Impact of not including proposed generators lacking RARF data in the planning models Planning Guide Section 6.9 Issues February 17, 2016.

Slides:



Advertisements
Similar presentations
Houston Region Import Capacity Project Planning for Reliable Power.
Advertisements

Al McBride MANAGER, AREA TRANSMISSION PLANNING Existing Import Interfaces: Transmission Transfer Capabilities and The Calculation of Tie Benefits DECEMBER.
Amendment 3/5 Workshop.
1 Generation Adequacy Task Force Report to TAC April 7, 2005.
1 Licensing in the Energy Sector Georgian National Energy And Water Supply Regulation Commission Nugzar Beridze June 27 – July 3, 2008.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
ROS Meeting November 8 th, 2012 SSWG 13DSB Case Preparation Extraordinary Dispatch.
NERC LTRA Update / CDR Capacity Counting Issues
The Status Of The Electric Grid In ERCOT The Electric Reliability Council Of Texas Sam R. Jones, P.E. ERCOT – Retired As a retiree of ERCOT this presentation.
Topics to Cover Interconnection Process Overview
RenewElec October 21, 2010 Robert Nordhaus, David Yaffe Van Ness Feldman 1050 Thomas Jefferson Street, NW Washington, DC (202) FERC’s.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
NRG Comments/Concerns with HIP Assumptions January 21, 2014 RPG Meeting NRG Comments/Concerns with HIP Assumptions - January 21, 2014.
RTWG Report to TAC August 5, 2010 Howard Daniels.
November 10, 2009 NOIE DRG Settlements TF update to COPS Settlement Discussion for ALL DG < or = 1 MW Don Tucker on behalf of the NOIE DRG Settlements.
April 23 rd OWG UFLS Survey & Power Factor Review.
Engineering a sustainable future 1 ERCOT Voltage Ride-Through Study Workshop June 26 th, 2009.
Texas Wind Energy American Meteorological Society Summer Community Meeting – Norman Oklahoma Henry Durrwachter, P.E. August 12, 2009.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee March 4, 2010.
August 17, 2012 Solar PV Inverters Anuj Dixit Planning Engineer Resource Integration RPG Meeting.
NPRR514, Seasonal Generation Resource Wholesale Market Subcommittee April 12, 2013 Amanda Frazier.
Wind ELCC Calculation Comparisons and ERCOT’s NERC LTRA Capacity Forecasts GATF Meeting, June 24, 2014.
Section 5.9 – added export language Each ERS Generator site must have an interconnection agreement with its TDSP prior to submitting an ERS offer and must.
NPRR425 - Creation of a WGR Group for GREDP and Base Point Deviation Evaluation and Mixing Turbine Types Within a WGR Art Deller, P.E. RARF Workshop 8/29/13.
ERCOT PUBLIC 4/22/ RTP Inputs and Assumptions April 22, 2014.
Project Cyber Security Order 706 Version 5 CIP Standards Potential to Adversely Impact ERCOT Black Start Capability.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
MIG TF Voting Items Market Participant Notification Period (Transmission outage) – =1 Year Interconnection Date for Protocol Considerations – First Interconnection.
Transmission Outage Process April Purpose In compliance with the Protocols and the Electric Reliability Council of Texas (ERCOT) Operating Guides,
Generation Adequacy Task Force Update to WMS November 18, 2009.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
Southern California Edison The San Onofre Nuclear Generating Station April 14, 2011.
ERS Update – DSWG Presentation September 21, 2012.
Outage Scheduler Transition Plan Kenneth Ragsdale NATF.
Distributed Generation Registration June 30, 2008.
Steady-State Working Group: Resource Modeling Discussion Wes Woitt September 27 th, 2011.
October 29, 2012 RARF Workshop 2 Introduction to ERCOT Modeling Process Jay Teixeira Manager, Model Administration.
February 3, 2011 TAC ERCOT Planning Go-Live Update Jay Teixeira Manager, Model Administration.
Impacts of Environmental Regulations in the ERCOT Region Dana Lazarus Planning Analyst, ERCOT January 26, 2016.
1 WMS Report TO TAC April 2007 (which is in March)
ERCOT PUBLIC November RPG Meeting RTP – Study Scope November 20, 2015.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee October 1, 2009.
© CONSTELLATION ENERGY GROUP, INC. THE OFFERING DESCRIBED IN THIS PRESENTATION IS SOLD AND CONTRACTED BY CONSTELLATION NEWENERGY, INC., A SUBSIDIARY.
Panhandle Renewable Energy Zone (PREZ) Study
PLWG Report to ROS September 4, PGRR039 PGRR requires Interconnecting Entities (IEs) to provide information for ERCOT’s resource adequacy reports,
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
2006 Report on the Capacity, Demand, & Resources for the ERCOT Region Technical Advisory Committee June 1, 2006 Kenneth A. Donohoo. P.E. Manager, Transmission.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
CREZ Related Generation Interconnection Studies July 2008 Jeff Billo RPG meeting
2006 CDR Status Report Technical Advisory Committee May 4, 2006 Bill Bojorquez.
ERCOT PUBLIC 3/25/ RTP Inputs and Assumptions March 25, 2014.
October 12, 2012 RPG Planning Guide 5.3.2(2) Developer obligation to keep RARF data updated Cathey Carter Resource Integration.
Transition Plan Network Operations Model Change Requests 5/26/2010.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
Generation Adequacy Task Force Meeting April 10, 2014.
October 15, 2012 PV & Storage Workshop ERCOT’s Interconnection Process John Adams Principal Engineer.
Slide 1 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N BPA Network Open Season 2013 Cluster Study ColumbiaGrid Planning Meeting May 2, 2013.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
TAC Report to the ERCOT Board
PLWG Review 6.9 and the Interconnection process
Southern Cross Directives Planning Items
Planning Geomagnetic Disturbance Task Force (PGDTF) Update to the ROS
Generation Adequacy Task Force Update to WMS
Study Scope - Quarterly Stability Assessment
Presentation transcript:

Impact of not including proposed generators lacking RARF data in the planning models Planning Guide Section 6.9 Issues February 17, 2016

Historical Background on Generation Modeling Pre-Nodal TSP’s were responsible for modeling existing and future generation resources in the planning model. All the future generation resources were modeled in the planning base cases, once the resource has signed an IA, given Notice to Proceed and provided Financial commitment. The future generation resource is modeled based upon the preliminary/FIS data. The model is updated on a regular basis, based upon the most up-to-date information received from the resource. Post-Nodal ERCOT is responsible for modeling existing and future generation resources in the planning model. All the future generation resources are modeled in the planning base cases, once the resource has met all the requirements of Planning Guide Section 6.9 The model gets updated once the resource has been modeled in the operations and when the planning model gets synched with operations model.

Planning Guide Section Addition of Proposed Generation Resources to the Planning Models (1) ERCOT will include a proposed Generation Resource in the base cases created … once each of the following has occurred: (a)The Interconnecting Entity (IE) provides all data required in the Resource Registration Glossary; (b)ERCOT determines that the IE has received all necessary Texas Commission on Environmental Quality (TCEQ)-approved air permits or that no such permits are required; (c) The IE submits a completed Declaration of Adequate Water Supplies (Section 8, Attachment B, Declaration of Adequate Water Supplies); and (d) ERCOT receives one of the following: (i)A signed Standard Generation Interconnection Agreement (SGIA) from the Transmission Service Provider (TSP) and a written notice from the TSP that the IE has provided: (ii)A public, financially binding agreement between the IE and the TSP under which the interconnection for the Generation Resource will be constructed along with: (3) The IE shall provide to ERCOT the data necessary to model the Generation Resource in the basecases created and maintained by SSWG, SPWG, and the DWG, as directed by ERCOT. (4) Once the IE has met these requirements, ERCOT will notify the SSWG, SPWG, and the DWG, and the proposed Generation Resource will be included in the base cases created and maintained by these working groups.

