding Process Prof. Ralph V. Locurcio, PE.
Chapter18 Contract Construction 1CE 417, King Saud University.
Project Procurement Management
Project Procurement Management
Facilities Institute July , 2012 Houston, Texas Click to edit Master title style
CIVL202 Construction Engineering I
Time for a new standard - AS General Conditions of Contract
Introduction -Discussed preparation of the overall plan for the project - as well as its implementation. -The control system quantitatively measures actual.
Rethinking Construction Review of traditional construction models and a comparison of product development processes with other industries School of Architecture.
PROCEDURES FOR SELECTING THE CONTRACTOR
INTRODUCTION TO PUBLIC PROCUREMENT
Construction Engineering 221 Cost Estimating and Bidding.
Introductory to the “Basics” of Contract Types and Their Impact in the Management of Government Property Presented by: Fay K. Schulte, CPPM.
A SOUND INVESTMENT IN SUCCESSFUL VR OUTCOMES FINANCIAL MANAGEMENT FINANCIAL MANAGEMENT.
Hartley, Project Management: Integrating Strategy, Operations and Change, 3e Tilde Publishing Chapter 11 Procurement Management Embedding value into the.
PM/CAM Training H. Jeff Moore May 11, AGENDA Overview CM at Risk Design (Completion) / Build Lunch Break / Discussion – 11:30 AM – 12:30 PM CM Agency.
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
Contract Pricing Methods Ch 2. Lump Sum –Contractor bids 1 price for entire project –Estimate needs to be detailed –Design needs to be finished before.
Local Government Forum, 15 September 2010 Tender Negotiations, Indemnity and Exclusion of Liability Kathryn Walker Senior Associate (08)
Chapter 12 Procurement Management
Construction Contracts and Project Delivery Methods
Compensation events and claims Presented by Prof. Khem Dallakoti.
Richard E. Thompson II, Esq.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Advanced Project Management Project Procurement/Contract Management Ghazala Amin.
CONSTRUCTION CONTRACTS PRIME CONTRACTS Format and Major Components CHAPTER - 4.
TYPES OF CONTRACTS.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Agency Construction Management :CM NOT AT-RISK
July 14, Rural Electric Cooperatives Procurement/Contracting Guidance Roger Jones Region VIII Disaster Assistance Division.
Chapter 11: Project Procurement Management
Generic Documents for the Design, Build, Operate Contract for a Solid Waste Facility.
CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.
Project Procurement Management
1 CONTRACTING. 2 WHAT IS CONTRACTING ? CONTRACTING IS BASICALLY AN AGREEMENT BETWEEN TWO PARTIES, ONE CALLED THE CONTRACTING PARTY AND THE OTHER THE CONTRACTED.
CLAIMS MANAGEMENT. PRESENTATION OUTLINE INTRODUCTION TYPICAL CLAIMS AGAINST OWNER TYPICAL CLAIMS AGAINST CONTRACTOR CRITICAL PATH METHODS UTILIZATION.
University of Calgary Continuing Education Construction Contract Law and Documents Week 12 Changes Delays Claims Contract Documentation.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
IT PROJECT MANAGEMENT B U D I L U H U R U N I V E R S I T Y POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
Presented by: Jane Bachynski March 1, 2016 Avoidance and Management of Construction Claims – Fact or Fiction?
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
1 1 Effective Administration of Commercial Contracts Breakout Session # Session D06 Name: Holly Walker, CPCM Corporate Learning Solutions and Contract.
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 2 Construction Contracts.
HOW TO PROTECT YOUR INTEREST IN A SALE CONTRACT Focus on what you “get” when you sign!
Procurement Management
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Ch 11 - Procurement Management Learning Objectives
(Additional materials)
Types of contract selection based upon following:
ARCH 435 PROJECT MANAGEMENT
Unique General Conditions of the Alabama Building Commission (ABC)
Construction Contracts
Directed Change Constructive Change
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

Contracts, Change Order Administration and Claims Management Dieter J. Preiser, PMP

What is a Contract? A contract is a mutual business agreement recognized by law under which one party undertakes to do work (or provide a service) for a second party for a “consideration”. A contract is an agreement between two parties, one called the contracting party or owner and the other the contracted party or the contractor to perform a previously determined scope of work for a previously determined amount of money. 04/07/1438

