Monday 6.9. 04h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Day ● 09:00-14:00: Collimation setup 3.5 TeV – Slowed down by losses induced by tune hump. – 48 collimators set up. – Beam dumped by ATLAS during.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Aperture measurements during LHC commissioning 2017
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
SPS extraction, transfer lines, injection
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Summary Friday h38: Ramp down and pre-cycle.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
Tuesday TOTEM and transverse loss map (1) OK
Tuesday 23/11/10 8:00 Physics fill #1511 dumped
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
LHC commissioning Week 38
LHC Injection and Dump Protection
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Lost at 12:05 to power converter (RTQX2.R1) problem
Saturday 2/4/ :00-09:00 Problems with SPS:
Tuesday 20 March 2012.
Week 35 – Technical Stop and Restart
Monday February 28th 8h00: Injection
Week 36 Machine coordinators R.Assmann, R.Bailey
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
Tuesday 9th November 10:02 Fill beams dumped
Sunday
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
Wednesday 03/11 – The Plan Finish electron-cloud program:
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
Planning for the week MO M P
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 24 October hours of 25ns MD
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
MD Planning Fri – Sat (1. – 2.7.)
Summary Tuesday h23: Machine closed. Precycle started.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
LHC status - Week 35 G. Arduini, M. Lamont Main aims:
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Wednesday h18: 228b fill lost just before start of ramp.
Injection Studies: 50 ns ABT/BTP.
Another Immortal Fill….
Wednesday 6.10 Morning: Quench test at 450 GeV
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Monday 6.9. 04h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated corrections and removed it in order to prepare the knob correction. The one for IP8 is not good and needs to be redone. Another iteration on beta beat measurement. 10h23: dump because of losses on un-maskable channel MBW.B6L7 11h47: Injection/Injection protection 19h52: Transverse damper Gains were changed for beam 2 and beam 1 dampers and emittances recorded. Emittance increase again does not depend on damper gain. Could run at higher gain than our standard gains. 23h05: PLL commissioning 04h08: k-modulation 08h30: Collimation setup 450 GeV 8:30 meeting

Dump Event 10h23 8:30 meeting

Beta Beat 3.5 TeV B1 R. Tomas et al 8:30 meeting

Beta Beat 3.5 TeV B2 R. Tomas et al 8:30 meeting

Summary of TL and Injection setup with trains I (B. Goddard et al) TDI setup again checked for B1 with angle scan: confirmed the 900 urad misalignment of the lower jaw New TDI thresholds trimmed into the beam process Single trains of 4 nominal bunches on LHC3 cycle extracted to TT40/60 and TI2/8 TEDs TI2 and TI8 steered back to July 2010 references. New working references taken (not yet defined as official references) Settings copied LHC3 -> LHCFAST1- kicker synchronisation checked B1 with beam trajectories and B2 with just OASIS keep present settings of 69 us for B1 and 54 us for B2 8:30 meeting

Summary of TL and Injection setup with trains II (B. Goddard et al) Injection into LHC then looked good for both beams with single 4b train Both beams injected cleanly B1 & B2 losses only from over-injection above IQC thresholds B1 2nd batch injected very cleanly with no loss warnings and IQC all green B2 could not inject 2nd batch as BPF FALSE - BCT fix needed Injection oscillations looked fine - injecton NOT steered Transfer line losses OK - some TCDIs to re-center Next steps to do detailed TCDI adjustments - need to be able to fill with 48 bunches for this. 8:30 meeting

Batch Injection Long Injection Fill Injection of 4b per batch (0.9e11 per bunch) 8:30 meeting

Injection/Injection Protection Plan (preliminary) Monday : 12-19, 7 h - finish off TDI setups, steering of TLs with 1 train of 4b [BG, WB, CB] Tuesday: 12-20, 8 h - steering of TLs with 1 train of 4b, injection steering, setup of TCDIs in TLs, [BG, WB, CB] Wednesday: 12-23, 11h - finish setup of TCDIs, start injection protection validation checks, [BG, WB, JU] Thursday: 9-17, 8h - injection protection validation checks, [VK, WB, JU] Friday: 8-16, 8h - injection of 2 and 3 trains of 4b, [BG, VK, WB] 8:30 meeting

Summary PLL (R. Steinhagen et al) re-validated beam-transfer-functions (BTFs) with various damper settings - zero crossings at BTF phase-responses were within 10deg the same as during last measurements (and initial setup done last December) locked the PLL on tune and applied dp/p modulations to test the tracking bandwidth and tune measurement stability for various ADT gains and dQ'+-5 trims initial observations (more details in log): The PLL gave nice tune tracking signals, provided the excitation and set-bandwidth was large enough. With the tested excitation amplitudes no obvious beam size growth has been seen in addition to the already constant increase which seem to occur regardless of whether the damper was on/off (observation of the previous ADT expert tests) or whether the PLL excited the beam or not (this test) 8:30 meeting

Summary k-modulation Completed the intended measurement programme nearly as planned for the vertical plane in IR1 for crossing angles of -170, -100 and -50 urad We lost half of B2 due to a beam instability (seen on the tune) while modulating Q2L1 with a crossing angle of +100 urad (Q1 scans were OK). We aborted the missing Q2 and Q3 modulations in favour for some scans in H since this would have been the fourth measurement point in the vertical plane. For the horizontal plane only the modulation of Q1 at 2 and 1 mm separation has been performed. The feed-down effects were generally small (kicks much below 1urad) but the global r.m.s. generally at least four times larger than the residual BPM noise floor. 8:30 meeting

Example Result (more in logbook) Q1.L1 changed: +k, -k Q1.R1 changed: +k, -k Delta k = 2e-5 Tm Offset: BPMSW.1L1.B1 (V) wrt to quad center: ~ 0.8 mm 8:30 meeting

Ahead Add to weekly plan: IR aperture measurements Interlock tightening at 450 GeV RF setup, once we have train commissioned Access requests: QPS (3h), CMS, ALICE in shadow 8:30 meeting