Answers to Reviewer Questions

Slides:



Advertisements
Similar presentations
CONDUCTORS + CAPACITORS
Advertisements

TPC Proposal for the 35 Ton Liquid Argon Test Abstract We propose to equip the 35 ton cryostat with one APA and two CPA’s, and all the necessary equipment.
1 Short update Itzhak Tserruya HBD meeting BNL, April 11, 2006.
Chapter 23 Gauss’ Law.
Background to the current problem 1. As a result of the high stresses in the bobbin due to the magnet load, the bobbin end plate needs to be increased.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM26 at Riverside California March 26, 2010.
Performance of the DZero Layer 0 Detector Marvin Johnson For the DZero Silicon Group.
VELO upgrade electronics – HYBRIDS Tony Smith University of Liverpool.
Lecture 4: Boundary Value Problems
CERN LBNE Test Experiment. Plan view of Bat
Chapter 24. Electric Potential
ZTF Cryostat Finite Element Analysis Andrew Lambert ZTF Technical Meeting 1.
Dec. 4, 2001 CERN-1 Hans de Vries VELO Mechanics  RF/vacuum foil  Rectangular bellow  Wake field suppressors  Cabling Summary & Outlook VELO mechanical.
FOOTINGS. FOOTINGS Introduction Footings are structural elements that transmit column or wall loads to the underlying soil below the structure. Footings.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
RADIATION SOURCE Design Review Dmitry Gudkov BE-BI-ML.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
FLARE Constructing the detector First FLARE Workshop November 4-6, 2004 Rafael Silva Fermilab / PPD / MD Fermilab Liquid Argon Experiments.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Structure Update Installation & Building Update Revisions Outlined Costs Revisited (since given to Gina) Jeff Nelson Fermilab.
CLAS12 Drift Chamber Prototyping
1 03/21/2006 GLAST CU Beam Test Workshop Scanning Table.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
Hall D infrastructure and integration Elton Smith Hall D Collaboration Meeting September 9-11, 2004.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
The integration of 420 m detectors into the LHC
Concept Design for LBNF Far detector (LAr single phase)
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
D. Peterson, for discussion of LC-TPC LP, interface of Endplate and Field cage, Discussion of the LP endplate and field cage geometry A version.
DUNE (SP) and SBND TPC Field Cage Designs Bo Yu Brookhaven National Lab.
CPA: Decisions, Issues, Next steps Francesco PIETROPAOLO CERN / INFN-Padova Field Cage CPA and Integration/Installation week, BNL, March 11th, 2016.
Single-Phase ProtoDUNE Construction Planning Jim Stewart LBNC January 11, 2016.
Single Phase ProtoDUNE TPC QA/QC Plans The SP TPC Team Jan. 13, 2016.
Value Engineering proposal: Putting APA’s on outside or put short drift cell on outside April 21, 2014, Post meeting rev. April 25, 2014 Russ Rucinski.
Grid Pix Field Simulations and precision needed for a module Peter Kluit, Jan Timmermans Prepared 16 May 2016.
FC: Decisions, Issues, Next steps Bo Yu BNL Field Cage CPA and Integration/Installation week, BNL, March 11th, 2016.
Recent Changes to the FD TPC Design Bo Yu Oct. 20, 2015.
Electrostatic FEA on Field Cage Profile Configurations Bo Yu.
Single Phase ProtoDUNE TPC CERN The SP TPC Team Jan. 13, 2016.
V. Raginel, D. Kleiven, D. Wollmann CERN TE-MPE 2HiRadMat Technical Board - 30 March 2016.
ProtoDUNE High Voltage Design
An extension of Ramo's theorem to include resistive elements
Telescope - Mechanical
T2K Upgrade First look at TPC constraints (WAGASCI)
Cold mass design, assembly plans and QA/QC at CERN
EIA approval process, Management plan and Monitoring
Ohm’s Law and Resistance. Resistivity.
Quality Control Chamber Production
Grid Pix Field Simulations and precision needed for a module
Development of a low material endplate for LP1 and ILD
Applied Electricity and Magnetism
First tests on the roll-formed field cage.
SiD Muon Yoke Structure - Deformation Studies -
Opening Executive Session M.C.
Design Review: DUNE Single Phase Cathode Plane Assembly, Field Cage and High Voltage CloseOut CERN 10/11/16.
5. Conductors and dielectrics
NP04 CPA/FC/HV Interfaces
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
TPC Field Cage Progress Report
Engineering materials lecture #12
Proton Source and LEBT Luigi Celona & Lorenzo Neri
TPC Support and Constraint TPC Support
Electrostatic Tray.
NEG-coated gun: Black R30 arc at 227kV, white R30 arc at 164 after refurbishing and second bake Carlos Wednesday, August 10, 2018.
PSS verification and validation
ANALYSIS OF THE HORN UNDER THERMAL SHOCK – FIRST RESULTS
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
Presentation transcript:

Answers to Reviewer Questions

The committee has pointed out several times the concern of unknown field in regions where insulators such as G10/FR4/FRP, that can charge up, are used in the vicinity of high field regions. Can you review and tell us the current knowledge and positive experiences from other experiments, detectors, lab tests? Will this issue be still tested in the 35ton test? Answered

Charge build up FEA with “zero perpendicular field” boundary condition on all surfaces of the I-beams except at top and bottom. This is the condition when surfaces have charged just enough to repel any further incoming charge. White contour lines: V Black contour lines: E High fields at corners. Charge-up rate depends on volume adjacent to surface. 3

Currents, time constants, and effect of bulk resistance Charging of two sides can be asymmetric if volume on one side is different from the other. E.g., for box beams holding field cages, roughly 20 pA/m2 on one side, 30 pA/m2 on the other. Approximate analytic calculation gives ~2 day time constant to charge one side only if no current on other side, ~2 wks for both sides to charge, for 1/4” thick material. A non-infinite bulk resistance would mitigate charging: internal E = J ρ. E < (30 pA/m2) (1016 ohm-m) = 3000 V/cm. Attempted to measure resistivity of 12” x 12” x 1/4” FRP plates at K-State at E = 4.7 kV/cm. Saw long, increasing time constants of hours then days, slow “self-recharge” after applied voltage zeroed or reversed. Done in air at room temp. Need test at full HV and E scale, in LAr. 3 kV pA 4

Similar wide insulating structure in MicroBooNE

Present plans for the 35ton test Present plans for the 35ton test. The committee would like to understand if the foreseen tests and setup can reply on time to the open issues and risks that have been identified in the presentations and discussions. Answered by QA/QC talk

Could you make a short summary of the test results of the effect of discharges in the resistive kapton laminated panels? What current do you expect in each plane? Answered by QA/QC talk

Have the project discussed alternative designs to the profile caps of the FC Al profiles? The committee believes these parts may pose a significant risk if they degrade.

UHMW PE is the material used in nearly all cryogenic HV feedthroughs. The caps are expected to shrink ~2% in LAr. This is accounted for in the opening of the caps. No significant stress is expected from the attachment of the caps to the profiles The caps are locked onto the profiles with two nylon rivets. The locking of the cap is tested in LN2 with ~ 14kg of pulling force (force gauge limit) Since the small higher field test was successful, we are fairly confident that we have a viable solution and have not discussed alternatives. But, other interesting configurations are available

Conductive Caps on the Profiles Caps (plugs) are 3mm thicker than the profiles. Max E: 29.5kV/cm CNC or casted metal plug screwed into the profile ends

Conductive Caps with PE Edge The exposed caps/plugs would allow direct arching across the caps to adjacent FC modules in a discharge. To achieve HV isolation, we can encase the caps in a polyethylene tube (with one side slotted). This tube should be locked on the CPA side, and allow shrink on the APA side. The tube length does not need to exceed 2m. With this scheme, the metal electrodes is safe during normal operation without the PE tube. The tube helps to maintain HV isolation. If the tube is damaged, only this gap can arc through, while the rest of the modules are still protected.

End wall to top/bottom arrangement

The mechanical properties of the proposed FC Aluminum profiles are well defined. Can you show the mechanical requirements (alignment, planarity, etc) when they are together in assembled panels, and when adjacent panels are joined together?  Is there a value of how possible deformations after assembly will affect the electric field?

2cm Gap between Modules CPA APA Field cage Ground plane Field lines along a symmetry plane splitting the gap Electrons drift out of field cage Projection of field lines originating from the CPA onto the CPA plane Active volume 5cm

2cm gap + 2cm offset CPA APA Field cage Ground plane Field lines along a symmetry plane splitting the gap Electrons drift out of field cage Projection of field lines originating from the CPA onto the CPA plane Active volume 5cm

6cm Gap at FC Corners 5cm Active volume Projection of field lines originating from the CPA onto the CPA plane End wall FC module Field lines along a diagonal plane splitting the gap and viewed in the beam direction Bottom FC module Ground Plane

FC profile off plane by 10mm 180kV differential between the displaced profile and the “ground plane” on top. This should be the worst case.

