Progress on Beryllium Cavity Design R. Fernow, D. Li, R. Palmer, D. Stratakis, S. Virostek as told to Michael S. Zisman Center for Beam Physics Accelerator.

Slides:



Advertisements
Similar presentations
MICE RF Cavities and RFCC Module Update Derun Li Lawrence Berkeley National Laboratory MICE RF Workshop Daresbury Laboratory, UK April 17, 2012 April 17,
Advertisements

MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
KEK Recent results of beam tests on clearing electrode and grooves 2010/1/191ILC DR WebEx Meeting Y. Suetsugu, KEK.
MICE RF Cavity Design and Fabrication Update Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 27, 2004.
Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
MuCool Test Area RF Workshop Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 15, 2010.
RF Measurement Plan Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory January 20, 2011 MICE Video Conference Meeting.
Integration of Cavities and Coupling Coil Modules Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting March 28 – April 1, 2004.
Effects of External Magnetic Fields on the operation of an RF Cavity D. Stratakis, J. C. Gallardo, and R. B. Palmer Brookhaven National Laboratory 1 RF.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
Status of the 201 MHz Cavity and Coupling Coil Module Steve Virostek Lawrence Berkeley National Laboratory MICE Video Conference March 10, 2004.
Module Vessel Connection Concept Steve Virostek Lawrence Berkeley National Laboratory AFC Module Meeting April 23, 2004.
Electron Motion in a RF Cavity with external Magnetic Fields Diktys Stratakis Brookhaven National Laboratory RF Workshop – FermiLab October 15, 2008.
D. Li and R. Rimmer, RF Workshop, Fermilab, MHz Cavity Refurbishment and suggestions on future tests Derun Li and Robert Rimmer* Lawrence.
Update on Be Wall Cavity Steve Virostek Lawrence Berkeley National Lab MTA RF Workshop November 15, 2010.
Safety Review: RF Issues Derun Li Absorber Safety Review December 9-10, 2003 Lawrence Berkeley National Laboratory Berkeley, CA
201 MHz NC RF Cavity R&D Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory WG3 at NuFact 2004 July 28, 2004.
Status of 201 MHz Prototype and RFCC Module Derun Li, S. Virostek, M. Zisman Center for Beam Physics Lawrence Berkeley National Laboratory In collaboration.
Design of Standing-Wave Accelerator Structure
5-Year RF R&D Plan Derun Li Lawrence Berkeley National Laboratory NFMCC and MCTF Phone Meeting Friday, September 18, 2009.
Samuli Heikkinen CLIC Workshop October 2007 a short summary of the doctoral thesis on the CLIC fatigue study.
Progress on the MuCool and MICE Coupling Coils * L. Wang a, X. K Liu a, F. Y. Xu a, A. B. Chen a, H. Pan a, H. Wu a, X. L. Guo a, S. X Zheng a, D. Summers.
NCRF R&D Programs and Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MUTAC Review at BNL April 28, 2004.
201 MHz and 805 MHz Cavity Developments in MUCOOL Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Nufact 2002 Workshop, London,
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
Design Concepts for Magnetic Insulation Diktys Stratakis Advanced Accelerator Group Brookhaven National Laboratory NFMCC Meeting – LBL January 28, 2009.
1 Calorimeter Thermal Analysis with Increased Heat Loads September 28, 2009.
New HOM coupler design Demountable Damped Cavity (DDC) Sokendai, The graduated university for advanced studies. KEK, LL / Ichiro Cavity Group October 21,
Status of RFCC-Module Development Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE Collaboration Meeting at INFN-LNF, Frascati,
201 MHz NC RF Cavity R&D for Muon Cooling Channels
201-MHz RF Cavity Construction (Plan) for MICE Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory NFMCC Meeting March 17, 2008.
201 MHz Cavity Status and Test Plans at MTA MICE Collaboration Meeting at RAL, UK October 22 ~ 24, 2005 Derun Li Center for Beam Physics Lawrence Berkeley.
ATLAS Calorimeter Argon Gap Convection Test Bed Brian Cuerden 24 Apr
Normal Conducting RF Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory March 5-6, 2013.
ATLAS Calorimeter Argon Gap Convection Test Bed April 25,
201 MHz Cavity Fabrication Update Derun Li Lawrence Berkeley National Lab MICE CM24 at RAL, UK June 1, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
1.3GHz Input Coupler for ILC
RF studies at Fermilab MuCool Test Area Fermilab MuCool Test Area MuCool Test Area (MTA) at Fermilab is a dedicated facility at the end of the LINAC built.
MICE RF Cavities and RFCC Module Update Allan DeMello and Derun Li Lawrence Berkeley National Laboratory MICE CM32 at RAL, UK February 9, 2012 February.
Study Plan of Clearing Electrode at KEKB Y. Suetsugu, H. Fukuma (KEK), M. Pivi, W. Lanfa (SLAC) 2007/12/191 ILC DR Mini Work Shop (KEK) Dec.
1 Al Moretti, APC, Fermilab MAP- Winter Meeting February 28 - March 4, 2011 TJNAF Newport News, VA.
MICE RF Cavity Measurements Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory July 8, 2010 Rutherford Appleton Laboratory, UK.
A. Bross MICE CM17 February MuCool RF Program 805 and 201 MHz Studies.
Simulation of the CLIC Compressor Cavity, Luca Dassa (EN-MME/ES)10/04/ di 10 Simulation of CLIC Pulse Compressor Cavity Report, April 10th, 2013.
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
RF Breakdown Study Arash Zarrebini MuCool RF Workshop 15 th October 2008 U.K Cavity Development Consortium.
Update on 201-MHz RF Cavity Construction (Plan) for MICE
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Cavity support scheme options Thomas Jones 25/06/15 1.
A 350 MHz, 200 kW CW, Multiple Beam IOT Lawrence Ives, Michael Read, David Marsden, R. H. Jackson, Thuc Bui Calabazas Creek Research, Saratoga, CA. USA.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory Oxford, UK July 7, 2011 July 7, 2011.
Multipacting Simulation for the Muon Collider Cooling Cavities* L Ge, Z Li, C Ng, K Ko, SLAC R.B. Palmer, BNL D Li, LBNL The muon cooling cavity for the.
201 MHz Cavity Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory February 11, 2011 MAP Friday Video Conference Meeting.
RF Modeling of the LHC Crab Cavity Zenghai Li SLAC Zenghai Li LARP CM20 April 8-10, 2013.
2008/12/10 INFN R&D on Low Impedance Beam Chamber and Components Y. Suetsugu, for KEKB Vacuum Group Contents Introduction Beam Chamber Components Connection.
PXIE RFQ Engineering Design Steve Virostek Engineering Division Lawrence Berkeley National Laboratory April 10, 2012 Project X Collaboration
RFCC Engineering Status and Plans Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Meeting March 6, 2012 March 6, 2012.
Engineering of the power prototype of the ESRF HOM damped cavity* V. Serrière, J. Jacob, A. Triantafyllou, A.K. Bandyopadhyay, L. Goirand, B. Ogier * This.
704 MHz cavity design based on 704MHZ_v7.stp C. Pai
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
PXIE RFQ Design Overview Derun Li for PXIE RFQ Design Team Center for Beam Physics Accelerator and Fusion Research Division Lawrence Berkeley National.
RF R&D (Issues) for Muon Ionization Cooling Channels
RF Dipole HOM Electromagnetic Design
T5.2: Harmonization - Material and Component Reference
Overview of the RFCC Module and 201-MHz Cavity Design
MICE RF Cavity Simulations and Multipactor
Effects of External Fields on RF Cavity Operation
Summary of MuCool/MTA RF workshop
Multipacting Simulation for the Muon Collider Cooling Cavities*
Presentation transcript:

Progress on Beryllium Cavity Design R. Fernow, D. Li, R. Palmer, D. Stratakis, S. Virostek as told to Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research division Lawrence Berkeley National Laboratory NuFact10-Mumbai October 24, 2010

October 20, 2010Accel. Concepts & Challenges - Zisman2 Introduction MuCool RF studies have shown significant reduction in maximum gradient when an axial magnetic field is applied —seen in 805 MHz test cell —hints of problems at 201 MHz also o in this case only fringe field is presently available for testing In both cases, it appears that problems in the coupler region are playing a strong role in observed breakdown —possible that further studies will change our perception of this issue Some models have suggested that Be may be a better wall material than Cu —motivated by this, plans to fabricate a cavity with Be walls are in progress

October 20, 2010Accel. Concepts & Challenges - Zisman3 Present Situation Brief summary of experimental data shown below —note that behavior at 805 MHz and 201 MHz look different o but fields are also quite different —“missing” 201 MHz requirement by factor of ~2

October 20, 2010Accel. Concepts & Challenges - Zisman4 Model Type of data we hope to explain and mitigate: —damage resulting from focused field emission (a) o information from surface ohmic heating (b) provides “calibration point” on when damage can occur –damage believed to be caused by fatigue from repeated strains due to heating

October 20, 2010Accel. Concepts & Challenges - Zisman5 SLAC Studies Used special cavity with no surface electric fields but with surface currents —damage observed (Tantawi et al.) on soft copper after cyclical heating o  T ~ 45°C —we assume similar effect from beamlet heating

October 20, 2010Accel. Concepts & Challenges - Zisman6 Choice of Materials To mitigate fatigue damage, seek materials with —low coefficient of thermal expansion —high specific heat —high thermal conductivity —for surface heating effect, also want high electrical conductivity Materials being considered —copper —beryllium o low density o lack of damage in experiments to date —aluminum