Why do we need written contracts? Basic lack of trust Clearly establishes the risks and obligations of each party Provides means by which performance can be assessed and measured Provides means by which breaches can be identified Provides means by which default can be established Establishes the owner’s means of control Establishes the contractor’s scope of work 04/07/1438

What does a written contract do for us? A written contract provides the document by which risks, obligations, and relationships of both parties are clearly established, thus ensuring the performance of these elements in a disciplined manner. 04/07/1438

Goals of Contract Management and Administration The effective management and administration of contracts results in reducing risks, maximizing cost savings, minimizing claims, and improving economic return. 04/07/1438

How do contracts minimize risks? A contract provides the means to manage and allocate risks. You you want to “share” the risks appropriately through your contractual relationship. Your contracting strategy needs to be built around the relationship between the terms and conditions, and the accompanying risks and cost impacts. The type of contract and the specific language used should flow from these relationships. Failure to manage risks in this manner can result in cost overruns, loss of market, or loss of quality. 04/07/1438

Risk Areas Cost - possibility of overruns and other financial losses Time - delays in schedule and resultant loss of market Quality - loss of desired quality of engineering and construction 04/07/1438

Contracting Strategy Priority of project management goals Cost, schedule, quantity Status of project definition Schedule and cost constraints Facility startup date and availability of capital State of the economy Market urgency for product Number of competitive bidders Workload of competitive bidders Vendor backlogs 04/07/1438

Types of Contracts Lump-sum fixed price Unit price Fixed price with escalation (price adjustment) Guaranteed maximum price (target price) Cost plus incentive fee (time/cost goals) Cost plus fixed fee Cost plus percentage of cost 04/07/1438

Elements of Cost Labor Costs Material Costs Equipment Costs Overhead Costs - Direct and Indirect Profit 04/07/1438

Analysis of Cost DIRECT COST INDIRECT COST Items of Work OVERHEAD COSTS Profit Margin Costs which are incurred for specific items of work Difference between all costs and all income At the Job Operating Costs which cannot be allocated to specific items Costs which cannot be allocated to specific jobs The Work The Site The Firm The Motive COST FEE TOTAL CONTRACT SUM 04/07/1438

Fixed Price vs. Cost Reimbursable Definitions Agreement to perform the scope of work at a set price regardless of Contractor’s actual cost. Cost Reimbursable Agreement to perform work on a reimbursable basis. 04/07/1438

Fixed Price vs. Cost Reimbursable Basic Conditions Fair and reasonable price can be established using a detailed scope of work, complete design and specifications and known environmental and business conditions. Adequate professional inspection & supervision provided by other parties. Risk: Contractor assumes maximum amount of risk, and has incentive to perform economically. Cost Reimbursable Scope & cost of work not defined sufficiently to allow fixed price quotes. Qualified contractors unwilling to accept financial risk of fixed price. Owner wishes to exert more control, develop design as project progresses, or achieve technology transfer from contractors. Owner is required to be more sophisticated in contractor selection and oversight. Risk: Owner accepts most risk 04/07/1438

Fixed Price vs. Cost Reimbursable Advantages Less risk on the Owner, at least on the surface. Substantial amount of case law and administrative protocol. Overall cost known before project begins. Minimal Owner involvement Owner realizes price competition. Contractor has incentive to finish early. Cost Reimbursable Construction can be phased. Changes can be accommodated more easily. Reduces adversarial relations:Contractor & Owner are partners. Reduced Contractor contingency included in price. 04/07/1438

Fixed Price vs. Cost Reimbursable Disadvantages Adversarial relations Contractor may bear risk for conditions beyond his control Changes more likely to end in dispute. Contractor has no direct financial motivation to provide superior quality or service. Extra time required to complete the plans and specs. Cost Reimbursable Generally, the construction costs are higher. Increased Owner involvement. Final cost not known until project is finished. More detailed negotiations and contractor selection process. More cumbersome administrative and bookkeeping requirements. 04/07/1438

Fixed Price vs. Cost Reimbursable Applicability Routine projects. Conditions with an abundance of qualified contractors. Public works projects. Cost Reimbursable High-risk industrial or manufacturing projects (petrochemical, power, offshore). Situation where qualified contractors are scarce. R&D projects (aerospace, military). 04/07/1438

