MICE Absorber and Focus Coil Magnet – Test Results

Slides:



Advertisements
Similar presentations
Focus Coil Update Roy Preece / Tom Bradshaw / Mike Courthold STFC – RAL VC 17 th Jan 2013.
Advertisements

The Use of Small Coolers for Hydrogen and Helium Liquefaction
MICE hydrogen review Commissioning, testing and operations.
Russ Rucinski, PPD/MD/DZero Ops DZero Solenoid status November 29, 2004.
Magnet Cooldown Scheme 17 th February 2012 Roy Preece (STFC RAL)
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
SS and AFC Control Systems Brian Martlew 21 st Sept 2011.
AFC Schedules and Status Tom Bradshaw John Cobb Wing Lau Matt Hills MICE MICO Meeting 12 th October 2011 Elwyn Baynham Mike Courthold Victoria Bayliss.
AFC Status Tom Bradshaw John Cobb Wing Lau Matt Hills MICE MICO Meeting 11 th January 2012 Elwyn Baynham Mike Courthold Victoria Bayliss 1.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
Report from meeting Hydrogen system operation from cryocooler and level control Cryocoolers for MICE Tom Bradshaw Elwyn Baynham Yury Ivanyushenkov Rutherford.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #129 February 25, 2010.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
1 The Genoa Tracker Solenoids and their Contribution toward a New Design Michael A. Green Lawrence Berkeley National Laboratory and Pasquale Fabbricatore.
1 Superconducting Magnets for the MICE Channel Michael A. Green Oxford University Physics Department Oxford OX1-3RH, UK.
MICE collaboration meeting RAL 28 October 2004 Absorber R & D Plan by Wing Lau – Oxford University.
1 Technical Arguments in Favor of using the Cryomech PT-415 Cooler for Cooling the LH 2 Experiment Michael A. Green Lawrence Berkeley Laboratory Berkeley.
12 March 2006NFMCC Meeting, IIT, Chicago1 Progress on the MICE Cooling Channel and Tracker Magnets Michael A. Green Lawrence Berkeley Laboratory.
Hydrogen Delivery System – R&D Activities T W Bradshaw M Courthold M Hills J Rochford Daresbury Controls Group etc…
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #26 University of California.
Test plan for the MICE SS cryostat and magnet Tapio Niinikoski LBNL Spectrometer Solenoid Workshop May 10, 2011.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Spectrometer Solenoid Update Steve Gourlay Steve Virostek Lawrence Berkeley National Lab Steve Gourlay Steve Virostek Lawrence Berkeley National Lab MICE.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
MICE - UK Project Progress Roy Preece 30 th April 2013.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
Spectrometer Solenoid Fabrication & Testing Update S. Virostek and Mike Zisman Lawrence Berkeley National Lab NFMCC 2010 Collaboration Meeting University.
MICE CM32 8 th February 2012 Magnet Group Report Vicky Bayliss Victoria Blackmore John Cobb Mike Courthold Roy Preece Mike Zisman 1.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Spectrometer Solenoid Test Plan Workshop: Spectrometer Solenoid Overview Steve Virostek - LBNL February 17, 2012.
Instrumentation and Controls Test Plan Review 17 th February 2012 Roy Preece (STFC RAL)
HD target.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Spectrometer Solenoids MICO 214 Steve Virostek LBNL February 6, 2013.
Spectrometer Solenoids MICO 197 Steve Virostek LBNL August 15, 2012.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Spectrometer Solenoid Overview Roy Preece 31 st January 2011.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Spectrometer Solenoid Review A summary of P.Fabbricatore on behalf the review board Amalia Ballarino, Elwyn Baynham, Tom Bradshaw, Mike Courthold,
Spectrometer Solenoid Background Info Steve Virostek Lawrence Berkeley National Lab MICE Spectrometer Solenoid Review: Phone Meeting October 5, 2009.
FC Status MPB 1/20 April 2014 OXFORDRALDARESBURY V. BlackmoreV. BaylissT. Hartnett J. CobbT. BradshawS. Griffiths W. LauM. CourtholdI. Mullacrane R. PreeceA.
Cryogenic Summary - K. C. Wu Testing D2L102 in MAGCOOLJune, 02 Difference between D2L102 and D2L101 Operating Summary Cooldown to 100 K and 6 K Test Condition.
Magnet Issues 1/19 Nov 2013 MICE MAGNET ISSUES Brief update on –Coupling Coils (CC) –Spectrometer Solenoids (SS) Both are US responsibilities Details of.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
1 MICE Absorbers work package MPB – 17/04/15 RAL Tom Bradshaw Vicky Bayliss Mike Courthold Matt Hills Andy Nichols Roy Preece Mark Tucker Steve Watson.
FC Status CM39 1/20 June 2014 OXFORDRALDARESBURY V. BlackmoreV. BaylissT. Hartnett J. CobbT. BradshawS. Griffiths W. LauM. CourtholdI. Mullacrane R. PreeceA.
MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.
Progress on AFC Procurement T W Bradshaw Rutherford Appleton Laboratory Harwell Science and Innovation Campus Didcot, OX11 0QX, UK
MICE Spectrometer Solenoids Step IV running
S A Griffiths CM42 June 2015 Electrical & Control.
Refrigeration of Superconducting Solenoids T W Bradshaw Rutherford Appleton Laboratory Harwell Science and Innovation Campus Didcot, OX11 0QX, UK
Muon Ionization Cooling Experiment - MICE HEPTech - Grenoble 4-5 th June 2015 Tom Bradshaw STFC, Rutherford Appleton Laboratory.
E3 HVACR Controls and Devices
Spokesman's update.
Cryogenic behavior of the cryogenic system
E3 HVACR Controls and Devices
Spectrometer Solenoid Update
Project Manager’s Report + DC/MoM Report
Spectrometer Solenoid Fabrication Status and Schedule
Small Coolers for MICE MICE Collaboration Meeting RAL Michael A. Green
Focus Coil Quench Detector
Technical Summary - ANL
Cryogenic behavior of the magnet
Cryogenics – The Basics
Presentation transcript:

