CUSC Panel – 19th July 2016 Binoy dharsi

Slides:



Advertisements
Similar presentations
July 2003 Structure of Electricity Distribution Charges Update and Proposals Martin Crouch Director, Distribution.
Advertisements

Review of NTS entry charge setting arrangements - IA 1 July 2010.
Mod Publication of UK Wholesale Gas Market Liquidity Data Richard Fairholme E.ON UK Transmission Workstream, August 7 th 2008.
Operating Margins. 2 Competitive Provision of Operating Margins Change to National Grid Gas’s Transporter Licence which:  Introduced Special Condition.
Incentive Based Regulation for SO Costs Andrew Mcintosh European Policy Manager Florence School of Regulation Workshop Improving and Extending Incentive-based.
Green Energy Program Redesign Wilson Mallard – Georgia Power Company NARUC Staff Subcommittee on Accounting and Finance Fall Meeting October 13, 2008 Wilson.
1 CODE MODIFICATION PROPOSAL No 0243 Amendments to the process for initialisation of Enduring NTS Exit (Flat) Capacity at the Moffat NTS Exit Point Presentation.
SO Incentives from April 2010 John Perkins. 2 Gas System Operator (SO) Incentives National Grid operates the high pressure Gas Transmission System in.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Code Governance Review UNC Modification Proposals Chris Shanley - National Grid NTS.
1 EHV DG Charging Nigel Turvey. 2 Background Our current EHV charging methodology was not vetoed on 18 th February 2010 with the following treatment of.
Revision of the UNC Post-Emergency Arrangements draft proposal July 2009.
Mod 0333: Update of default System Marginal Prices Review Group August 2010 Transmission Workstream 07/10/2010.
Modification Proposal 0246: Quarterly NTS Entry Capacity User Commitment Chris Shanley.
Delivering Connections and Capacity RIIO-T1 and associated commercial changes - Summary June 7th 2012.
Gas Emergency Arrangements Proposal Transmission Workstream 5 th April 2007.
Governance and Charging Methodology for User Pays Services 10 th January 2007.
NARUC SUMMER COMMITTEE MEETINGS Committee on Water Agenda California Regulatory Initiatives Case History – California American Water B. Kent Turner – President.
Force Majeure - Capacity Transmission Workstream 2 July 2009.
Modification proposal 0073 ‘Revision to the Notice Period regarding the implementation of changes to Transportation charges’ Transmission Workstream, 2.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Customer Charge On behalf of all DNs 25 October 2010.
Gas Distribution Transportation Charging What are the Risks to Pricing predictability? Stephen Marland Pricing Manager
Emergency Cashout Prices and Emergency Curtailment Quantity (ECQ) Adjustment Ritchard Hewitt Gas Code Development Manager.
INVESTMENT COMMITTEE REVIEW: HBO Latin America Divestiture Opportunity January 22, 2010 [DRAFT]
Managing the Costs of New Developments Initial Proposals on Transmission System Operator Internal Costs from 1 st April 2007 Update from National Grid.
Energy Market Issues for Biomethane Projects Workshop - 31 October 2011 RIIO-GD1 Environmental Incentives.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Proposal to modify Standard Special Conditions A4, A5 and D11 of the Gas Transporter licence Distribution Charging Methodology Forum (DCMF) 13 August 2007.
DNPC05 Consultation Paper Balance of Revenue Recovery between LDZ System Charges and Customer Charges Steve Armstrong 27 th July 2009.
DN Interruption Reform Transmission Workstream Mark Freeman 5 th April 2007.
Www2.nationalgrid.com/bsuos An Introduction to Balancing Services Use of System Charging (BSUOS)
Stuart Forrest, Network Planning Manager, Scotia Gas Networks 19 th October 2010 MOD Review of Industry Charging & Contractual Arrangements in Relation.
Interim Fuel Factor Adjustment and Surcharge for Under-Recoveries
California Product Offerings
7 December 2006 Ritchard Hewitt
IFRS 4 Phase 2 Insurance Contract Model
Interactions with the implementation of RIIO-T1
Presentation to the BSC Panel
CMP277 ‘Special License Condition 4J’ CMP278 ‘BSIS 2017 Housekeeping’
Narragansett Electric Rate Classes
Presentation to the BSC Panel
Code Governance Review UNC Modification Proposals
An Introduction to Balancing Services Use of System Charging (BSUOS)
Holistic view of Charging Modifications – In flight 11th June 2018
CAP104 Amendment to System to Generator Inter-trip Related Terms concurrently defined in the Grid Code and the CUSC. Emma Carr 25th August 2005.
SO Incentives from April 2010
CAP190: Workgroup Report CUSC Modifications Panel, 26th August 2011
4th Quarter 2016 Earnings Call
Recovery of Costs due to Invalid Ex-Ante Contracted Quantities in Imbalance Settlement 12th December 2017.
Incentives 26 September 2018.
Part B Unsecured Bad Energy Debt and Unsecured Bad Capacity Debt
CSEPs Reconciliation Proposals
Exit Capacity Substitution and Revision
Consideration of issues raised by UNC Modification Proposal 0244
UNC Mod 392/ IGT Mod 040 Proposal to amend Annex A of the CSEP NExA table, by replacing the current version of the AQ table August 2011.
Joint Office Presentation for Modification 0678
Mod_38_18 Limitation of Capacity Market Difference Payments to Loss Adjusted Metered Quantity. 12th December 2018.
October 2, 2009 Dianne Feeney, HSCRC
Determining Marginal Energy Action Prices Modification Proposal
Transmission Workstream 2nd December 2010
Summary Issue Modification Aim Effect of the mod Impacts
Consideration of issues raised by UNC Modification Proposal 0244
Options for the Development of a Demand Side Response Mechanism
Modification 421 – Updates and Benefits Case
CMC_05_18 Combining Candidate Units into a Capacity Market Unit
Determining Marginal Energy Action Prices Modification Proposal
Recovery of Costs due to Invalid Ex-Ante Contracted Quantities in Imbalance Settlement 25th January 2018.
Modification Proposal 136
Capacity Market Code Modifications
Presentation transcript:

