Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.

Slides:



Advertisements
Similar presentations
Mo morning set up 228 bunch injection (36 bunch trains), ramp, squeeze, collisions h luminosity (depending on experiments) ATLAS length scale calibration.
Advertisements

Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
Saturday 7ish – refill for RP set-up 9:15 Going for Roman pot alignment. Stefano is coming. 12:10 TOTEM: Alignment of horizontal RPs B2 finished, short.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Fri – Sat - Sunday 30 Sept - 2 nd October Friday  06:00 Operator dump fill #2171, integrated lumi 75 pb-1.  90 m  * optics Optics ok, collisions at.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
:00 meetingEBH 1  8:40 – 9:30 access for MKB (dilution kicker) LBDS B2 – PLC exchange  Pre-cycle  11:17 – 12:50 RF problem with ion injection.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ion Commissioning: Thursday & Friday
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Saturday 24 March 2012.
Wednesday September 14th
Monday 11/07: Recovery Plenty of accesses.
Saturday 30th June - Sunday: Rocky !
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Saturday 12:00 Fill 1992 in stable beams.
Summary of Week 11: 14 – 21 March
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC commissioning Week 38
Thursday morning 09:30 Dump of pPb fill.
Lost at 12:05 to power converter (RTQX2.R1) problem
Friday 31st August & night
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 36 plan Todo’s: And also: 12+b injection.
LHC Operations overview Week 28 – Getting back
Week 35 – Technical Stop and Restart
Friday 14th December - morning
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Monday Morning – recovery from cryo.
Tuesday Loss maps in the night:
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
Friday morning 10:30 Optics measurements and corrections.
LHC Morning Meeting - G. Arduini
Yesterday’s morning’s controls issues
Friday Morning 7:30 injection for fill 2908
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
LHC Morning Meeting - G. Arduini
Sunday/Monday & :30 Stable beams. Fill #1851.
Tuesday morning 08:30-09:00 Squeeze with probe.
Tue/Wed 12/ :00 Probe beam back again
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Sat morning Until 12:40: Loss maps at injection
Thursday 22 September 2011.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Tuesday In the morning test cycle with probe for Q’ measurement.
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Tuesday – Morning and Evening
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Another Immortal Fill….
Monday 10th December - morning
Wednesday 26 October 2011.
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
31/3/2010 Difficult day… but at the end stable beams.
Tuesday
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of 90 m * “run” The Collimator piquet disabled a resolver that was giving wrong measurement -> fix Saturday morning 10:07 At flat top for 90 m optics, problem with TCTs IP5 12:50 In collision, except IP5, dump beam to give access for collimators in point 5 15:30 Collimator access finished 17:11 Ramping 19:00 Beams into collisions: Collisions found. 20:00 ALFA puts pots in on B1 and Totem on B2 20:30 Beam dumped due to an inner limit on ALFA RP that had not been updated. B1 dumped. Dump B2 manually afterwards. Refill. 22:00 Injecting again – decide to go for optics measurements as time is tight to do pot alignment and data taking before 7:30 deadline Saturday morning 00:23 Lost end of squeeze: We lost the RQTF.A45B2 03:03 Second ramp of the night. During squeeze, UPS down in UJ56 01/10/2011 LHC 9:00 meeting

90 m optics Filling scheme: 2 big, 13 small bunches 01/10/2011 LHC 9:00 meeting

Collisions found Optimization of IR 1 and 5 after collisions were found The BRANS in IP1 and 5 show noting, but signals can be seen in IP 2 and 8 01/10/2011 LHC 9:00 meeting

Collimator in IP5: TCTH.4L5.B1 and TCTVA.4L5.B1 Found a short circuit somewhere on the 24V power supply used for switches and also other components Problem came from the downstream anti-collision switches at collimator side (in the tunnel). There was a short circuit between one of the conductor and the ground of the connector In the tunnel and finally we found that inside a 50 pins connector of the long cable, a small wire of copper was not correctly crimped and was slightly in contact with the metallic cover of the connector This cable and his connectors have been installed during the cabling campaigns in 2006 and never touched since, so it's difficult to understand why the problem occurs only now... Jerome Lendaro 01/10/2011 LHC 9:00 meeting

The small wire of copper... 01/10/2011 LHC 9:00 meeting

Optics measurements for * = 90 m Ramp 1: We lost about 1/3 of the beam at the start of the ramp. It seems that the longitudinal blow-up was pushing the bunch length up a lot and we had huge off-momentum losses at point 3. End of un-squeeze, beams lost due to trip RQTF.A45B2 Ramp 2: Loss of a UPS in the middle of the unsqueeze To be noticed that for both unsqueeze, the QFB was continuously switching off for B1 Using 3 fat pilots per beam Should be better without longitudinal blow-up 01/10/2011 LHC 9:00 meeting

Expect UPS to be fixed during the morning Plan Saturday 7:30 Dump beam to prepare for VIP visit Point 2 8:15 RP check IP2 and IP5 9:45 RP check IP1 Around 12: search IP2, close machine Pre-cycle and then back to Physics Sunday: Physics Next week (besides physics) Abort gap cleaning at 3.5 TeV 25 ns MD Possibly large pile up MD Expect UPS to be fixed during the morning 01/10/2011 LHC 9:00 meeting