Procurement of Nb 3 Sn strand, cable fabrication, and quality control for the U.S. Hi-Lumi LHC Accelerator Upgrade Project Lance Cooley, Fermilab L3 manager.

Slides:



Advertisements
Similar presentations
 Contracts  Subcontracting  Suppliers  Complaints  Corrective and preventive actions (CAPA)  Internal audits  Management reviews Management requirements.
Advertisements

LARP MSM Conductor, Cable and Procurement - A. Ghosh1 Strand, Cable and Procurement BNL -FNAL - LBNL - SLAC Magnet Systems Meeting Jan 09, 2014.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Spectrometer Solenoid Procurement Update Steve VirostekWing Lau Mike GreenStephanie Yang Lawrence Berkeley National LabOxford Physics MICE Collaboration.
Outline: Goals for the cable development at CERN. Main parameters of the cable. Cable development work for a cable width of 15.1 mm and for a cable width.
ISO 9000 Certification ISO 9001 and ISO
Oct , 2013, CDP D.R. Dietderich LARP Conductor & Cable Review 1 Conductor Development Program Support for LARP and HiLumi LARP- HiLumi Conductor.
Nb3Sn Cable and Insulation for LARP High-Gradient Quadrupole Magnets
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
From Research Prototype to Production
Collaboration Mtg, St Charles, IL 10/5-6, 2005 A. Ghosh1 Conductor R&D Plan Arup K. Ghosh BNL.
MQXF RRP® Strand for Q1/Q3 A. K. Ghosh MQXF Conductor Review November 5-6, 2014 CERN.
Status of MQXF Conductor LARP Update
AARD Sub-panel at Fermilab Feb , 2006 LARP Magnet R&D Program - S. Gourlay1 BNL -FNAL - LBNL - SLAC LARP Magnet R&D Program Steve Gourlay AARD Sub-Panel.
QXF Cable Status D.R. Dietderich Conductor Working Group Video Meeting, Sept. 17, 2014.
LQ status and plans – G. Ambrosio 1 LARP Collaboration Meeting - LBNL, April , 2006 BNL - FNAL - LBNL - SLAC OUTLINE: Goals, Input and Output Sub-tasks.
MQXF Cable for Q1/Q3 D.R. Dietderich MQXF Conductor Review November 5-6, 2014 CERN.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
F. Savary. Click here to add footer 2 Outline Context Constraints & Boundary conditions Project plan Production strategy A few words on QA Conclusions.
NCSX NCSX Design Review Guide May 27, 2005 Wayne Reiersen NCSX.
Title – xxxx 1 LARP & US-HiLumi Contribution to the Inner Triplet Quadrupoles G. Ambrosio Cost and Schedule Review CERN, March 9 th -11 th 2015.
Quality assurance of the QXF- Q2 Nb 3 Sn cable mass production C. Scheuerlein, 6 November 2014 HL-LHC/LARP International Review of the Superconducting.
Lab Coordination Meeting 3/21/13LHC IR Quadrupole Plan – G. Sabbi 1 LARP Magnet Systems Plan GianLuca Sabbi Lab Coordination Meeting March 21, 2013.
15 Th November 2006 CARE06 1 Nb 3 Sn conductor development in Europe for high field accelerator magnets L. Oberli Thierry Boutboul, Christian Scheuerlein,
Outline: Main characteristics of the FRESCA2 cable Main characteristics of the strand Strand stability, an issue to avoid magnet quench at low field Procurement.
LARP Meeting April 2006LARP Magnet Program – D.R. Dietderich LARP Cable R&D D.R. Dietderich LBNL.
MQXF Q1/Q3 Conductor Procurement A. K. Ghosh MQXF Conductor Review November 5-6, 2014 CERN.
D.R. Dietderich Frascati, Italy Nov , 2012 RRP-NbSn Conductor for the LHC Upgrade Magnets RRP-Nb 3 Sn Conductor for the LHC Upgrade Magnets A. K.
Conductor Review Oct 16-17, 2013LARP Strand :Specs. Procurement, Measurement- A. Ghosh1 LARP Strand: Specifications, Procurement and Measurement Plans.
Hi-Lumi Conductor Procurement A.Ballarino, B. Bordini, L. Oberli HL-LHC/LARP International Review of Superconducting Cable for the HL-LHC Inner Triplets.
E. Todesco OUTPUT OF THE CABLE REVIEW E. Todesco and the QXF team CERN, Geneva Switzerland CERN, 10 th December 2014 QXF design review, CERN.
LARP Meeting, Oct. 6, 2005 D.R. Dietderich, LBNL1 LARP Cable R&D FY05 & FY-06 Plans D.R. Dietderich, LBNL Geneva, IL October 5-6, 2005 bnl – fnal – lbnl.
Outline: Strand R&D and strand procurement and inventory. Main parameters of the cable without a core. Results obtained during the cable development without.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
24 Th January Status of the Conductor Development Status of the manufacturing for Alstom Status of the manufacturing for SMI L. Oberli.
HL-LHC/LARP Cable Review, CERN, Nov Lessons Learnt in LARP- A. Ghosh 1 Lessons Learnt from LARP experience Arup. K. Ghosh HL-LHC/LARP International.
1 BNL -FNAL - LBNL - SLAC P. Wanderer IR’07 - Frascati 7 November 2007 U.S. LARP Magnet Programme.
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
29 th September 2009 EuCARD-WP7 HFM Conductor specification and procurement Luc OBERLI CERN, TE-MSC-SCD.
Long Quad (LQ) & High Gradient (HQ) Series Alexander Zlobin bnl - fnal- lbnl - slac US LHC Accelerator Research Program DOE LARP review Fermilab, June.
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
LARP Review, June 10, 2013Magnet Cost and Schedule – M. Kaducak 1 IR Quadrupole Cost and Schedule Marc Kaducak LARP Review June 10, 2013.
Discussion about the technical specification of the Nb-Ti strand and Rutherford cable for the MCBXF corrector magnets.
Logo area 11 T Wire: Procurement Strategy and QA/QC B. Bordini, A. Ballarino, M. Macchini Acknowledgments: thanks to E. Charifoullina for her contribution.
Answers to the review committee G. Ambrosio, B.Bordini, P. Ferracin MQXF Conductor Review November 5-6, 2014 CERN.
LARP Collaboration Meeting 15 Nov 1-3, 2010 A2C- Materials Working Group Arup Ghosh (coordinator), Emanuela Barzi, Dan Cheng, Dan Dietderich, Soren Prestemon,
LARP CM15, SLAC, 11/3/2010GianLuca SabbiSummary of MS Parallel Sessions Summary of Magnet Systems Parallel Sessions GianLuca Sabbi LARP Collaboration Meeting.
2 nd LARP / HiLumi Collaboration Mtg, May 9, 2012LHQ Goals and Status – G. Ambrosio 11 LHQ Goals and Status Giorgio Ambrosio Fermilab 2 nd LARP / HiLumi.
LARP DOE Review July 13-14, 2009Materials – Conductor Support - A. Ghosh1 LARP DOE Review July , 2009 FNAL 2.4 Materials – Conductor Support Arup.
Conductor Requirements for Magnet Designers DOE- Conductor Development Program Daniel R. Dietderich Superconducting Magnet Program Office of Science ICFA.
LARP Collaboration Meeting 15 Nov 1-3, 2010 Conductor Procurement and Qualification Arup K. Ghosh (BNL) bnl - fnal- lbnl - slac US LHC Accelerator Research.
DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Answers to committee questions - magnets.
CERN QXF Conductor Procurement and Cable R&D A.Ballarino, B. Bordini and L. Oberli CERN, TE-MSC-SCD LARP Meeting, Napa, 9 April 2013.
MQXF Cable for Q1/Q3 D.R. Dietderich MQXF Conductor Review November 5-6, 2014 CERN.
Cost drivers for very high energy p-p collider magnet conductors Lance Cooley and Ian Pong FCC 2016, Rome.
Lessons learnt from CERN experience
Crab Cavities Contribution from the U.S.
MQXF Goals & Plans G. Ambrosio MQXF Conductor Review
MQXF Planning Paolo Fessia, Frederic Savary, Ezio Todesco, Lucio Rossi - CERN Mike Anerella, Peter Wanderer - BNL Giorgio Ambrosio, Mark Kaducak - FNAL.
CERN Conductor and Cable Development for the 11T Dipole
EDR HLRF Work Packages Draft Summary
MQXF Short Models Status and Plans
To be presented at Nb3Al R&D Review,
Procurement of Nb3Sn strand for coils assembled at CERN
P. Ferracin and G. Ambrosio
MQXF updates P. Ferracin October 9th, 2014.
Risk Description: Bus Tapes
Presentation transcript:

Procurement of Nb 3 Sn strand, cable fabrication, and quality control for the U.S. Hi-Lumi LHC Accelerator Upgrade Project Lance Cooley, Fermilab L3 manager for strand and cable MQXF International Review – CERN, June 7 th – 10 th, 2016

logo area Overview - strand  The U.S. team is moving forward with an acquisition plan for 10 tons of conductor  The present LARP procurement of 208 km = ~1 ton, to conclude early 2017, has exhibited properties well above specification  Pre-production issues have emerged as well  The AUP profile requires a LARP procurement of 1.5 ton = 300 km at FY17 start with option for 1700 km = 8.5 additional tons after CD-1 / CD-3a  Magnets are critical path; procurement start is important for schedule margin  The acquisition plan assumes a phased procurement  The schedule addresses risks for raw material delay by adding 20% of (year+1) needs to yearly procurement Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th 20162

logo area Overview - cable  The AUP plan assumes fabrication of 100 cables will be needed for 90 coils  Risk for cable failure is incorporated into the project baseline procurement  Mitigation requires procurement of more unit lengths …  … However, the UL will reduce, so net procurement is same  6 long cables have been fabricated with no issues; the 7 th long cable was started and then halted due to a strand break 15 m after start of run  Resolution and corrective actions will be discussed  LARP will have produced 17 long cables by close of program Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th 20163

