Friday 07:00 Power glitch on the EDF network. Point 8 affected.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ion Commissioning: Thursday & Friday
Wednesday
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
LHC Operation Week 41 Coordination G.Arduini, M. Lamont
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
LHC operation in week 42 Coordination:, Malika Meddahi, Joerg Wenninger Thanks to OP crews, HW and SW teams + experiments Aims for the week Cure aperture.
Saturday 1.3 e32 Overnight Morning
Summary of Week 11: 14 – 21 March
Tuesday 23/11/10 8:00 Physics fill #1511 dumped
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
LHC Operation Week 38 Coordination G.Arduini, R.Bailey
LHC operation in week 39 Coordination: Mike Lamont, Jan Uythoven, Malika Meddahi Thanks to OP crews, HW and SW teams + patient customers Aims for the week.
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Friday 31st August & night
Week 36 plan Todo’s: And also: 12+b injection.
Week 35 – Technical Stop and Restart
Friday 14th December - morning
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Programme for Saturday 10 July
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday Fill 1364 (24 bunch) dumped at 07h
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Summary week 18 Intensity ramp up & production
Saturday Nov Stop proton operation. Switch back to ions
Thursday 26th July 13:21 Fill 2880 beam dumped
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Coordination: Eva Barbara Holzer, Mike Lamont
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Monday 27th August & night
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
HI2011 Commissioning Status
Monday 152 bunch operation summary
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Friday 07:00 Power glitch on the EDF network. Point 8 affected. 10:00 Recovered. Injection for Van der Meer scan. Problem with the UPS status for PIC fixed during the morning (reason for failure not totally clear) During the morning investigations in the injectors on the beam quality. 13:30 Start of Van der Meer scans 18:27 Beam dump due internal fault on MKB (fake vacuum reading: vacuum pressure ) - End of Van der Meer scans Intervention on the cryogenics for sector 23: change of a WorldFip receiver done with no stop of the Cryo plant 21:00 Injecting. Beam 2 Losses in the injection area and LHCb OK 22:00 LSS6 BPM Interlock verification with 312 bunches OK 02:30 STABLE BEAMS #1424 with 312 bunches: L0=1.3x1032 cm-2 s-1 03:29 Beam dump: UFO event 04:30 Injection. Losses on Beam 1 in the injection area  investigating

Injection losses Thu-Fri night Losses at TCTVB comparable for Beam 1 and Beam 2 Beam 1 Beam 2

Injection losses Thu-Fri night No significant improvement after capture optimization in the LHC Before opt. After opt. RF capture opt.

Injection losses Thu-Fri night No significant losses in LHCb and TCTVB when kicking without injecting beam and no dependence on longitudinal emittance of the extracted beam  RF capture in the LHC not responsible for the observed effect. Kick without beam

Injection losses Thu-Fri night From LHCb (R. Jacobsson): Losses on rising edge of kicker waveform At -700 ns At -100 ns Losses on falling edge of kicker waveform At +9250 ns Consistent with satellite/uncaptured beam in the SPS Thorough verification of the beam quality in the SPS started in the night and continued during the morning (T. Bohl): found 800 MHz RF frequently not locking to reference (given by main RF system)  source of noise, blow-up and uncaptured beam even at SPS flat-top  corrected  need for remote monitoring of the RF frequency and/or alarms when not correct Increased the LHCb BCM threshold by factor 3

Injection losses Thu-Fri night Verification that 800 MHz was the origin of the losses observed during the night Thu-Fri. Comparison of the losses at TCTVB.R8 confirmed by LHCb observations (R. Jacobsson) SPS 800 MHz RF not OK SPS 800 MHz RF not locking SPS 800 MHz RF OK

Stable beams #1424 3.5x1013 p/beam in collision (~20 MJ/beam) L0>1.3x1032 cm-2 s-1  Emittance in collision 2.6 um (2 to 2.4 um at injection). Initial lifetime in collision ~4 h rapidly recovering to 20 h Damped by UFO event after 1 hour (~400 nb-1)

UFO event UFO event on beam 2 in triplet R8. Beams dumped by LHCb

Plans Friday overnight Physics 312b 12 hour fill Saturday Saturday overnight Sunday TL BL calibration + Injection checks with 32 bunches 4 hours Quench test 6 hours Sunday overnight Physics 360b This was the initial plan: to be reviewed on the basis of the results of the investigations for injection B1

Orbit shift versus TCT check: OP Periodic loss maps Betatron loss map done week 40. Orbit shift versus TCT check: collide 1 bunch and check the TCT center change as compared to predicted orbit change. All in one ramp, squeeze, collide - 1 shift Plus test of 'dynamic' references for the OFB (varying Xing.separation bump): injection, then test of ramp + first part of squeeze IR aperture at 3.5 TeV 50 ns – pilot runs After 3-4 fills with ~400 bunches Push beam-beam tune shift with 150 ns one test already performed with #1410

BI studies – list to be updated Check the linearity of the fast BCT’s in the new configuration for nominal bunches Tune the High BW/Low Gain fast BCT calibration for the coming ion run Measure the High BW/Low Gain fast BCT sensitivity limit and linearity for low intensity bunches (ion run) Re-check BPM sensitivity limit Calibrate the abort gap over the whole ramp Check the abort gap acquisition gate timing resolution and stability Commission BGI in preparation to ions – started! Check BSRT/BGI/BWS cross-calibration including corresponding emittance logging Test and compare bunch/bunch profile measurement via BWS and/or BSRT PLL studies during ramp continued JJG: for all this, we would need the 2 rings for a few hours at 450 GeV then a ramp and again a few hours at 3.5 TeV. This would be really difficult to fit in a 4 hour slot. 8 would be perfect but we could try with 6.

Other Abort Gap Cleaning – on at injection for physics continue testing Injection studies 32 Bunches when required (344 bunches) Injection studies with 50 ns Transfer line collimator cross-talk calibration Quench test at 3.5 TeV – pilot beam Bernd & co

Experiments 50 pb-1 total (20 delivered so far) 10 fills@3 pb-1 ~ 10 good days Alice – fill without dipole Totem – dedicated fill Totem – 90 m optics LHCb – switch polarity – plus test ramp (combine with BI plus map)

Access Requests Verification of the flange alignment between MSIB and MSIA  2 hours TE/VSC Verification MSI transition in point 8  ½ day (Radiography) IR1 solenoid (for e-cloud suppression) controls Intervention on DCBCT  P. Odier (2 hours) ALICE pixel cooling: 1 h (for preliminary investigations) + 8 h