Summary week 23 Luminosity production

Slides:



Advertisements
Similar presentations
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Advertisements

LHC Status Sat Morning 9-June Bernhard Holzer, Joerg Wenninger Status Friday Morning: 09:00h end of fill “studies” rf coupler fine tuning ADT gain reduced.
:30 meetingEBH 1  No beam during the morning:  4:15 – 9: V distributor: Recovery after electrical interruption  access for TI services.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
Friday 15th June 01:11 Injection.
Wednesday September 14th
Summary of week 7 Hardware Commissioning:
Thursday 09:30 VdM scan for CMS, standard ADT gain.
trigger and other general LBDS electronics
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
LHC Morning Meeting - G. Arduini
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
LHC Morning Meeting - G. Arduini
Saturday 12:00 Fill 1992 in stable beams.
Barbara Holzer, Jorg Wenninger
Monday 6th August & night
LHC Morning Meeting - G. Arduini
Fri 15th – Sun 16th June Friday Saturday Sunday Monday
Summary of week 22 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Tuesday 08:30 Fill 2700 dumped by QPS on RCBXH2.L1
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary of Week 16 G. Arduini, J. Wenninger
Bernhard Holzer, Joerg Wenninger
Coordination by E. B. Holzer & J. Wenninger Production
Mike Lamont, Jorg Wenninger
LHC Morning Meeting - G. Arduini
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Summary week 29 VdM scans Luminosity production
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Wire almost entirely through beam before BLM triggers dump
Saturday – Morning 7:36 beams dumped
Not the most productive 24 hours on record
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Thursday morning 08:45 Stable beams fill 2855 for ATLAS/CMS VdMs.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Summary week 18 Intensity ramp up & production
Tue/Wed 12/ :00 Probe beam back again
Thursday 26th July 13:21 Fill 2880 beam dumped
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday 11th June 08:10 Beam dumped in the ramp by OP. OFB did not start its function and kept the injection orbit. 08:50 Switch LHCb polarity to negative.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Polarity inversion 07:00 ALICE solenoid and dipole polarity switched to positive External Crossing angle polarity unchanged at injection/ramp & squeeze.
LHC Morning Meeting - G. Arduini
LHC - Week 38 Technical stop: Katy Foraz
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Week 25 Summary Coordinators: Mike Lamont and Barbara Holzer
Wednesday 23/2 Thanks CRYO!!!.
Thursday
Saturday 24 September 2011.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Coordination: Eva Barbara Holzer, Mike Lamont
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Monday 27th August & night
Thursday Morning/Afternoon
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Saturday 26 November 2011.
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Presentation transcript:

Summary week 23 Luminosity production Bernhardt Holzer, Jorg Wenninger

Sunday 23:50 Fill 2718 dumped by OP after almost 16 hours of stable beams. Refilling… 01:50 Fill 2719 in Stable Beams… for 3 minutes. Dumped by vacuum spike in Pt3 ~ 1E-6 - Q6.L3. ‘Normal’ losses when going into collisions. 02:20 Vac. expert increased interlock level to 4E-6. 03:00 Refilling… 04:07 Fill 2720 in Stable Beams … for 30 minutes. RF dump, crowbar on M2B1, circulator arc. Waiting for MKI8 temperatures to cool down… 11/7/2018 LHC 8:30 meeting

Vacuum spike Few % 11/7/2018 LHC 8:30 meeting

Monday morning 08:10 Beam dumped in the ramp by OP – OFB did not start and kept injection orbit. Try again… 11/7/2018 LHC 8:30 meeting

Overview of an excellent week Intensity per bunch : ~1.5E11 p/b Initial L : 6.2 - 6.7x1033 cm-2s-1 52% Luminosity LBDS TSU Access, PSB RF 11/7/2018 LHC 8:30 meeting