logo area Overview – QA / QC  Quality Assurance  International standards, written procedures, personnel and facility qualification, and benchmarking are integrated into the project  Quality Control  Primary strand QC responsibility is the supplier  Testing at each end of billet mandatory  Interior piece testing shall be triggered by breakage  QC test is a ~3% cost penalty, encourages long pieces  Labs will verify supplier tests with graded testing approach  50% at start; lower as production continues  Benchmarking has been completed  Cables qualified by RRR and microscopic analyses  Addition of cable scanning and strain sensors on Turk’s head Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th 20164

logo area Specification table for LARP and HL-LHC AUP strand Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th 2016 Magnet length and field gradient Field quality Magnet protection 5 Field quality

logo area Specification table, p.2 Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th 2016 < 5% reduction of properties upon cabling Cooling 6 Magnet length Cooling

logo area Conductor acquisition plan for HL-LHC AUP  100 cable ULs x 40 strands = 4000 unit lengths = 2000 km = 10,000 kg  1 cable UL = 500 m  1 cable UL = 20 km strand = 100 kg = $175k (per basis of estimate) or $155k (present LARP cost)  About 250 billets  8 potential suppliers (next slide)  Only OST was qualified under LARP  Best value procurement  Technical review panel identified  Cost-performance balance defined Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th 20167

logo area Suppliers and qualification A source evaluation board will not be used for HL-LHC AUP Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th Only vendor to meet LARP qualification = Vendors with significant potential to respond to Project RFP

logo area RRR vs Ic for present LARP procurement Statistical process control at 3-sigma (99.1%) level  Statistics (11 billets, 22 spools) for 665 °C / 75 h HT  Shipment B received 31 March 2016, Lab measurements not yet available  Hotter, longer HT promotes higher 15 T Jc  RRR difference was found to be arise from different sample preparation by benchmarking, and possible actions are being considered at this time Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th  = 48 A 3  = 59 A 2738 A/mm A/mm 2 3  = 90 9

logo area N-values and copper to non-copper ratio Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th  =  = 4.8 Cu:NC = 1.2 ± 0.1 Average Dia. Spec ± mm

logo area Delivered piece length distribution (162 of 308 km) Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th m 1100 m 2200 m3300 m4400 m5500 m6600 m7700 m8800 m9900 m Max length for 45 kg billet = 9250 m  LARP = 141 UL (i.e. 3.5 cables)  CERN = 123 UL

logo area Diameter measurements along axes – example of QC A discrepancy at supplier was corrected after shipment A Average diameter = (dx + dy) / 2 12 Verification at labs identified a faulty laser micrometer, a die out of calibration, and vertical axis vibration on supplier’s line  non-conformity, corrective actions completed Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th 2016

logo area Deviations and Non-conformance  While the QC plan outlines procedures for handling discrepancies, established procurement policies at the supplier and the labs work very well  Supplier is required to receive authorization to deliver, and must provide a certificate of compliance  Request for authorization to deliver must include all QC data, billet pedigree report, and piece report  Verification samples are sent to lab when request is made; lab can hold shipment until QC data are verified  NC, DR, and discrepancy processes have all been exercised during the present LARP procurement  Non-conforming: diameter at specification limit, corrective actions  Deviation request for piece shorter than minimum length  RRR test discrepancy revealed difference in sample preparation Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th

logo area QA as a continuous process  Diameter non-conformity: fault at 2 levels  A round-robin test (OST, LBNL, BNL) revealed the discrepancy  Laser micrometer out of calibration and was replaced; drawing die was retired; new equipment and dies were installed  Raw material: boron impurity caused hard NbB precipitates to occur  Boron was not included in material specifications (e.g. ASTM)  Documentation allowed OST and sub-contractor to trace defect to ore source at sub-contractor  New spec, QC and testing have been added  Cable: fault at 2 levels and production learning  A clean room defect was present within “manually scan” length  QC procedure was not followed by 2 nd shift tech in production Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th

logo area Conclusions  A comprehensive acquisition plan, QC plan, and strand specification have been completed  These were exercised in a pre-production LARP procurement  LARP will request proposals for 1.5 tons, with option for additional 8.5 tons (AUP), this summer, for contract award Oct-Dec 2016  Start of procurement at beginning of FY17 is required to provide adequate schedule margin for magnet production  The 0.85 mm RRP ® 108/127 strand meets or exceeds specifications, with significant margin for I c and RRR  Delivered piece lengths are consistent with past performance and cost model, no surprises Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th

logo area Conclusions - 2  Risks were uncovered during the pre-procurement run  Strand production has been delayed by 9 months due to raw material issue  Phased procurement will add 20% of (year+1) strand needs to mitigate risk of raw material gap  A strand break occurred during the 7 th long cable run  Location was in startup length, cause appears to be an inclusion that escaped supplier QC at a “manually scan” region  At OST: R&D teams are handing off responsibility for conductor to production teams  If this had occurred in the middle of the run, the cable would have been lost  Total acquisition will support 100 cable unit lengths to address a 10% cable failure rate Cooley – US Strand, Cable, and QC - MQXF International Review, June 7th-10th