Types of Contracts Min Min Lump Sum Lump Sum + Variation Admeasurement Bill of Quantities Schedule of Rates Owner's Flexibility Owner’s Control (Contract Type) Cost + Fixed Fee Cost Reimbursable Cost + % Fee Max Max Client‘s Risk Min Max Contractor's Incentive to Perform Max Max Min Client’s Project Definition Firm Changeable

Project Schedule Duration vs. Type of Contract 5 Engineering Required to Start Construction 4 Construction Contract Type 3 Start of Construction Project Completion 2 1 Project Duration 1. Cost Reimbursable w / %Fee 2. Cost Reimbursable w / Fixed Fee 3. Cost Reimbursable w / Incentive 4. Guaranteed Maximum Price 5. Lump-Sum Fixed Price 04/07/1438

Phased Construction Traditional Construction Method Bid/Award Construction Phase Design (Single Construction Contract) Phased Construction Method Design Foundations Mechanical Structures Electrical Landscape Sitework Construction Phase (Multiple Construction Contracts) 04/07/1438

Precontracting Activities Score Pre-Quals and Prepare Bid Slate Establish Plan of Action Prepare Pre-Qual Documents Contractors Develop Response Bid Slate Management Approval Prepare Management Submittal Release Pre-Qual Management Review Prepare Contract Draft Review Contract Draft Revise Contract Draft Prepare Job Ex Meeting Release Bid Package Job Ex Meeting 04/07/1438

Pre-Contracting Activities Receive Bids Contract Award Contractor Prepares Bid Tech Bid Review Price Bid Review Prepare Management Recommendation Management Review Prepare Contract Contractor Signs Owner Signs Prepare Company Estimate Functional Review 04/07/1438

Pre-Qualification Process Financial Strength and Credit Rating Previous Experience on Similar Projects Organization Loss Prevention Program QA/QC Program Equipment Availability Availability of Key Personnel Current and Future Workload 04/07/1438

Components of Contract Package Invitation for the Bid Instructions to Bidders Bid Form Contract Form Schedule of Plant General Conditions or Provisions Special Conditions, Supplementary Conditions or Special Provisions 04/07/1438

Components of Contract Package Performance Schedule Price Schedules Scope of Work Specifications Performance Specification Proprietary Specification Design Drawings 04/07/1438

Contract Bonds Bid Bond (5% to 10% of contract price) Performance Bond (50% of contract price) Payment Bond Maintenance Bond 04/07/1438

Insurance Public Liability Insurance Builder’s Risk Insurance Provides coverage against bodily injury and property damage to third parties as the result of construction activities. Builder’s Risk Insurance Protects against loss/damage of structures and equipment Comprehensive Automobile Liability Insurance Special Policies 04/07/1438

CHANGE ORDER ADMINISTRATION

Change Order Administration An organized effort to eliminate unnecessary cost and time impact as a result of processing project work outside the scope of the contract. A Change is not a Claim. 04/07/1438

Contract Change Clause Fixed price contract require a change clause. Establishes the owner’s right to make changes and provides a mechanism for their administration and resolution. 04/07/1438

Types of Changes Formal Constructive Cardinal Via contract change clause Constructive Action of owner that has the effect of directing a change, although not initially documented as such. Cardinal Change totally out of scope of original contract. Should re-negotiate entire contract. 04/07/1438

Change Orders Virtually all project have change orders. Need to recognize their implications. Set up an effective management system to handle them. Minimize cost/time impact and prevent costly legal action. Modification of the contract. 04/07/1438

Sources of Change Orders Unanticipated site conditions Owner requested design modifications, additions or deletions Clarification of contract documents 04/07/1438

Disagreements Change or design development Scope of the change Material cost Equipment rental rates Acceptable profit Overhead cost Consequential effects of the change 04/07/1438

Change Orders Prior approval Unilateral change order After the fact Adverse effect on construction Unilateral change order Urgent situations or conditions After the fact 04/07/1438

Change Order Process Change Order Identification Bid Closing C.O. Award C.O. Design Cost/Schedule Analysis C.O. Request Bid Period Bid Analysis Prepare Bid Package 04/07/1438

Cost of Changes Engineering Construction Time Cost Flexibility 04/07/1438

CLAIMS MANAGEMENT

Typical Claims Against Owner Poor project planning Scope changes Constructive change orders Errors and omissions Contract accelerations and stoppages Site access or availability Other construction interference and delays Strikes and acts of God Low bidders 04/07/1438