MICE Absorber and Focus Coil Magnet – Test Results MICE Project Board 9th May 2013 Oxford University and RAL Cryogenics Group Tom Bradshaw John Cobb Wing Lau Roy Preece Elwyn Baynham Mike Courthold Victoria Bayliss Victoria Blackmore Jason Tarrant Trevor Hartnett Steve Griffiths Ian Mullacrane Adrian Oates Chris White

Commissioning Programme Since the magnet was delivered and installed in R9 hall we have performed the following: System set-up and operation check Leak check magnet under vacuum and pressure Pre-cooling with LN2 to 80-90K Cool-down with Helium to 4K Steady state thermal performance check zero boil off Cryocooler excess performance check Step by step current ramp to full current (Solenoid mode) Thermal performance check Step by step current ramp to full current (Flip mode) Pre-cooling with liquid nitrogen and cooling down to 4K: This talk will go through the results of the powering tests, conclusions and the way ahead.

Instrumentation and control Operating points for the magnet in the various modes are as follows: Operating points Flip mode Solenoid mode 200 MeV/c 240 MeV/c Current 187.14 224.75 94.15 113.09 Current density NbTi 584.82 702.35 294.23 353.41 Current density coil 104.75 125.80 52.70 63.30 Bz max 3.090 3.711 2.598 3.121 Bpeak conductor 6.264 7.523 3.763 4.520

Run Summary Quench history is such that the training is taking longer than expected (or we would like) Remember that this acceptance is the responsibility of Tesla although the process necessarily involves RAL personnel Runs and results Solenoid mode # Current 17th January 2013 50.0 Deliberately induced quench 25th January 2013 1 95.0 Quench 29th January 2013 2 104.5 30th January 2013 3 114.0 Target achieved - no quench 31st January 2013 4 Target achieved and held for several hours Flip mode 12th February 2013 145.1 27th February 2013 152.1 28th February 2013 157.8 1st March 2013 159.7 7th March 2013 5 161.8 24th April 2013 6 170.6 2nd May 2013 7 178.4 8th May 2013 8 179.9 Quench (2nd coil?) A “run” occupies approximately two people from RAL for 2-3 days although we have previously had 3-4 people from DL in attendance to capture events.

