Extension of time and how it is granted to a contractor (Referencing JCT 2005)

Slides:



Advertisements
Similar presentations
B. Progress Schedule Schedule Costs –2002 C&MS … the cost of preparing and updating the schedule is incidental to all contract items. –2005 C&MS.
Advertisements

A Joint Code of Practice Objectives and Summary Presentation
CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension.
ISTISNA’.
Contracts – important issues
What is the Duty of Disclosure? If a barrister is retained by the solicitor, not directly by the client, then the primary duty of disclosure to the client.
‘CHANGES IN LAW’ Contractual Provision September, 2012 Topic for discussion Business Confidential Foster Wheeler Iberia/Chile Sep/2012.
LECTURE 7 CLAIMS RELATED TO SUB-CONTRACTORS
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
NORDRESS Consortium Agreement highlights. All participating institutions have signed the CA This presentation gives a brief overview of the main items.
Charging and financial assessment Care Act Outline of content  Introduction Introduction  Conducting the financial assessment Conducting the financial.
Time for a new standard - AS General Conditions of Contract
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT Defects Liability [Construction Contract Administration] Chapter 11.
LOGO October The Employer FIDIC 1999 dasdas Supervisor: Dr.Kamalain shaath Done by: Mahmoud Abu Kmail Construction Contract Administration ENGC.
Insurance provisions under JCT 1998 and JCT Standard Building Contract 2005 Brian Lewis – QBE CAR.
A Review of Board of Health Liability James A. LeNoury LeNoury Law Counsel to alPHa February 5th, 2015.
CONTROLLING TIME. ”Remember that time is money” Benjamin Franklin 1748.
Compensation events and claims Presented by Prof. Khem Dallakoti.
1. Introduction Time is of essence in basically every construction project Yet, delays of some sort are general rule, rather than the exception Consequence:
General Condition THE EMPLOYER Construction Law Supervised By : Dr. Kamalain Shaath Prepared By : Eng. Fawzy El.farra.
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
Threshold Concepts in Construction Law: Prevention & Extension in Construction Contracts Brodie McAdam University of Salford
FORMULATION & PRESENTATION OF EOT CLAIMS
Mitigating Circumstances 2015/2016 Leicester Medical School.
7 Plant, Materials and Workmanship. 7.1Manner of Execution The Contractor shall carry out the manufacture of Plant, the production and manufacture of.
Conditions Of Contract For Construction Conditions Of Contract For Construction Presented BY : Arch. INA’AM J. El TAWIL FIDIC 1999Conditions of Contract.
April 19, 2001L&L/MDI1 Impact of Force Majeure On Contracts Presentation by Mohit Saraf Partner Luthra & Luthra Law Offices.
Chapter 38 Agency Twomey, Business Law and the Regulatory Environment (14th Ed.)
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
By Khalil T. Hasan Construction Solutions ( Joint Operation/Administration of multiple FIDIC Forms – A Case Study.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
LEB Slide Set 3 Sale of Goods: National and International Legal Provisions Definition of Conforming Goods Legal Remedies for Defective Goods Matti Rudanko.
TOPICS – THIS SESSION Domestic Enquiry Principles of Natural Justice
Code of Ethics and Ethics Panel
Mitigating Circumstances 2016/2017
What are HR policies and procedures?
International Contracts Slide Set 5
SDAB HEARINGS ROLE OF THE DEVELOPMENT OFFICER
Profession Practices (ECIV-5105)
Administration of a FIDIC Contract - Project Control
Administration of a FIDIC Contract - Commencement Date to + 28 Days -
Auditing & Investigations II
Particular Conditions of Contract & Appendix to Tender
Performance of Contract
Overview: VAT and exportation
Termination of an employment relationship
AGENCY FORMATION AND TERMINATION
Particular Conditions of Contract & Appendix to Tender
ENGINEERING MANAGEMENT (GE 404)
INTRODUCTION TO Compliance audit METHODOLGY and CAM
Renting Homes (Wales) Act 2016
SSA Adverse Decisions and Administrative Finality
ПОСИЛЕННЯ ПОТЕНЦІАЛУ ІНСТИТУЦІЇ УКРАЇНСЬКОГО ОМБУДСМЕНА:
Certificates JCT 11 SBC allows for 10 different kinds of certificates.
بسم الله الرحمن الرحيم Tests on Completion Dr. Kamaleen Sha’ath
THE EMPLOYER Right, of access to the site.
Function of the International Court of Justice (ICJ):
TECHNICAL REPORT.
Compliance of Voluntary Organisations
Dennis Li - HKCIC Lecturer
STRUCTURE OF THE PRESENTATION
Public works contract Clauses 10.5 & 11.5 Explored
Wrongful Dismissal.
Unique General Conditions of the Alabama Building Commission (ABC)
A Review of Board of Health Liability
EMPLOYER’S RIGHTS – COMMON LAW AND CONTRACTUAL DETERMINATION PROCEDURE
Construction Contract Administration
Compliance of Voluntary Organisations
TABLE OF CONTENT Introduction
Presentation transcript:

Extension of time and how it is granted to a contractor (Referencing JCT 2005) (GROUP 5) Extension of time and how it is granted to a contractor (Referencing JCT 2005) (GROUP 5) CONSTRUCTION CONTRACT ADMINISTRATION (QTS 411)

GROUP MEMBERS ISHOLA HALEEMAH SOLIHU 13/31QS014 MUHAMMAD ZULFAT O. 14/31QS062 OSADARE BENJAMIN DAMMY 14/31QS055 BADMUS BASHIR 13/31QS008

 Introduction  Aims and Objectives  Extension of time  Time and delay related provisions  Relevant Events  Assessment and Granting of Extension to contractor  Conclusion TABLE OF CONTENTS

INTRODUCTION  In a construction contract, both the employer and the contractor may contribute to causing delay and thus, the need for extension of the presumed date of completion.  There are also delays that are caused by events which neither party has control over e.g. force majeure and adverse weather.

AIMS AND OBJECTIVES Aims  The aim of this report is to explain the term ‘Extension of time in building contract’ with references to the provisions in the JCT  Explain how extension of time is assessed and granted to a contractor by a contract administrator on a building project.

The main objectives of this report is to; AIMS AND OBJECTIVES  Explain the term extension of time.  Highlight the factors leading to extension of time.  Examine Clauses in the Joint contract tribunal (JCT) 2005 dealing with time and delay related provisions and by that extension of time.  Examine how extension of time is granted to a contractor.

EXTENSION OF TIME (EOT) WHAT IS EXTENSION OF TIME?  A simple definition; Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor’s fault.  However, there are more to extension of completion time; the causal agents for extension needs to be explained with the provisions in the JCT, also the procedure for securing an extension and more detailed explanations are given as we proceed.

TIME AND DELAY RELATED PROVISIONS (JCT 2005) The parties’ obligations relating to provisions on time and delay in the current JCT contracts have been structured well and are extensive. The provisions include clauses on; 1. POSSESSION OF SITE  Delay in allowing “possession of the site" as mentioned in clause 2.4 of the JCT 2005 may lead to;  A claim for extension of time by the contractor under the Relevant Events clauses, Unless stated in the contract otherwise.  Deferment of the provision of site possession is allowed up to six weeks under clause 2.5 of the current JCT contract.  The contractor may be entitle to an extension of time if the possession of site is defer by the employer.

TIME AND DELAY RELATED PROVISIONS (JCT 2005) 2. PROGRESS OF THE WORK  Upon receiving site possession, the contractor is obliged to proceed to conduct/deliver the work “regularly and diligently“, as regarding;  Compliance with all the authorities required under the contract and Statutory Requirement, the contractor is free to plan their own methods for executing the contract and completing their obligations on time.  Using their ‘best endeavours to prevent delays in the progress of works’.

TIME AND DELAY RELATED PROVISIONS (JCT 2005) 3. COMPLETION OF WORK  Under clause 2.4, the contractor is responsible to execute his work regularly and diligently and “...to complete the same on or before the relevant Completion Date";  Delay will be calculated starting from this point, in the event the contractor fails to complete the work by the completion date.  If the employer is found to have hindered the contractor from finishing the work before or on the completion date, the date of completion specified in the contract will be ineffective.  Thus, it could be said that; Completed works or ‘Practical Completion’ of a construction projects under JCT contracts is easier to be identified rather than defined.