FC profile off plane by 10mm

FC profile shift on plane by 10mm

FC profile shift on plane by 10mm

Currently, the design of the HV feedthrough is mostly in hands of ETHZ Currently, the design of the HV feedthrough is mostly in hands of ETHZ. Does the Single-Phase team have a plan to move timely from the current design and validation phases to production? Our understanding is that we’ll receive one of the 3 identical HVFT constructed and tested from DP. We’ll work with the DP team to implement the spring loaded tip and validate it.

A safety factor of 3. 75 has been agreed A safety factor of 3.75 has been agreed. Minor changes to the design will be made to raise the factor of safety of all components below 3.75 in all loading scenarios.  Is it possible to get a table that summarizes and explains uncertainties on which the 3.75 safety factor will apply on top. Have all the components of the design, as known today, be included in the baseline calculations carried out till today? Has the worst case scenario been considered? All of the load carrying components have been examined and considered. During the analysis all of the worst case scenarios were considered (ie during installation; 200 lbs worker)

At which point in time will you include CERN HSE (Safety unit) to validate key aspects of the design and the described assembly and installation scenarios? Their input (to aspects such as co-activity, electrical risks, work on coffined spaces, etc) may have a severe impact on the procedures being worked out now. Example: It is planned that the construction and assembly of CPA modules, FC modules and installation in the detector will be performed according to a set of Work Planning and Control (WPC) documents. Who validates WPC?

CERN HSE has been involved since the beginning, we are in close contact with them and working with them to develop the installation procedures that will occur at CERN. Installation procedures are being developed based on the experience at Ash River and these will be reviewed and approved by HSE. The WPC for the construction/assembly of CPA/FC at institutions in the US will be approved by each institutions safety organization.

Can you show a full team organization chart Can you show a full team organization chart? Are responsibilities well defined for the different phases of the project? How will the project management guarantee that the knowledge acquired by the current team is available during production, assembly and integration? Succession planning? Answered by Vic’s talk

Is there already a safety matrix resulting of a global risk analysis and how this will for instance translate in the safety/monitoring interlock strategy for the different systems? What kind of revision/validation are you planning to perform on this global risk analysis? Do you have already a preliminary global risk assessment? Need clarification

Example of HA Form

Can you describe in more detail how is the mass cut from the HV cable into the HV feedthrough made? What’s the electrical stress in that specific region? Franco

Can you clarify the difference between results in Fig59 in Design Doc V25 and Fig50 of V20, where a factor of 20 in terms of displacement appears? How has this number been improved? The analysis was done months ago and the original figure was a mistake that has been corrected.

When will you be ready to review the beamplug When will you be ready to review the beamplug? This part as it is very innovative an critical, it needs careful revision. Is any test foreseen for validating the design? Would you consider making a full sized test at 1.3 times design voltage in a N2 atmosphere and with an appropriate beam? Tim

Entire part will be immersed in LAr and will have open ends Entire part will be immersed in LAr and will have open ends. Test will be at ~60 kV (30 kV per section). In‐beam high voltage test of full‐scale beam plug at ~150 kV. Beam plug interior at nitrogen gas environment, entire beam plug immersed in oil. Test will isolate performance of interior nitrogen volume of beam plug. High voltage test of full‐scale beam plug at nitrogen gas environment, entire beam plug immersed in LAr.

The assembly/installation procedure is not fully mature, have you considered the implications on schedule and cost if input from the trial assembly at ash river has an impact on parts that are already fabricated at that time?

The full assembly process will not start until ~August 2017. We believe that the majority of the issues and problems will be understood by the end of the December 15-16 workshop at Ash River and this would be resolved by the time we meet with the CERN HSE (Safety Team) early next year. We do not expect and major changes to the main parts (APA,CPA,FC) but there will be refinement of the installation tooling and interface connections (latches and connections) to allow safe access and minimize and danger to both the detector and personnel.

Have you studied and documented the implication on detector performance and physics if you are forced to operate at lower HV (space charge may increase and hence the field distortions…)? Glenn

While the design of the different parts seems sound, which is the foreseen validation process for the overall design?

Validation of the overall design is being done with the 3d solid model and a detailed beam FEA model of the entire detector