Existing Generators that meet PG Section 6.9 requirements except for RARF data requirement INR NumberGeneratorTSPCODTypeMW to GRID MW Based on Zone* Notes 11INR0062Patriot WindAEP12/30/2016Wind18099Insufficient Data on RARF 11INR0082aVal Verde WindAEP11/1/2016Wind Insufficient Data on RARF 14INR0013San Roman Wind 1AEP12/31/2016Wind No RARF Submitted 14INR0041aRedfish W 2aAEP12/1/2016Wind Insufficient Data on RARF 14INR0041bRedfish W 2bAEP12/1/2016Wind Insufficient Data on RARF 15INR0059Pecos Solar IAEP10/31/2017Solar108 Insufficient Data on RARF 16INR0024Hidalgo & Starr WindAEP10/1/2016Wind25030Insufficient Data on RARF 16INR0073East Pecos SolarAEP12/1/2016Solar100 No RARF Submitted 15INR0049Albercas WindAEP12/31/2016Wind25030No RARF Submitted 14INR0057Buckthorn Wind 1Brazos6/30/2016Wind Insufficient Data on RARF 14INR0057bBuckthorn Wind 2Brazos6/30/2016Wind485.76Insufficient Data on RARF 14INR0031Baytown ChillerCenterPoint6/1/2016Gas270 Not Included in the Table 13INR0049Friendswood GCenterPoint4/30/2017Gas129 Insufficient Data on RARF 16INR0003Freeport LNGCenterPoint6/1/2017Gas11 No RARF Submitted 17INR0007Colorado Bend IIICenterPoint7/31/2017Gas1148 No RARF Submitted 14INR0062Salt Fork 1 WindCTT12/31/2016Wind20024Insufficient Data on RARF 15INR0070_1bPearl SolarLCRA10/30/2016Solar50 Insufficient Data on RARF 16INR0065SP-TX-12LCRA12/1/2016Solar180 Insufficient Data on RARF 16INR0065BSP-TX-12-Phase BLCRA8/15/2016Solar120 Insufficient Data on RARF 16INR0087RTS WindLCRA12/31/2016Wind20024Insufficient Data on RARF 16INR0114Upton SolarLCRA12/1/2017Solar102 Insufficient Data on RARF 13INR0056Fluvanna Renewable 1Oncor3/1/2017Wind Insufficient Data on RARF 13INR0005cGrandview W 3Sharyland12/15/2016Wind Insufficient Data on RARF 13INR0038Swisher WindSharyland12/31/2016Wind30036Insufficient Data on RARF 14INR0023bLonghorn SouthSharyland12/31/2016Wind Insufficient Data on RARF 16INR0091Santa Rita WindSTEC12/1/2016Wind30036Insufficient Data on RARF Total 5143 MW2790 MW * COASTAL wind units are assumed to have 55% average capacity percentage and NON-COASTAL wind units assumed to have 12% average capacity percentage during summer (as represented in December 2015 CDR) * Solar units are assumed to have 100% capacity

Impact of not modeling proposed generators lacking RARF data o ERCOT & SSWG members are required to resort to using Extraordinary Dispatch Conditions due to Generation – Load Imbalance issues. o Not modeling these proposed generators lacking RARF data may result in masking or creating a reliability issue. o ~2800 MW of proposed generators lacking RARF data is not being modeled. o ~1500 MW of conventional proposed generators lacking RARF data connected to CenterPoint Energy Transmission System o Less realistic generator modeling assumptions are reflected in Planning cases. o Generators may not end up being included in the Planning models until just prior to Commercial Operations which is not representative of a Planning Horizon.

SSWG Extraordinary Dispatch Process 1. DC ties dispatched to increase transfers into ERCOT to the full capacity of the DC ties. 2. Increase NOIE generation with prior NOIE consent. 3. Ignore spinning reserve. 4. Mothballed units that have not announced their return to service. 5. Increase wind generation dispatch up to 50% of capability, starting with wind farms in counties bordering the coast. 6. Add units with interconnection agreements, but do not meet all of the requirements for inclusion defined in planning guide. 7. Add publicly announced plants without interconnection agreements. 8. Dispatch units that are solely for black start. 9. Increase wind generation dispatch up to 100% of capability, starting with wind farms in counties bordering the coast. 10. Add generation resources to the 345kV transmission system near the sites of existing or retired units. The following is a summary of Extraordinary Dispatch Conditions for each of the 15DSB cases: 2017SUM1: Steps 1 through 2 were employed. 2018SUM1: Steps 1 through 4 were employed. 2019SUM1: Steps 1 through 5 were employed. 2020SUM1: Steps 1 through 5 were employed. 2021SUM1: Steps 1 through 5 were employed. 2022SUM1: Steps 1 through 6 were employed.

Complete RARF data submittal impacts timeliness of Planning Model – Example o Received Full Interconnection Study request on April 2013 o FIS completed on October 2013 o Initial proposed Commercial Operations Date of November 2015 o Air Permit and IA signed by January 2014 o Notice to Proceed given on May 2014 o Completed RARF data submitted to ERCOT on February 2015 o Reflected in both SSWG Planning and Operations Models in April 2015 (nearly 1 year after IA and NTP).

Potential solutions to address these concerns o Possible Solutions o Remove RARF data requirement from PG Section 6.9 and use “preliminary” data for modeling purposes that was used during FIS process. o Add generators that have met all requirements of PG Section 6.9 except for RARF data as a high priority in Extraordinary Dispatch. o Require Generators to submit RARF sooner than the existing 90 day prior to COD requirement. (e.g. 12 months prior to COD) o Review RARF data requirements needed for Planning modeling purposes and ensure rejected RARFs do not in fact have the data needed for modeling.

Questions? o Do others see this as a concern? o Next Steps?