CUSC Panel – 19th July 2016 Binoy dharsi CMPxxx: Defer the recovery of BSUoS costs, after they have exceeded £30m, arising from any Income Adjusting Events raised in a given charging year, over the subsequent two charging years. CUSC Panel – 19th July 2016 Binoy dharsi

Background Under the Balancing Services Incentive Scheme (BSIS) National Grid is able to apply for the SO Incentives to be revised so as to allow them to recover costs which were beyond their reasonable control and were caused by an unforeseen event i.e. an Income Adjusting Event (IAE). Any additional cost incurred by the SO is recovered in the regulatory year in which the IAE was raised. Black Start contracts to a maximum value of £113m across chargeable volume of 521.9TWh (taken from March 2016 MBSS report for the 2015/16 period) would equate to an annualised cost of £0.22/MWh to industry participants.

Summary of Defect National Grid notified Ofgem of an IAE in relation to the 2016-2017 System Operator Incentive Scheme. Approval of the IAE would lead to the recovery of up to £113m, through 2016-2017 BSUoS charges. Historically, Black Start contracts have been a relatively small component of Balancing Services costs at £20-£40m/year for ~16-18 plants. The recovery of up to £113m for two plants is an unprecedented amount and if the IAE is approved, will have a significant commercial impact on market participants, and ultimately customers. We believe that the potential for such a material short notice impact on BSUoS charges to occur in these circumstances, represents a defect to the CUSC

Proposed CUSC Modification This proposal seeks to defer unforeseen increase in BSUoS costs arising from an IAE by two years. This proposal only applies to IAE’s which, in their total in any given charging year, have a combined effect on “raw BSUoS” of over £30m. We believe most market participants will be able to manage IAEs in a charging year with a combined effect on BSUoS of under £30m (i.e. the same amount as the floor on National Grid’s incentive scheme which reflects its maximum commercial exposure under the scheme) in the year it is incurred. This proposal enables market participants to spread out the unexpected cost over a two year period.

Justification against Applicable CUSC Objective (a) that compliance with the use of system charging methodology facilitates effective competition in the generation and supply of electricity and (so far as is consistent therewith) facilitates competition in the sale, distribution and purchase of electricity; This modification will mitigate the impacts of the unprecedented and unforeseen BSUoS charges on market participants. By allowing the costs to be known in advance and be recovered over a two year period, the proposal facilitates effective competition in the generation and supply of electricity, by removing the uncertainty that comes from short-notice, unforecastable, changes in BSUoS of materiality above this threshold. These short-notice, unforecastable, changes create risks that are hard for any participant to finance efficiently, adding to consumer costs; they may also have more adverse impacts on some categories of participant than others.   Since the modification will apply to future IAEs as well as the current potential IAE, it provides clarity going forward if a similar event occurs again. It provides the clarity that market participants need.

Justification against Applicable CUSC Objective Charging Objective (b) The proposer believes that the proposal is neutral against applicable charging objective (b).   Charging Objective (c) The proposer believes that the proposal is neutral against applicable charging objective (c). Charging Objective (d) The proposer believes that the proposal is neutral against applicable charging objective (d).

Justification for Urgent Status Historically, Black Start contracts have been a relatively small component of Balancing Services costs at £20-£40m/year for ~16-18 plants. £113m for two plants is an unprecedented amount and if the IAE is approved, will have a significant commercial impact on market participants, and ultimately customers who may experience higher risk premia as a result of the IAE. Currently BSUoS costs are just under £1bn so this additional cost represents a 10% increase in costs. However, as we are already mid-way through the year effectively if recovered within year this increase costs for parties by a factor of 20% Since Ofgem has to determine on the level of cost pass-through by 24 August 2016 (i.e. 3 months from the date of National Grid’s notification), we would like our CUSC modification to be considered as an Urgent modification. It is time sensitive to Ofgem’s determination of the IAE