TIME AND DELAY RELATED PROVISIONS (JCT 2005) 4. CONTRACTOR’S PROGRAMME  To enable the employer to monitor and anticipate the contractor’s plans for the completion of the project, An efficient programme will normally consist of;  The identification of the critical path.  The sequencing of activities and Identification of the critical activities.  The provisions require the contractor to submit a ‘master programme’ with the identified critical path and sequencing on the execution of the contract. NOTE: The programme is only considered as a measuring tool and does not form part of the contract document.

TIME AND DELAY RELATED PROVISIONS (JCT 2005) 5. NOTICE OF DELAY  Under clause 2.27 of the current contract the contractor is obliged to serve a notice of delay to the Architect or Contract Administrator on the event and about how “works or any section is being or likely to be delayed”  It requires the contractor to submit particulars on the expected impact of the events listed in the notice  what are the consequences if the contractor failed to issue such a notice?.  Architect should always consider whether an event may lead to delay and grant appropriate extension of time even though the contractor failed to submit a notice on the delay.

TIME AND DELAY RELATED PROVISIONS (JCT 2005) 6. ADJUSTMENT OF COMPLETION DATE  The current JCT 2005 allows the Contract Administrator to reduce the completion date earlier and also extend the date of completion fixed before.  It also provided the extension of time clause to preserve the rights of deducting liquidated damages in the case of an employer’s delaying event.  Under clause 2.29, there are lists (next slide) prescribing the ‘Relevant Events’ which will give the contractor entitlement to an extension of time, for example;  Clause to considers the delay caused by employers and neutral events which are not caused by either, still entitles the contractor to claim for an extension of the contract date of completion.

RELEVANT EVENTS AND DELAY  Relevant Events: is the terminology and provision used in JCT contracts 2005 to describe grounds to be considered by the contract administrator for an extension of time.  The ‘event’ must be the cause of the delay and affect the date of completion of the contract.  Delay might be;  Contractor caused.  Employer caused.  A neutral or relevant event.

EXAMPLES OF RELEVANT EVENTS  Variations  Deferment Of Site Possession  Suspension Of Work By The Contractor  All Inclusive Clause of; I mpediment, prevention or default  Civil Commotion

EXAMPLES OF RELEVANT EVENTS  Statutory Undertaker  Exceptionally Adverse Weather  Loss Or Damage By Any Of Specified Perils  Force Majeure

ASSESSMENT AND GRANTING OF TIME EXTENSION TO CONTRACTOR In practice it is probable that the contract administrator will base an extension of time decision on:  The latest agreed programme.  Information submitted by the contractor.  Awareness of progress to date.  Careful consideration of available facts at the time.

 Whilst the extension of time and loss and expense clauses are clearly related, it is not necessary the case that time and money claims are linked.  From a practical standpoint, granting an extension is likely to be a complex matter because, unless the project is a simple one, there is unlikely to be a single cause of delay, as there may be;  Concurrent delays and,  Some delay events may be more significant than others (i.e. a dominant cause of delay).  As a result the legal principle of mitigation (reasonable action to minimize the amount of loss suffered). ASSESSMENT AND GRANTING OF TIME EXTENSION TO CONTRACTOR

In summary ;  When it becomes reasonably apparent that there is a delay, or that there is likely to be a delay that could merit an extension of time, the contractor gives written notice (notice of delay) to the contract administrator identifying the relevant events that has caused the delay.  If the contract administrator accepts that the delay was caused by a relevant event, then an extension of time may be granted and the completion date adjusted. ASSESSMENT AND GRANTING OF TIME EXTENSION TO CONTRACTOR

CONCLUSION  According to the JCT 2005 ( Clause ),the contractor is entitled to an extension of time for relevant events where the contract completion date is likely to be delayed.  An important consideration with regard to both extensions of time and delay is the long standing legal principle of mitigation i.e. reasonable action to minimize the amount of loss suffered by the employer.  Contractor in non culpable delay cannot just sit back, rub his hands together and wait for the money to pour in from the employer. The contractor must employ a fair and reasonable means to reduce the impact of the circumstances in question 

THANK YOU FOR LISTENING… ANY QUESTION?