Saturday 12:00 Fill 1992 in stable beams.

Slides:



Advertisements
Similar presentations
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
Advertisements

LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
:30 meetingEBH 1  7:53 start VdM scans LHCb  8:18 beam dump: RF M2B1 crowbar (3 rd time within 24 hours)  Access for RF  Changed thyratron.
Summary of Week 30 G. Arduini, J. Wenninger Main aims: “Adiabatically” increase peak luminosity by emittance reduction Luminosity production.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
LHC Status Tue Morning 22-Aug
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Wed 27/7 – Thu 28/7 09:00 LHC Controls problems
Last 24 hours RQ4.L1 Lost going into collision Test ramp Storm
Machine Coordinators: G. Arduini, J. Wenninger
Friday 15th June 01:11 Injection.
Monday fill with 1092 bunches (6 h stable beams)
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
LHC Morning Meeting - G. Arduini
Monday 6th August & night
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Tuesday 08:30 Fill 2700 dumped by QPS on RCBXH2.L1
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
Summary of Week 16 G. Arduini, J. Wenninger
Coordination by E. B. Holzer & J. Wenninger Production
Thursday 10th May - morning
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Finally.... We had to wait a long time.... We had many problems....
Tuesday 22 November 2011.
Friday Morning 7:30 injection for fill 2908
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
Summary Thursday h21: Stable beams fill #1303.
Sunday/Monday & :30 Stable beams. Fill #1851.
Thursday morning 08:45 Stable beams fill 2855 for ATLAS/CMS VdMs.
Monday 14:00 beam dump Access:
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Mon Access for switching temperature probe DFB L7.
Summary week 18 Intensity ramp up & production
Fill 1743 Peak luminosity ~6.7 e32 Integratated lumi ~20 pb-1
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
LHC Status Tue Morning 22-Aug
Monday 11th June 08:10 Beam dumped in the ramp by OP. OFB did not start its function and kept the injection orbit. 08:50 Switch LHCb polarity to negative.
Thursday 22 September 2011.
Saturday :42 stable beams fill 3541
Friday morning 08:00 Stable beams with 840b.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Sat 15/10 New record bunch population profiting of the scrubbing period on Friday. Nb~1.42x1011p/bunch  110 MJ at 3.5 TeV. Filling slowed down by ZS sparking.
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
LHC Status Fro Morning 9-Sep
Saturday 24 September 2011.
Saturday 2nd October BLM threshold follow-up - Bernd Dehning and Joerg Wenninger Following MPP approval, Bernd Dehning has increased the BLM thresholds.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Coordination: Eva Barbara Holzer, Mike Lamont
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Thursday 20th July - morning
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Monday 10th December - morning
Monday 27th August & night
Wednesday 14:30 Fill 2011 dumped.
Wednesday morning / afternoon
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Saturday Luminosity production 1380 bunches
Saturday 26 November 2011.
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Presentation transcript:

Saturday 12:00 Fill 1992 in stable beams. Lumi for the first time above 2E33 cm-2s-1. This time tune shift of +0.002 before colliding. 11/18/2018 LHC 8:30 meeting

Lifetime 50-100 hours when going into collisions 11/18/2018 LHC 8:30 meeting

It did not last… 12:40 Dump due collimator interlock IR1 – communication lost. Access needed – power supply had to be changed. Could be SUE, but could be ‘normal’ failure. Problem with MAD in UJ16 – problem with the detection system. It had to be disable to close, then re-enabled (access piquet). During MKI2 softstart another erratic on MS3. Occurred above the normal operational voltage. Triggering of the other switches worked correctly. Access in IR2. 11/18/2018 LHC 8:30 meeting

Saturday PM MKI2 intervention S78 tripped on spurious nQPS signal. Installed magnetic cores on trigger inputs to MS3 tank. Replaced crate for MS3 & DS3 heater and reservoirs. Replaced 3 trigger units for MS3. Added 2 scopes for diagnostics. S78 tripped on spurious nQPS signal. Performed 3 softstart sequences, 20 shots in inject and dump – no problems. 21:45 Refill for physics. 23:00 Stable beams fill 1993, L = 2E33 cm-2s-1. Tune shift +0.002 – again lifetimes 50-100 hours. 11/18/2018 LHC 8:30 meeting

UFO End of fill @ 23:45 - arc UFO – 31L8 Fast and strong. 11/18/2018 LHC 8:30 meeting

Night Interlock problem on TCP.6R3. This collimator became ‘red’ on the fixed display during the fill, but no interlock. Alarm on limits. After the ramp down the interlock could not be reset. STI piquet disabled a resolver. 02:20 RF HOM interlock line2 B2 at injection. Reset by piquet, no T increase visible in logging, only small increase of power with current 03:50 Stable beams fill 1994, L = 2.03E33 cm-2s-1. Again tune shift +0.002. 04:40 Beam dumped – HOM again on line2 B2. Glitch on T reading visible in logging. Piquet compensated for a T offset in one reading. 11/18/2018 LHC 8:30 meeting

Refill… 07:00 Beam dumped just before stable beams by ATLAS. L over 2E33 cm-2s-1. Mini UFO in triplet region. Similar events have been seen in ALICE and LHCb. 11/18/2018 LHC 8:30 meeting

Saturday Nice fills …. that do not last – none longer than 1 hour ! Dropping intensity a bit… Cryo Pt8: problem with insulation vacuum on cold box. They are trying to work around. 11/18/2018 LHC 8:30 meeting

Fill list Fill Termination Peak L (cm-2s-1) Length (h) Int. L (pb-1) Dump cause 1975 STABLE 1.6E33 2.5 13 Cryo valve PROFIBUS (SEU?) 1976 ADJUST - BLM TCSG.L7 1977 SQUEEZE RF Module trip 1979 1.3E33 6 23 QPS RCO 1980 RAMP QPS RQTL7 1982 1.7E33 3 El. net 1985 1.75E33 11 50 1986 1.85E33 14 RF klystron vac 1990 7.5 41 PC trip RCBXV3.R1 1991 1.88E33 5 27 Cryo valve UJ16 1992 2E33 1 Collimator control PS US15 11/18/2018 LHC 8:30 meeting