October 20, 2010Accel. Concepts & Challenges - Zisman7 Estimation of Strain Approach —use approximate calculations to estimate temperature rise and resulting strain o  (T) is coefficient of thermal expansion; A beam is beamlet area at surface; Q(T) is factor to account for thermal diffusion (increases transverse heat zone) –assumes no temperature variation with lateral diffusion

October 20, 2010Accel. Concepts & Challenges - Zisman8 Thermal Diffusion Two different assumptions made for thermal diffusion effects —diffusion size small compared with spot size o Q(T) = 1 —diffusion size comparable to spot size o Q(T) = d(273)/d(T) —third option, with large diffusion size, would not match observed B dependence

October 20, 2010Accel. Concepts & Challenges - Zisman9 Temperature Rise Normalized to give  T = 45°C for Cu at room temperature —this value resulted in damage for Cu in the SLAC experiments —Be gives lowest temperature rise

October 20, 2010Accel. Concepts & Challenges - Zisman10 Strain Use equation in slide 7 to evaluate strain for different cases —Be has much less strain than Cu —Al is somewhat better than copper —for case b, where thermal diffusion matters, model predicts improvement at lower temperatures for Be and Al

October 20, 2010Accel. Concepts & Challenges - Zisman11 Breakdown Gradients Assume damage occurs at same strain as for Cu at 45°C —Be looks better o shape roughly consistent with what we have seen –needs to be tested!

October 20, 2010Accel. Concepts & Challenges - Zisman12 Conclusions from Modeling Beryllium appears to be ideal cavity material —except for fabrication issues —may well solve the observed gradient shortfall Aluminum also somewhat better than copper —would need TiN coating Be pillbox cavities would have substantial advantages over magnetically insulated cavities —much higher shunt impedance —better ratio of acceleration field to maximum surface field

October 20, 2010Accel. Concepts & Challenges - Zisman13 Test Program (1) Initial tests will use back-to-back buttons —button field enhancement increased to 3x o should eliminate possibility of breakdown on Cu surfaces —will test Be, Al, and Cu and possibly other materials

October 20, 2010Accel. Concepts & Challenges - Zisman14 Test Program (2) Subsequent experiment will use Be wall cavity —funding for design and fabrication in hand Two designs have been considered —only one fits Lab G magnet

October 20, 2010Accel. Concepts & Challenges - Zisman15 Cavity Fabrication Design being done by S. Virostek —with guidance from D. Li and R. Palmer CAD model for one concept has been completed —next steps o evaluate cost of beryllium material o evaluate cost of various fabrication techniques o analyze manufacturing risks –brazing –coupling port –bolted joints –machining processes

October 20, 2010Accel. Concepts & Challenges - Zisman16 Cavity Concept Main features —two bolted halves with vacuum and RF seals o offers accessibility advantages over e-beam welded cavity —main body is Cu-plated Hastelloy or solid Cu —coupling port slotted in side wall —inner side walls are Be (TiN coated) Side wall options —thin Be foil (0.5 mm) brazed to side walls —thick Be plates (6 mm) brazed to side walls —solid Be walls (no brazing) o all-Be cavity probably impractical

October 20, 2010Accel. Concepts & Challenges - Zisman17 3D CAD Model Initial model has been developed —progress delayed by other priorities recently

October 20, 2010Accel. Concepts & Challenges - Zisman18 Manufacturing Issues Brazing —Be brazing is only done at select shops —differential expansion may be a problem for solid Cu body —may be some issues with brazing to Cu plated Hastelloy —transition from Be side walls to rounded corner at cavity OD presents some challenges Coupling port —interface between Be and cavity body material at port needs to be fully brazed —need to incorporate a connection flange to RF waveguide Cavity joints —seal(s) between cavity halves needs to provide a good RF connection as well as a vacuum seal Machining —few shops available to do Be machining

October 20, 2010Accel. Concepts & Challenges - Zisman19 Task List Complete conceptual design layouts Perform analysis and trade-off studies Develop final conceptual design Generate fabrication drawings Procure long lead materials (Be) Fabricate cavity components Braze, coat Be and assemble cavity LBNL responsibility (S. Virostek, D. Li)

October 20, 2010Accel. Concepts & Challenges - Zisman20 Summary Observed RF gradient in magnetic field less than required —SLAC sees damage due to cyclical RF heating by only 45°C —possible that our effect due to cyclical heating from field emitted beamlets Damage thresholds estimated —with several assumptions Indication that performance improved for Be cavity —and possibly for cavity operated at LN temperature Initial experiments with Be buttons planned Be wall cavity design under way —will be tested ASAP