Building for Learning Project Photo Progress Report September 2010 Project commencement 21 st September 2009
Furniture removal and storage ready for refurbishment works 21 st Sept 2009
Erecting scaffolding before roof replacement part of refurbishment works 22 nd Sept 2009
Chimney removal (Murphy’s) part of roof replacement Refurbishment works 23 rd Sept 2009
Project Manager Graeme Connelly, Architect Lindsey Jordan and Structural Engineer Mark – steel column design Sept 23 rd, 2009
Heater replacements in rooms 1-5 part of refurbishment works 24 th Sept 2009
New roof going up (over Room 1) 25 th Sept 2009
Student Computer Lab relocation ready for Room 6-9 demolition 28 th Sept 2009
New roof going up (over room 2) 28 th Sept 2009
New roof going up (over room 3) 29 th Sept 2009
Electrics being made ready for refurbishments 29 th Sept 2009 Denis – In Touch Computing making ready for Admin move to Room 3 for refurbishment works 30 th Sept 09
The thumbs up from WorkSafe Inspector Terry Wilson on our building works (the biscuits helped to sweeten him up!) – 29 th Sept 2009