APEX Status and Plan Phil’s Meeting, March 20, 2012 M. Bai.

Slides:



Advertisements
Similar presentations
APEX Report April 28-29, 2009 May 4, 2009 Fulvia Pilat Time Meeting, May
Advertisements

AGS pp Status Feb. 6, 2015 RSC Meeting Haixin Huang.
RHIC Status Haixin Huang Time Meeting 02/1/2011. Jan. 26 Ring access for six hours to fix jet and many other jobs. Difficulty to provide 28X28 store overnight.
1 RHIC Run-7 Au-Au Operation A. Drees APEX workshop, Nov 2 nd 2006 Run organization Previous run and expectation for Run7 Start-Up plan Problem areas.
RHIC polarized protons – The next decade – Wolfram Fischer 14 May 2010 RSC Meeting, Iowa State University.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 5 Apr 2011 Agenda: Open.
APEX Report: March 31 – April 1, 2009 Fulvia Pilat Time Meeting, April 7, 2009.
AGS pp Status Feb. 20, 2015 RSC Meeting Haixin Huang.
AGS Polarized Proton Development toward Run-9 Oct. 3, 2008 Haixin Huang.
Beam-beam Observations in RHIC Y. Luo, W. Fischer Brookhaven National Laboratory, USA ICFA Mini-workshop on Beam-Beam Effects in Hadron Colliders, March.
Overview Run-6 - RHIC Vadim Ptitsyn C-AD, BNL. V.Ptitsyn RHIC Spin Workshop 2006 RHIC Run-6 Timeline  1 Feb – Start of the Run-6. Start of the cooldown.
RHIC Accelerator Capability: Present and Future Mei Bai Collider Accelerator Dept. BNL.
Thomas Roser Snowmass 2001 June 30 - July 21, 2001 Polarized Proton Acceleration and Collisions Spin dynamics and Siberian Snakes Polarized proton acceleration.
October 4-5, Electron Lens Beam Physics Overview Yun Luo for RHIC e-lens team October 4-5, 2010 Electron Lens.
May 17, 2005Wednesday Experiment Meeting BNL, Upton Acceleration beyond 100 GeV  Goal To evaluate the spin dynamics beyond 100 GeV  What’s the impact.
Preparation for RHIC PP Run in 2011 Wednesday 20, 2010 RHIC Machine Planning Meeting Haixin Huang RUN website: RUN.
RHIC Run14 Time Meeting. Run14 Status – Apr. 29 Operations running well, 11 full stores over the past 7 days; setting STAR ZDC rates to 50 khz is now.
Plans for Polarized Beams at VEPP-2000 and U-70 Yu.Shatunov BINP, Novosibirsk P S IN 2006.
RHIC Status: Startup Run 12 V. Schoefer RHIC Spin Collaboration Meeting 1/13/12.
RHIC Run14 Time Meeting. Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing.
RHIC Run14 Time Meeting. Run14 Status – Apr. 22 Operations running well, 12 stores over the past 7 days with 1 “super store” of 17 hours. Repositioned.
APEX Report March 3, 2010 Fulvia Pilat Time Meeting, March 9, 2010.
RHIC pp 500 GeV development M. Bai C-A Department.
APEX Report: February 26-27, 2008 Fulvia Pilat Time Meeting, March 4, 2008.
RHIC Run11 Summary May 6, 2011 RSC Meeting Haixin Huang Luminosity Availability Polarization RHIC setup issues.
Feb. 23, 2005Wednesday Experiment Meeting BNL, Upton Status on AGS cold snake  Cold mass is now in the cryostat. It is in the phase of wiring, and because.
APEX RUN-14 APEX Schedule April 1, :00am Store Elens commissioning Gu, Fischer, Luo, Simon 10:00am 4:30pm2:00pm AC dipole setup Bai Momentum Aperture.
Polarization in ELIC Yaroslav Derbenev Center for Advanced Study of Accelerators Jefferson Laboratory EIC Collaboiration Meeting, January 10-12, 2010 Stony.
Preparation Status of pp Run11 Haixin Huang Time Meeting 12/21/
Status of Head-on Beam-Beam Compensation BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program A. Valishev, FNAL 09 April 2009 LARP CM12.
J-PARC Spin Physics Workshop1 Polarized Proton Acceleration in J-PARC M. Bai Brookhaven National Laboratory.
Simulation of Spin Interference and Echo Effect Abstract Successively jumping across a depolarization resonance twice produces interesting spin dynamics.
POLARIZATION MEASUREMENTS AND ABSOLUTE POLARIZATION VALUES EVOLUTION DURING PROTON BEAM ACCELERATION IN THE RHIC ACCELERATOR COMPLEX A.Zelenski, T.Roser,
