Proposal to Remove from Service the PV-COI RAS

Slides:



Advertisements
Similar presentations
Summary of Second Draft of the NERC Standard PRC Disturbance Monitoring and Reporting JSIS Meeting August 10, 2010 Salt Lake City, UT.
Advertisements

Spinning Reserve from Load Consideration of a Trial at Xcel Energys Cabin Creek Station Presentation to CMOPS January 7, 2005 John Kueck ORNL Brendan Kirby.
Operating Transfer Capability Policy Committee Report Board of Directors Meeting April 21 & 23, 2004 Thomas A. Delawder OTCPC Chair Western Electricity.
Jerry Rust Chair - Underfrequency Load Shedding Criterion Team
Western Electricity Coordinating Council 1 WECC MIC Meeting Report on Operating Transfer Capability Policy Committee (OTCPC) Marina Del Ray October 30.
Goshen Area Bus Reconfiguration
Public Service Company of New Mexico
Northwest Quadrant Joint Security Study Southern Company Headquarters Birmingham, Alabama August 12, 2002 Presented by Saeed Arabi.
Tucson Area Reliability Mike Flores Control Area Operations Tucson Electric Power May 2000.
Presentation to WECC TSS May 8, 2015
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
Visibility 10/1/ Agenda Visibility Overview Status –WECC –ColumbiaGrid Issues Preliminary Thoughts Regarding Conclusions and Recommendations Next.
Review of BPA Voltage Control Conference
Grizzly-Summer Lake 500 kV Line Planned Outage May 27-June hours Mike Viles – BPA Transmission Operations Technical Management Team June.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
Project WECC-0100 Update Reliability Subcommittee February 2014.
Steve Rueckert Director of Standards TPL Discussion – PCC Steering Committee March 25, 2014.
Lyndonville Electric Department Feasibility Analysis Review December 2,
1 TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE April 17, 2007 New Mexico Transmission System Overview.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Steve Rueckert Director of Standards TPL Discussion – PCC Steering Committee March 25, 2014.
TRANSMISSION INFRASTRUCTURE IMPROVEMENTS — Current Projects — The Center for the New West “ The Sun Valley Energy Roundtables 2006” November 30 – December.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
ERCOT DYNAMICS WORKING GROUP Report to ROS August 16, 2007 Vance Beauregard, American Electric Power.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Path Definition (for studies) 
Conclusion: reliable post contingency capacitor switching should be feasible to be planned. However, the simulation needs to be repeated as new information.
Remedial Action Scheme Workshop RAS Workshop May 9, 2016.
TEP RMR Workshop Presentation1 Workshop on ACC RMR study submitted with 2004 ten year plan Tucson Electric Power January 15, 2004 Ed Beck Supervisor Transmission.
Project WECC-0100 Standards Briefing WECC-0100 SDT April 7, 2016 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
RASRS Report to Operating Committee March 21, 2017
Visibility Ramu Ramanathan 10/1/2007.
CSC DETERMINATION PROCESS
WECC Load Modeling and Validation Group Meeting
Kenneth Silver Los Angeles Department of Water & Power
Columbia Grid Wind Integration Study Team Dynamic Transfer Capability Studies Update 9/10/09.
Eleanor Ewry Base Case Coordination Subgroup Chair
Updates to the Path Rating Process for Approval by the PCC
Compliance Report to ERCOT TAC February 2007
Presented by: LADWP November 14, 2017
HARRY ALLEN TRANSFORMER REMEDIAL ACTION SCHEME (RAS)
I-5 Corridor Reinforcement Project
Project WECC-0100 Update Load Modeling Task Force
PRC-006-RFC-01 Automatic Under Frequency Load Shedding Requirements
DEC System Voltage Planning - June 2018
Protective Relaying Conference
Naughton RAS (Southwest Wyoming Generation Tripping Scheme) – LAPS
Out of Region Market Assumptions
CMPLDWG Composite Model with Distributed Generation Approval
Yale Runback Local Area Protection Scheme
MODELING DG IN BASE CASES
HARRY ALLEN TRANSFORMER REMEDIAL ACTION SCHEME (RAS)
MODELING DG IN BASE CASES
Naughton RAS (Southwest Wyoming Generation Tripping Scheme) – LAPS
CMPLDWG Composite Model with Distributed Generation Approval
Project WECC-0100 Update Reliability Subcommittee
WECC Load Modeling and Validation Group Meeting
WECC Joint Synchronized Information Subcommittee
User Experience with New Solar PV Models California ISO
Palo Verde-COI RAS Retirement
Project WECC-0100 Update Load Modeling Task Force
Proposal to Remove from Service the PV-COI RAS
Palo Verde-COI RAS Retirement
Planning Meeting November 4, 2010 Marv Landauer.
Presentation transcript:

Proposal to Remove from Service the PV-COI RAS Justin Lee August 2, 2017

Agenda Purpose Historical Background Summary of Study Results Recommendation 08/02/2017

Purpose Obtain RASRS approval to remove from service the PV-COI RAS 08/02/2017

Historical Background Planned upgrades of the three Palo Verde (PV) Units Winter / Summer PV Unit #2 – November 2003 (121MW / 92MW) PV Unit #1 – November 2005 (121MW / 92MW) PV Unit #3 – November 2007 (121MW / 92MW) 08/02/2017

Historical Background Technical Studies showed impact on California Oregon Inter-Tie (COI) Pre PV unit upgrades showed minimum of 134MVAR margin on COI system busses Post PV unit upgrades study case diverged, indicated zero MVAR margin on COI system busses Direct Load Tripping of 150MW in Phoenix Area restored MVAR margin to 139MVAR 08/02/2017

08/02/2017

0MW 200MVAR 400MW 0MVAR 1000MW 200MVAR 08/02/2017

08/02/2017

Historical Background A Direct Load Trip (DLT) scheme was designed and implemented Scheme arms when output of any two units at Palo Verde exceeds 2550MW Scheme operates if two Palo Verde units trip within five minutes 150MW of load armed, 120MW to trip DLT scheme placed in service in 2004 08/02/2017

Historical Background The Transmission System has Changed Since the PV-COI RAS was Installed Series capacitors installed on John Day – Grizzly #1 and #2 500kV lines 308MVAR Shunt capacitor installed at the Slatt 500KV bus 08/02/2017

Historical Background To be compliant with PRC-012 through 014- WECC-CRT-2 WR10, SRP began a project to assess the operation, coordination, and effectiveness of the PV-COI RAS A third party consultant was hired to perform the technical analysis 08/02/2017

Summary of Study Results The study results show that with the COI stressed to it limit and without the PV-COI RAS in service The system continues to meet all power flow, voltage, stability, and transient stability criteria There is a minimum of 472MVAR of Margin on the COI system busses, well above the 134MVAR of margin that the RAS was designed to maintain 08/02/2017

Recommendation Based on the study results, SRP recommends that the PV-COI RAS be removed from service by December 31, 2017 and decommissioned at a later date. 08/02/2017