Typical Claims Against Contractor Late completion - liquidated damages Out of specification materials Defective work Property damage 04/07/1438

Delays Excusable Delay Inexcusable Delay Concurrent Delay Beyond control of owner or contractor Inexcusable Delay Beyond the control of the contractor Owner caused changes to work Differing site conditions Suspension or termination of work by owner Concurrent Delay Two or more delays in same time frame 04/07/1438

Claims Analysis Brief of the case Owner’s position Contractor’s position Analysis and evaluation Recommendations 04/07/1438

Claim Prevention Suggestions Carefully analyze and consider exactly what you are building and precisely how it will be built so the contractor does not have to assume or guess about any aspect of the job. Complete the project design before the contract is bid, and if some parts of the project cannot be completely designed at bid stage, clearly identify them and its possible impact. 04/07/1438

Claim Prevention Suggestions Conduct a thorough review of the design prior to the bid stage to identify and correct any design errors or inadequacies. Give bidders sufficient time to carry out a complete review of the bid package and an investigation of the construction site. Allow enough construction time, remember in this context, time is not money. Do not assume that bidders will simply increase their bids to cover a short schedule. 04/07/1438

Claim Prevention Suggestions Identify with enough anticipation what type of contract will best suite the project. Think about every sentence included in the contract, why it is there and whether it is necessary. Clearly identify in the contract every operation that the contractor must accomplish to complete the job. 04/07/1438

Claim Prevention Suggestions Draft for clarity, not confusion. Use standard list of definitions, and always use the same defined word consistently. Consider material arrival schedules as part of the contract. Identify long-lead items and possible vendors in the bid package. Avoid sole-source procurement unless absolutely necessary. Clearly identify who will be responsible for material delays. 04/07/1438

Claim Prevention Suggestions Analyze all potential bidders before preparing a bid slate. Examine contractors’ prior contracting experience, claims history, management capabilities and financial ability. Carefully analyze contractors’ technical proposal paying particular attention to the proposed method of construction and the planned number of man-hours claimed necessary to execute the job. 04/07/1438

Claim Prevention Suggestions Seriously question the contractors’ excessively low bid. If you are forced to accept a low-ball contractor, anticipate a claim and work on it from the beginning. Be reasonable when analyzing the contractors’ complaints about changes and omissions. Negotiate settlement as soon as possible and keep in mind that the older the issue, the more difficult it will be to settle. 04/07/1438

Claim Prevention Suggestions Appreciate the contractors’ right to perform the contract in any fashion he deems appropriate, as long as the methods and results conform to contractually specified standards. Keep in min that the owner has the obligation to provide: a suitable construction site, accurate plans and specifications, well-defined scope of work, and inspection without interference. 04/07/1438

Claim Prevention Suggestions Understand how many factors can affect a contract and delay and disrupt the work. Cooperate to establish an atmosphere of understanding and mutual respect. Keep strict control of: progress reports, daily meetings, schedule revisions, cost estimates, change orders and their justifications, correspondence. Develop a solid document control plan. 04/07/1438

Contract Disputes Resolution Continuum Review Contract Documents for Completeness and Accuracy Identify Disputes Resolution in Contract Policies and Procedures Risk Assessment and Allocation Budget and Contract PM Selection Phase I - Program/Project Planning (NO COST RESOLUTION RISK) A Problem and Request for Information Denial of Entitlement and Cost Change Order Request Change Order Estimate and Negotiation Change Order Issued Budget and Contract Pre-construction Meeting Settlement Phase II - Contract Administration (LOW COST RESOLUTION RISK) 04/07/1438

Contract Disputes Resolution Continuum Selection of Outside Intervention Options Denial of Entitlement and Cost Negotiations Involving the Party Principals Contracting Officer’s Decision Rapid Response Team Disputes Review Board Phase III - Contract Identified Resolution (MEDIUM COST RESOLUTION RISK) Selection of Outside Intervention Options Construction Master Rent-a- Judge/Jury Selection of Venue Options Mediation Mini-Trial Phase IV - Outside Intervention (HIGH COST RESOLUTION RISK) 04/07/1438

Contract Disputes Resolution Continuum Selection of Venue Options Settlement Hearings Non-Binding Arbitration Binding Arbitration Litigation Phase V - Arbitration and/or Litigation (MAXIMUM COST RESOLUTION RISK) 04/07/1438