RHIC Store Energy Scan Mei Bai Collider Accelerator Dept. Brookhaven National Laboratory.
Thomas Roser SPIN 2008 October 10, 2008 The Future of High Energy Polarized Proton Beams Spin dynamics and depolarizing resonances Early multi-GeV polarized.
09-21 Study of bunch length limits Goals: To identify and observe effects which put limits on the minimum bunch length in RHIC. Try to distiguish the limitation.
Orbit related issues of the spin tune control at RHIC V.Ptitsyn, M.Bai, W.MacKay, T.Roser.
First Demonstration of Optics Measurement and Correction during Acceleration Chuyu Liu Collider Accelerator Department, BNL.
Accelerating Polarized Protons to High Energy Mei Bai Collider Accelerator Department Brookhaven National Laboratory.
Beam Physics Issue in BEPCII Commisionning Xu Gang Accelerator physics group.
Thomas Roser Snowmass 2001 June 30 - July 21, 2001 Proton Polarimetry Proton polarimeter reactions RHIC polarimeters.
APEX Schedule April :30am12:30pm5pm IBS suppression lattice Litvinenko, Tepikian +team Back 2 Phys 4pm Nonlinear Chromaticity (Response.
1 RHIC II – Ion Operation Wolfram Fischer RHIC II Workshop, BNL – Working Group: Equation of State 27 April 2005.
Polarized Proton at RHIC: Status and Future Plan Mei Bai Collider Accelerator Dept. BNL A Special Beam Physics Symposium in Honor of Yaroslav Derbenev's.
APEX RUN-12 APEX Schedule Feb 22, 2012 Injection 8am 11pm IP transfer matrix Tepikian, Ptitsyn If needed: Beam Scrubbing Blaskiewicz, Montag, Huang Injection.
RHIC 250 GeV Polarized Proton Run 2009 Mei Bai RUN website: 12/16/2008RHIC Spin Collaboration Meeting.
RHIC Status April 8, 2011 RSC Meeting Haixin Huang.
Haixin Huang AGS Cold Snake: Status and Plans.
APEX Studies: Accelerating w. Near 3 rd Order Resonance Vincent, Al, Michiko, Steve, Don, Yun, Guillaume, Mei, Todd, Wolfram, Greg, …
RHIC Status Haixin Huang RSC Meeting 02/18/2011. l Fixed the blue dump kicker noise problem last Friday. l Declared physics last Friday. l Smooth run.
Thomas Roser SPIN 2006 October 3, 2006 A Study of Polarized Proton Acceleration in J-PARC A.U.Luccio, M.Bai, T.Roser Brookhaven National Laboratory, Upton,
Status of RHIC Polarization Studies. Summary of Polarization Studies during Run09 Tune scans: – Nearby 0.7 – Near integer tune Polarization ramp measurement.
Plan for 500 GeV Development Vadim, Mei. Goals 1.Explore polarization transmission to the 500 Gev CM energy. 2. Inspect the luminosity aspects (with 2.
CNI polarizations in Run09: Summary A.Bazilevsky For the RHIC CNI Group March 26, 2010 RSC meeting.
APEX RUN-11 APEX Schedule May 11, 2011 Injection 12am8am BBA Minty, Jordan, Liu, Rob, Rob, Kevin, … Spin Flipper Bai, Pablo, Oddo, Craig, Kevin IPM calibration.
AGS FY11 Summary RHIC Spin Collaboration Meeting 5/6/11.
Operation Notes APEX Status Fulvia Pilat Machine Experiments Meeting January 20, 2009.
APEX RUN-11 APEX Schedule Planned Feb. 23, pm ~ 3 ramps 8am 12x12 store Physics store Beta* unsqueeze +s* adjustment GRD+team 6x6 store AC dipole.
RHIC Status Haixin Huang Time Meeting 01/25/2011.
Polarized Proton Acceleration in the AGS with Two Helical Partial Snakes October 2, 2006 SPIN 2006 H. Huang, L.A. Ahrens, M. Bai, A. Bravar, K. Brown,
I Alexander Nass for the JEDI collaboration
Summary Thursday h21: Stable beams fill #1303.
Spin Transparency Study and Test
Update on MEIC Ion Polarization Work
Yu.N. Filatov, A.M. Kondratenko, M.A. Kondratenko
Progress Update on the Electron Polarization Study in the JLEIC
Current Status of Ion Polarization Studies
Summary and Plan for Electron Polarization Study in the JLEIC
Report on Electron Polarization Study
Status of RCS eRHIC Injector Design
Presentation transcript:

APEX Status and Plan Phil’s Meeting, March 20, 2012 M. Bai

Polarization Performance Challenges Polarization Transmission Efficiency –To achieve 100% polarization transmission efficiency between 100 GeV and 255 GeV –Identify where we loose One study –Deep understanding of depolarizing mechanism, benchmarking spin tracking code One study Polarization lifetime at store –Optimize snake setting including its orbital angle, parasitic/MD –Minimize vertical angle between rotators, parasitic/MD –Understand the effect of beam-beam on polarization lifetime One study –Benchmark stable spin direction calculation One study

Polarization Performance Challenges Polarimetry, polarimetry! –Fast and Reliable –It is very critical for all polarization related beam studies –So far, one dedicated beam study proposal Develop new working point for pp operation –Current working point has issues on emittance growth due to excitation of pi mode, which gets closer to 2/3 resonance. –Putting one ring working point above 0.7 showed bad polarization lifetime at store, which is yet not well understood and is on the APEX list –In preparation to the success of Elens, we need to find a new working point(s) which can accommodate not only as much as beam-beam tune shift, but also post no adverse impact on beam polarization

List of Polarization Related Beam Studies Impact of orbit harmonic correction – PI: V. Ranjbar – Goal: To determine impact of various harmonic orbit distortions on Polarization in RHIC. Understand if polarization can be improved via targeted harmonic correction to reduce associated spin imperfection resonance strength and to understand the impact of different harmonics on polarization. – Beam time request: 6 RHIC ramp to systematically scan the effect of orbital harmonic 29 at spin resonance 393+Qy, 411-Qy on polarization. Can be parasitic to physics data taking. – Impact on Physics: Can result in significant polarization losses during acceleration. Can also cause failed ramps if the request change in orbit exceeds the control of the orbit feedback.

List of Polarization Related Beam Studies Polarization loss crossing 411-Qy resonance in RHIC – PI: V. Ranjbar – Goal: To Understand Polarization loss due to crossing the 411-Qy and 393+Qy resonance during the RHIC ramp – Beam time request: This requires having two special acceleration and decceleration ramp, one goes to Ggamma= and another one goes to Ggamma= Polarization will be measured at injection as well as each store energy. – Impact on Physics: None

List of Polarization Related Beam Studies Evaluate polarization lifetime at store with different working point – PI: M. Bai, Y. Luo, S. White – Goal: to understand why polarization lifetime is much worse with tunes above 0.7. To have split tune for collision can be very beneficial for Elens. So, it is important to know how polarization behaves with this configuration – Beam time request: This study requires 2~3 regular stores, during which both detectors can continue take data. – Impact on Physics: Can have much lower average store polarization. Luminosity lifet

List of Polarization Related Beam Studies Measured polarization profile at Ggamma=462.5 – PI: V. Ranjbar, M. Bai – Goal: Measure Polarization Profile at Ggamma= Verify the spin tracking res – Beam time request: This study needs to store beam at Ggamma=462.5 without rotators for ~4-5 hours. Polarization profile as well as average polarization will be monitored by CNI as well as Jet polarimeter. – Impact on Physics: since this is at different energy, experiments may not be interested in taking data.

List of Polarization Related Beam Studies Polarimeter performance with special targets – PI: H. Huang – Goal: To study the effect of target orientation on polarization measurement with different target (regular, high twist, wide 5mm target). To quantify the effect of the target orientation – Beam time request: requires two hours of dedicated beam time – Impact on Physics: none

List of Polarization Related Beam Studies Near-working point development – Goal: To evaluate the polarization transmission efficiency To check the feasibility of swing the working point to 0.98 and above for collsion – Condition: Lattice: no beta-squeeze Ramping tune: 0.92, 0.93 Ramp: all four feedbacks+10Hz feedback – Beam time request: requires dedicated beam hours – Impact on Physics: none

Tentative APEX Schedules for Polarization sessionDurationPolarization development related studies March 218am – 8pmSpin flipper, impact of orbit harmonic study: test all the tools including software at injection (parasitic to others) March 288pm – 8amPolarimeter, Polarization lifetime with split tune(8 hour store), impact of orbit correction April 48am – 8pmPolarization loss crossing 411-nu(requires up-down ramp) April 118pm – 8amPolarization profile at Ggamma=462.5 April 188am – 8pmNew working point development

APEX Schedule March 21, 2012 Injection 8am 7pm IP transfer matrix Tepikian, Ptitsyn Off momentum beta beat measurement/correction White, Luo, Bai Store Injection 12pm V dispersioncorrection, weighted algorithm C. Liu, Luo, Minty Back2Physics 8pm Beam Beam: pi mode suppression Luo, White 5pm 3pm Store 10am Spin flipper M. Bai, P. Oddo, … ORM data taking Tasha, Jorg, … Triplet bpm BBA Joane, Jordan Longitudinal match w.o. GammaT C. Montag