Quench behaviour Bore of the cold mass Bottom of He Chamber Left at 30A overnight then started from that position the next day Stable temperatures right up to the event

Voltage taps Showing the location of the voltage taps and how they are wired into the QD system Thresholds are set at 600mV across the coils Ch3&4 and 20mV for the HTS and LTS leads

Cryocooler Cooling Power The cryocooler cooling power is decreasing and/or the heat load is increasing: .. Green – He chamber Purple – He bath pressure Red – Bath heater status 26% The red line is the bath heater that is activated when the pressure falls too low In recent times the heater has not been active A lot of this time the gas pack was attached and the cooler was condensing – this is not recorded Certainly the period leading up to the quench on the 24th April all valves were shut Bath pressure rises until the cryocooler cooling power matches the heat load

Cryocooler Cooling Power Checked that the pressures in the closed cycle refrigerators has not dropped: No issue with this – remains a puzzle

Temperatures post quench Not a huge indicator of where the problem lies but .. Temperatures at top of coil#1 hotter than #2 Temperature sensors 11&15 (top) off coil #1 and 12&16 (bottom) off coil#2 – HTS leads near the coils

Quench data Slight “bump” before quench Quench 7th March quench data Difficult to interpret the traces – after the “event” all sorts of things happen – we did get some sparking in the dump resistors which has now been fixed. Trace indicates that coil#1 is more resistive than coil 2

Quench data Quench is not too dramatic … Recovery from a run is difficult – best to leave on cryocoolers for a few days to bring temperature down then top up with Helium Otherwise – use a lot of helium.. Run cycle is probably 4-5 days Victoria Blackmore was quick enough to catch this….

AFC#2 OVC and Helium Turret AFC#2 is being completed and will be tested in R9 on delivery from Tesla. The experience from the testing of module #1 will be invaluable. AFC#2 should be finished June Radiation Shield

Summary Looks as though training on module #1 will continue but may take ~ 6 runs (~4 weeks?) If magnet is not training then we may want to take decision to switch horses and start work on module #2 Commissioning of module #2 may be delayed because of module #1

Summary and Conclusions Summary of where we are and what has been achieved: Test Result Summary System set-up and operational check Achieved Leak check magnet under vacuum and pressure Pre-cooling with LN2 to 80-90K Cool-down with Helium to 4K Achieved - actually filled on cryocoolers in first instance Steady state thermal performance check zero boil-off Achieved although some issues later… Cryocooler excess performance check Estimated to be 0.2W initially but seems to have degraded still checking this Step by step current ramp to full current (solenoid mode) Thermal performance check Cold mass slightly higher than expected by ~0.1K Step by step cuurent ramp to full current (flip mode) Getting there? Still work to do to understand this Note that there is little to say on Controls and monitoring – we had a few minor glitches but the DL group did very well….. Had issues with networking Level indicator not on board yet … There are some things that we don’t yet fully understand or need to do: Cryocooler cooling power and related pressure; Cryocooler sock insulation to reduce load (?); suspension system tension; Training behaviour

Schedule Module/Activity Due Date AFC1 at RAL Achieved Nov 2012 Absorber integration and test +5mths elapsed (Christmas Break) AFC2 at RAL June 2013 <3mths Negotiate on 3rd Module This FY The schedule is regularly reviewed but we don’t have a clear view because of the training required. Have to decide, based on training how to proceed when module #2 is available – do we jump horses ? CERN mapper won’t be back until August .. – would it be better to keep #1 cold ? Make our own checks …? Need to confirm planning with CERN over this.

END