Fills of the week Integrated luminosity 1106 pb-1 Fill Day L (h) Int L (pb-1) Dump 2698 Mo 5:00 89 Vacuum 2700 Tu 1:40 33 QPS on RCBXH2.L1 2701 11:49 160 OP 2710 We 14:26 200 PM56 door/loss of patrol 2711 Th 2:39 51 FMCM, electrical perturbation 2712 10:30 Adjust mode, electrical perturbation 2713 Fr 0:06 6 SIS due to CMW communication problem 2714 1:43 37 OP  LBDS TSU issue 2717 Sa 15:40 Electrical circuit breaker RF klystron B2 2718 Su 14:50 199 2719 0:03 - Vacuum Pt3 2720 0:30 11 RF crowbar M2B1 Integrated luminosity 1106 pb-1 11/7/2018 LHC 8:30 meeting

Integrals – well over 5 fb-1 11/7/2018 LHC 8:30 meeting

Main faults There were many small problems, with max 2.5 hours time lost. Water cooled cabled RQ10.R1, heater PS on current lead RQ7.R1, vacuum Pt5 & Pt3, access door PM56, klystron circuit breaker… Two main items: PSB RF: lost ~7 hours on Wednesday (beam quality, repair). LBDS TSU (Trigger Synchronization Unit): lost ~11 hours Friday night, but this time includes a very useful low intensity machine cycle for measurements (see later). 11/7/2018 LHC 8:30 meeting

Faults : rare event On Thursday morning beam dump due to patrol loss / access door in PM56 – during the end of fill MD. The door (YCPS01=PM45) opened because it was not properly closed (but seen closed by the LASS contacts). Probably the effect of a pressure change… This situation can actually be detected, but no info in the CCC. OP should get a simple view to detect such situations. Another door in Pt2 was in the same state  went in to close it. 11/7/2018 LHC 8:30 meeting

Faults & problems : controls Problems with the orbit FB service unit (OFSU) are back (no version change !). No beam loss, but frequent restarts needed, tasks failing… Friday PM: FCG gateway blocking / delayed subscriptions (> 1 minute) when an application (lumi scan) that subscribed to several properties got disconnected by CMW. The blocking is not understood. Consequence : beam dump triggered by SIS due missing orbit corrector data after 40 second timeout. 11/7/2018 LHC 8:30 meeting

LBDS TSU issue Friday around 18:30 V. Mertens informed us that an error had been identified within the LBDS that would render the LBDS inoperable: no dump executed. 20:00: E. Carlier’s team had designed a simple surveillance system to react in time on such a failure. In a meeting in the CCC it was decided to: dump the current beam, implement and test the surveillance system, run the machine through the cycle with low intensity to exclude evident side-effects (duration ≥ 3 hours). 11/7/2018 LHC 8:30 meeting

LBDS TSU issue V. Mertens During the preparation for a review on “LBDS powering” on 20 June … (triggered by asynch. dump), an error source was identified on the LBDS test bed which would (if this error would occur) render the LBDS inoperable ( NO dump when requested) Trigger Synchronization Units (redundant TSUs, powered by redundant PS) are installed in one crate. Loss of +12 V, e.g. by short circuit on a card, would make all output stages unusable. Power failure will be detected but, due to the loss of 12 V, not be transmitted further down into the LBDS (power triggers/pulse generators). 11/7/2018 LHC 8:30 meeting

LBDS TSU continued V. Mertens Simple (yet functional) fix was build and applied by midnight Friday. Detects 12 V loss and injects trigger into re-triggering system (i.e. behind TSUs). If 12 V loss in TSU crate  asynchronous dump (synchronization units not working). Note: Potential error source existed since beginning. Would have been – and will be – eliminated by new layout / design of TSU system in LS1. Upcoming: Review of LBDS powering (June 2012). Review of first years of operational experience (October / November 2012). 11/7/2018 LHC 8:30 meeting

trigger and other general LBDS electronics LBDS Beam 2 (UA67) 15 + 1 pulse generators TSU Fixing a (potentially fatal) safety problem V.Mertens for E.Carlier, N.Magnin, A.Patsouli

trigger injection into re-triggering system LBDS Beam 1 (UA63) trigger injection into re-triggering system pulse generation on detection of 12 V loss TSU BETS Fix will be improved in TS2 (surveillance of 12 V surveillance, …) Splitting of TSUs probably too involved for short stops New TSU layout/design in preparation, to be implemented in LS1 (taking latest information into account)

A happy end… Thanks to the prompt reaction of E. Carlier’s team from TE/ABT the solution was installed the same evening… … and the LHC was back with high intensity the next morning ! 11/7/2018 LHC 8:30 meeting

