TM 661 Chapter 5 Solutions 1 5.4) Consider the net cash flows and salvage values for each of alternatives 1 and 2 having lives 3 and 5 years respectively.

Slides:



Advertisements
Similar presentations
Capacity Planning. How much long-range capacity is needed When more capacity is needed Where facilities should be located (location) How facilities should.
Advertisements

Contemporary Engineering Economics, 4 th edition, © 2007 Incremental Analysis Lecture No. 28 Chapter 7 Contemporary Engineering Economics Copyright © 2006.
Chapter 2 Solutions 1 TM 661Chapter 3 Solutions 1 5) If you desire a real return of 8% on your money, excluding inflation, and inflation is running 3%,
Evaluating Business and Engineering Assets Payback Period.
Capital Budgeting. The process of determining and selecting the most profitable long-term (>1 year) projects. Firm ’ s capital budgeting decisions define.
Capital Budgeting Net Present Value Rule Payback Period Rule
Chapter 9 Net Present Value and Other Investment Criteria
Copyright © 2011 Pearson Prentice Hall. All rights reserved. Chapter 7 Fundamentals of Capital Budgeting.
1 Dr. Lotfi K.GAAFAR Eng. Ahmed Salah RIFKY ENGR 345 Engineering Economy.
TM 661 Engineering Economics for Managers
InvestmentWorth Investment Worth. Given a minimum attractive rate-of-return, be able to evaluate the investment worth of a project using Net Present Worth.
Multiple Investment Alternatives Sensitivity Analysis.
8/25/04 Valerie Tardiff and Paul Jensen Operations Research Models and Methods Copyright All rights reserved Economic Decision Making Decisions.
Contemporary Engineering Economics, 4 th edition, © 2007 Methods of Describing Project Risk Lecture No. 46 Chapter 12 Contemporary Engineering Economics.
Sensitivity and Breakeven Analysis
(c) 2001 Contemporary Engineering Economics 1 Chapter 7 Present Worth Analysis Describing Project Cash Flows Initial Project Screening Method Present Worth.
Contemporary Engineering Economics, 4 th edition, © 2007 Comparing Mutually Exclusive Alternatives Lecture No.18 Chapter 5 Contemporary Engineering Economics.
Corporate Financial Management 3e Emery Finnerty Stowe
T9.1 Chapter Outline Chapter 9 Net Present Value and Other Investment Criteria Chapter Organization 9.1Net Present Value 9.2The Payback Rule 9.3The Average.
ENGM 661 Engineering Economics Replacement Analysis.
Rate of Return Analysis: Multiple Alternatives Consider the following: You have $20,000 to invest in either alternative A or alternative B. Your MARR is.
Chapter 7 Fundamentals of Capital Budgeting. 7-2 Chapter Outline 7.1 Forecasting Earnings 7.2 Determining Free Cash Flow and NPV 7.3 Analyzing the Project.
Comparing Projects Using Time Value of Money
Engineering Economics. John Ayers September 17, 2004.
Chapter 11 Project Analysis and Evaluation 11.1Evaluating NPV Estimates 11.2Scenario and Other “What-if” Analyses 11.3Break-Even Analysis 11.4Operating.
Present Worth Analysis Chapter 5 Types of Economic Alternatives Mutually Exclusive Alternatives: –Only one of the viable projects can be selected. –The.
ENGINEERING ECONOMICS ISE460 SESSION 13 Annual Equivalent, June 17, 2015 Geza P. Bottlik Page 1 OUTLINE Questions? News? Annual Equivalent Examples.
Evaluating a Single Project
MIE Class #5 Manufacturing & Engineering Economics Concerns and Questions Concerns and Questions Quick Recap of Previous ClassQuick Recap of Previous.
Sensitivity and Breakeven Analysis Lecture No. 25 Chapter 10 Fundamentals of Engineering Economics Copyright © 2008.
L29: Sensitivity and Breakeven Analysis ECON 320 Engineering Economics Mahmut Ali GOKCE Industrial Systems Engineering Computer.
McGraw-Hill/Irwin © 2008 The McGraw-Hill Companies, Inc., All Rights Reserved. 1-1 McGraw-Hill/Irwin © 2008 The McGraw-Hill Companies, Inc., All Rights.
InvestmentWorth Investment Worth. Investment Worth MARR Suppose a company can earn 12% / annum in U. S. Treasury bills No way would they ever invest in.
7-1 Copyright  2007 McGraw-Hill Australia Pty Ltd PPTs t/a Fundamentals of Corporate Finance 4e, by Ross, Thompson, Christensen, Westerfield & Jordan.
TM 661 M2 - Probs II. Consider a simple five year investment project with discrete end-of-year cash flows shown below. Revenue at the end of year one.
TM 661 Chapter 6 Solutions 1 The manager of a canned-food processing plant is trying to decide between two labeling machines. Their respective costs.
Project cash flow n A B Example 1: Consider the following two mutually exclusive investment projects. Assume.
1 1. Order alternatives from lowest to highest initial investment. 2. Let Alternative A 0 (do nothing) be considered the current best. 3. Consider next.
TM 661 Engineering Economics for Managers Break Even & Sensitivity.
EGR Break-Even Analysis Break-even Analysis – performed to determine the value of a variable that makes two elements equal. In economic terms:
Prepared by Ingrid McLeod-Dick Schulich School of Business © 2015 McGraw–Hill Ryerson Limited All Rights Reserved Net Present Value and Capital Budgeting.
Construction Accounting & Financial Management, 3/e Steven Peterson © 2013 by Pearson Higher Education, Inc Upper Saddle River, New Jersey All Rights.
EXCERCISES ON BES. Compute the Break-even sales in pesos and units 1.A product line is sold at a unit selling price of P9.00. Variable cost is estimated.
IENG 217 Cost Estimating for Engineers Break Even & Sensitivity.
Lecture No.18 Chapter 5 Contemporary Engineering Economics Copyright © 2010 Contemporary Engineering Economics, 5 th edition, © 2010.
ENGM 661 Engineering Economics for Managers InvestmentWorth Investment Worth.
EGR Break-Even Analysis Break-even Analysis – performed to determine the value of a variable that makes two elements equal. In economic terms:
Chapter 6 Annual Equivalent Worth Criterion. Chapter 6 Annual Equivalence Analysis  Annual equivalent criterion  Applying annual worth analysis  Mutually.
Dealing with Uncertainty Assessing a Project’s Worth under Uncertainty or Risk.
Accounting Rate of Return mefielding.com1. Definition  Accounting rate of return (also known as simple rate of return) is the ratio of estimated accounting.
Estimating Cash Flows and Refinements to Capital Budgeting 11 CHAPTER Copyright © 1999 Addison Wesley Longman.
Cash Flow Estimation Byers.
Investment Decision Criteria
Part 1 : Understanding Money And Its Management (Ch1,2,3,4) Part 2: Evaluating Business and Engineering Assets (5,6,7)
Applying Annual Worth Analysis
Chapter 8 Fundamentals of Capital Budgeting
Chapter 12 - Capital Budgeting
Key Concepts and Skills
Comparing Mutually Exclusive Alternatives
Developing Capacity Alternatives
Chapter 7 Present Worth Analysis
Cash Flow Estimation Byers.
RATE OF RETURN ANALYSIS CHAPTER 7
Credit and Inventory Management
PLANNING FOR CAPITAL INVESTMENTS
PRESENT WORTH ANALYSIS Chapter 5
Chapter 11: Breakeven and Sensitivity Analysis
OUTLINE Questions? News? New homework due Wednesday
OUTLINE Questions? News? New homework due Wednesday
Presentation transcript:

TM 661 Chapter 5 Solutions 1 5.4) Consider the net cash flows and salvage values for each of alternatives 1 and 2 having lives 3 and 5 years respectively. Soln: Chapter 5 1

TM 661 Chapter 5 Solutions 2 5-10) A firm has available 4 proposals A, B, C, D. Proposal is contingent on acceptance of either proposal C or proposal D. In addition, proposal C is contingent on proposal D, while proposal D s contingent on either proposal A or proposal B. The firm has a budget limitation of $500,000. The cash flows are as follows: Initial Costs A = 250,000 B = 350,000 C = 50,000 D = 38,000 Soln: Note we did not need to include the entire cash flow since only the initial costs affect the initial budget of $500,000. Alternative Acceptable Reason A, B, C, D no exceeds budget A, B, C no exceeds budget A, B, D no exceeds budget A, C, D yes A, C no C contingent on D A, B no exceeds budget A, D yes B, C, D yes B, C no C is contingent on D B, D yes C, D no D is contingent on A or B A no A is contingent on C or D B yes C no C is contingent on D D no D is contingent on A or B Chapter 5 2

TM 661 Chapter 5 Solutions 3 5-23) Two mutually exclusive proposals, each with a life of 5 years, are under consideration. MARR is 12%. Each proposal has the following cash flow profile. Soln: a. Net Present Worth A NPW = -30,000 + 9,300 (P/A, 12, 5) = -30,000 + 9,300 (3.6048) = $ 3,525 B NPW = -42,000 + 12,625 (3.6048) = $3,511 Choose A b. Incremental Method NPW = -12,000 + 3,325(3.6048) = -14 Chapter 5 3

TM 661 Chapter 5 Solutions 3 5-23) (Cont) Soln: c. Equivalent Annual Worth A EUAW = -30,000 (A/P, 12, 5) + 9,300 = -30,000 (0.2774) + 9,300 = $ 978 B EUAW = -42,000 (0.2774) + 12,625 = $ 974 Choose A Chapter 5 4

TM 661 Chapter 5 Solutions 5 5-36) An aluminum extrusion plant manufactures a particular product at a variable cost of $0.04 per unit, including material costs. The fixed costs associated with manufacturing the product equal $30,000 per year. Determine the break-even value for annual sales if the selling price per unit is a) $0.40, b) $0.30, and c) $0.20. Soln: Let S = selling price Profit = SX - 30,000 - .04X = (S - .04)X -30,000 Since profit = 0 at breakeven X = 30,000 / (S - .04) a. X = 30,000 / (.4 - .04) = 83,333 b. X = 30,000 / (.3 - .04) = 115,384 c. X = 30,000 / (.2 - .04) = 187,500 Chapter 5 5

TM 661 Chapter 5 Solutions 6 5-37) Owners of a nationwide motel chain are considering locating a new motel in Snyder, Arkansas. The complete cost of building a 150-unit motel is $5 million. The firm estimates that the furnishings will cost $1,875,000 initially and every 5 years thereafter. Annual operating and maintenance cost for the facility is estimated to be $125,000. The average rate for a unit is anticipated to be $55 per day. A 15 year planning horizon is used by the firm in evaluating new ventures of this type. Salvage value is estimated at $1 million. Determine the breakeven if the daily occupancy is estimated to be 10%. Soln: I set up a spreadsheet showing revenues and costs. Revenues were based on an occupancy rate in cell C3. Net present worth is computed at 10%. I then just altered cell C3 until I got a NPV relatively close to 0. I compute an occupancy rate of 37.5%. Chapter 5 6