Team Members: Kyle Jones Mark Magee Jason Rippee

Slides:



Advertisements
Similar presentations
Want to be a Path Operator?. No true definition of Path Operator in Reliability requirements, responsible entities listed are RC, TOP, TO, BA, GO, GOP,
Advertisements

Industry Brainstorm on increasing Export Capacity From Alberta to B.C. January, 2006.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Goshen Area Bus Reconfiguration
Reliability Software1 Reliability Software Minimum requirements & Best practices Frank Macedo - FERC Technical Conference July 14, 2004.
NTTG Economic Study and Biennial Study Update NTTG Economic Study and Biennial Study Update NTTG Study Cycle.
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
Real-Time Transmission Congestion Management & Market Effects
Available Transfer Capability Determination Chen-Ching Liu and Guang Li University of Washington Third NSF Workshop on US-Africa Research and Education.
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
AUGUST 19, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
Team BUSS Backup Storage Source. Team BUSS Idaho Power Company Backup Storage Source Project Title Extra High Voltage (EHV) Station Second DC Storage.
Borah Mitigators Remedial Action Scheme for the Borah West Path Sponsored by: IDAHO POWER Team Members: Kyle Jones Mark Magee Jason Rippee.
1 Voltage Collapse Animation (AC) Created by Peter W. Sauer Department of Electrical and Computer Engineering University of Illinois at Urbana-Champaign.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
1 Local Area Planning Update to TRANSAC – September 18, 2014.
FRCC Seasonal Transmission Assessment & Operational Seasonal Study Winter 2012.
2013 Alternative Transmission Development Robert H. Easton March 17, 2004 RMATS Stakeholder Meeting.
System Operations Staffing Request Presented to the ERCOT Board Of Directors By Sam Jones, COO November 16, 2004.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
Dynamic Thermal Ratings for Overhead Lines Philip Taylor, Irina Makhkamova, Andrea Michiorri Energy Group, School of Engineering Durham University.
ATC/TTC Basics Transmission Customer Forum Doug McLaughlin 9/22/06 Transmission Customer Forum Doug McLaughlin 9/22/06.
March 11, 2011 RPG Meeting Lower Rio Grande Valley (LRGV) Import.
Superconducting Fault Current Limiters
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
A new Nomogram Development POM- based tool - Application results in the Idaho Power System. Orlando Ciniglio, IPC Marianna Vaiman, V&R Energy WECC TSS.
ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Hao Zhu Special thanks to Dr. Kai Van Horn Dept. of Electrical and Computer Engineering.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
ERCOT – LP&L Study Status Update For Regional Planning Group Ben Richardson March 22, 2016.
Project WECC-0100 Standards Briefing WECC-0100 SDT April 7, 2016 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Announcements Please read Chapter 3
CSC DETERMINATION PROCESS
Barrilla Junction Area Transmission Improvements Project
Local Area Planning Update to TRANSAC – September 15, 2016
Borah Mitigators Problem Definition: Sponsor: Idaho Power
Columbia Grid Wind Integration Study Team Dynamic Transfer Capability Studies Update 9/10/09.
Energy and Ancillary Services Design Stream Working Group Meeting 6
Updates to the Path Rating Process for Approval by the PCC
ECEN 460 Power System Operation and Control
Presented by: LADWP November 14, 2017
HARRY ALLEN TRANSFORMER REMEDIAL ACTION SCHEME (RAS)
IPS-SLR™ Static Line Rating Module and ElectraNet Use Case IPS-ENERGY™
Series Capacitor Compensation
Project WECC-0100 Update Load Modeling Task Force
ELECTRICAL INSTALLATION AND MAINTENANCE (EIM) 5 INSTALL ELECTRICAL PROTECTIVE DEVICES FOR DISTRIBUTION, POWER, LIGHTING, AUXILIARY, LIGHTNING PROTECTION.
Local Area Planning Update – TRANSAC
DEC System Voltage Planning - June 2018
Protective Relaying Conference
Overhead Conductors.
Naughton RAS (Southwest Wyoming Generation Tripping Scheme) – LAPS
Local Area Planning Update to TRANSAC – September 26, 2018
TVA RC 2017 Summer Outlook TVA RC July 27, 2017.
ECEN 460 Power System Operation and Control
HARRY ALLEN TRANSFORMER REMEDIAL ACTION SCHEME (RAS)
Naughton RAS (Southwest Wyoming Generation Tripping Scheme) – LAPS
TONBRIDGE POWER GREEN LINE
Palo Verde-COI RAS Retirement
Project WECC-0100 Update Load Modeling Task Force
Palo Verde-COI RAS Retirement
Module T1 Transmission Power Point Slide Set b.
Power system operation and control
ColumbiaGrid Planning Update to PCC Marv Landauer October 7, 2014
ECE 476 POWER SYSTEM ANALYSIS
Presentation transcript:

Team Members: Kyle Jones Mark Magee Jason Rippee Borah Mitigators Remedial Action Scheme for the Borah West Path Sponsored by: IDAHO POWER Team Members: Kyle Jones Mark Magee Jason Rippee

Project Background Idaho Power wants to add to a remedial action scheme for the Borah West Path To include the impact of ambient temperature changes to the system Maximize the power flow utilizing thermal capability

Deliverables Simulation of the modified scheme in PowerWorld 11 Provide a set of mitigation options to increase transfer capability

Needs Analysis Due to the growth of Boise, the load flow is increasing along the path The Borah West Path has elements that reach their thermal limit following the loss of critical transmission lines Compensating for thermal effects will increase the load carrying capacity in lines

Cost Analysis Investments/Costs Hours Total Dollars per Week Weeks per Hour Item Cost Student Time 15 26 390 $50.00 $19,500.00 Faculty Time 2 52 $150.00 $7,800.00 Laboratory Facility 10 4 40 $25.00 $1,000.00 PowerWorld Simulator $12,000.00 IEEE 738-1993 $143.35 Poster Board $14.69 Poster Photo   $45.00 Projected Total Cost: $40,503.04

Insights to the Problem The first slide demonstrates the current limit conditions The second slide gives a flow chart of what remedial action is to be taken The third slide is a graphical depiction of the flow chart

Midpoint East flow, MW (pre-disturbance) Calculated Borah West limits Midpoint East flow, MW (pre-disturbance) ( Summer time - 2005) W/ 1 unit trip = A = 1929 - 6.64*degC + 0.45 * 1st unit MW where Ta = actual ambient temperature in deg C 1st Bridger Unit to trip (MW) W/ 1 unit trip &bypass both series caps = Ac = 1293 -3.93*degC + 0.2384 * 1st unit MW + 0.484 * Midpoint East flow (MW) 2nd Bridger Unit to trip (MW) W/ 1 unit trip &bypass 1 series cap = AC/2 = A + (Ac-A)/2 W/ 2 unit trips = B =1929 – 6.64*degC +0.45 * (1st + 2nd unit MW) W/ 2 unit trip & bypass both series caps = Bc = 1293 – 3.93*degC + 0.2384 * (1st + 2nd unit MW) +0.484*Midpoint East flow (MW) W/ 2 unit trip &bypass 1 series cap = BC/2 = B + (Bc-B)/2

Is Midpoint East scheme will trip 1 Bridger Unit Bypass Burns Series Capacitor Critical Outage has occurred: Kinport – Midpoint and Borah – Adelaide – Midpoint #1 or #2 345kV lines Is AC/ 2 > A ? Is BW > ~1100MW Is BW > A yes yes yes no no no Is BW > A yes No action taken X33 No action taken No action taken no No action taken Trip 2nd Unit @ Bridger Bypass Midpoint Series Capacitor Initiate Bridger Redispatch or / and load curtailment to eliminate overloads on remaining Borah – Adelaide – Midpoint 345kV line and AMFLS – Adelaide and AMFLS – Plst Valley 138kV lines X33 Is BW > AC/ 2 Is BW > AC Is BW > BC yes yes yes no no no No action taken No action taken No action taken

Constraints Keep voltage deviation after one line loss below 5% of nominal operating voltage, and below 10% for a two line loss. Under normal conditions conductor temperatures should not exceed 80 degrees Celsius. Outage conditions should not exceed 90 degrees Celsius for more than 15 minutes.

Constraints 2 In order of importance: 1) Avoid tripping Generators at all costs! ( lots of money) 2) Avoid dropping loads. 3) Avoid shorting series capacitors (not that big of deal). Utilize thermal capabilities if possible.

Schedule

Fall Schedule

Project Learning IEEE standard publication 738-1993 PowerWorld Manual ETAP Software Series Capacitors Load Shedding Generator Dropping

اIا2*Rac+qs=qc+qr اIا, is the magnitude of maximum current (ampacity) Rac, is the ac resistance of the conductor qs, is the head absorbed by the sun qr, is the radiated heat of the conductor qc, is the convected heat of the conductor

Questions?

Our Questions Are violations outside of Idaho our concern? What are the required deliverables and what are optional? For thermal modeling do we use limit groups or can we scale all ampacities by a factor? How do we approach weather conditions? Do you want to increase transfer levels from the base case? Do we need the ATC PowerWorld add-on?

Limit Group Factors