Luminosity, CMS VdM & filling scheme On Tuesday we reverted back to the filling scheme with 3 non-colliding bunches for ATLAS/CMS. On Wednesday CMS and ATLAS changed their online luminosity calibration: CMS -2.2%, ATLAS +0.25%. Thursday: VdM scan for CMS, standard ADT gain. One scan with ±3 sigma TOTAL separation. Two scans with ± 6 sigma TOTAL separation. No losses. 11/7/2018 LHC 8:30 meeting

Tune activity during the VdM scans T. Pieloni, X. Buffat 11/7/2018 LHC 8:30 meeting

Losses in collision Losses when going into collision were observed in 2 fills. In the second case, the beams were dumped by BLMs in IR7 due to heavy losses on many B2 bunches. Case 1 : Fill 2700, B2 losses 11/7/2018 LHC 8:30 meeting

Losses in collision Case 2: fill 2716 was lost when going into collisions. Heavy losses on B2, starting already before colliding. Large(r) bunch int. spread. 11/7/2018 LHC 8:30 meeting

ADT gain tests at end of fill (1) Thursday morning: test with reduced ADT H gain. Separation in IR1 & IR5. Increased activity on tune with reduced ADT gain and with separation. Activity on the batches of 72 bunches (B1 &B2) on the ADT side, losses on a few isolated bunches of B1. 11/7/2018 LHC 8:30 meeting

ADT test (2) BBQ activity Separation ADT gain 11/7/2018 LHC 8:30 meeting

ADT test (2) Losses, B1 11/7/2018 LHC 8:30 meeting

Measurement cycle Low intensity cycle following TBDS TSU intervention was used to check tunes and chromaticity with probe bunches. Horizontal Q’ was found negative, around -1 in squeeze + collisions. Q’ trim to around +1 for squeeze/collisions on Saturday morning. Q Q’ 11/7/2018 LHC 8:30 meeting

TCSG IR6 alignment check A systematic drift of the average position of B2 BPMs in IR6 (wrt collimator alignment reference) lead to dumps by SIS in previous weeks. A TCSG6 re-alignment on Monday confirmed that the REAL beam position is correct (center shifts of 8 um (B1) and 160 um (B2)). BPM reference positions have been reset to the readings. 11/7/2018 LHC 8:30 meeting

RF cavity fine tuning Friday morning our RF colleagues used an end of fill to fine tune the cavities. Clear reduction of the klystron forward power. Tuning 11/7/2018 LHC 8:30 meeting

Injection kicker heating In the past week we heated the MKIs, and the temperature limits could be increased by 1-2 degrees on some magnets / probes. But the problem has come back this morning. Filling delayed due to MKI8 temperature. This morning 11/7/2018 LHC 8:30 meeting

MKI2 UFO dump – rare injection event UFO dump at injection Wed 3:30 AM, ~300 ms after injection, with 144+12 bunches in the machine. BCT 11/7/2018 LHC 8:30 meeting

For discussion – Leap second Saturday 30th June at 23:59:59 a leap second will be added to the UTC time. This will shift NTP time distributed over the network from the UTC time distributed by the timing systems (all machines). A stop of all machines is required to adjust the timings systems. Question from timing team: Can the re-synch be done Mo 2nd July (all machines) or does it have to be done in the night of 30th June? Clearly the logging from difference source will be out of step. Probably okay, but should be ready for ‘emergency’ intervention .. just in case. 11/7/2018 LHC 8:30 meeting

Pending Impact of TETRA on hump / beam. 30 mins at injection with probe bunches. SPS Q20 extraction tests to TI2/8 downstream TED. During LHC downtime –injection OK from ALICE/LHCb needed. Access: TCLIB.6R2.B1 electronics and LVDT sensor. MAD PM15: motors of inner doors not working (at least 4 hours). RQTL11.R7B2 temp DFBAN spikes (~3 to 5 hours). BI in Pt4 (3-4 hours, working hours). MKA test in Pt4 (1-2 hours). TOTEM vacuum gauge (3 hours). MCBV18.L4B1 and RCO.A12.B1 to be repaired. 11/7/2018 LHC 8:30 meeting