ISIS OPTIMVS NEVTRONVM SPALLATIONENSIVM FONS ORBIS TERRARVM RAL Front End Test Stand — Context David Findlay Accelerator Division ISIS Department Rutherford.

Slides:



Advertisements
Similar presentations
Imperial College 1 Progress at the RAL Front End Test Stand J. Pozimski Talk outline : Overview Ion source development LEBT RFQ Beam Chopper MEBT.
Advertisements

WG 4: High Power Proton Accelerators S. Holmes, J. Thomason PASI Collaboration Meeting April 3-5, 2013.
Front end test stand — WP2
RAL Front End Test Stand Overview, Status and Plans RAL 12 th January 2005 Alan Letchford, ISIS Injector Group.
ESS Timing System Plans and Requirements Timo Korhonen Chief Engineer, Integrated Control System Division May 19, 2014.
ISIS Accelerator Division
The RAL Front End Test Stand David Findlay ISIS Accelerator Division Rutherford Appleton Laboratory Oxfordshire, UK STVLTVS EST QVI ACCELERATORIBVS CVRANDIS.
Manchester University and the Cockcroft Institute Roger Barlow Technologies manchester.ac.uk Accelerators for ADSRs An account of the requirements.
CW neutron source Benjamin Cheymol, Angel Jesus Romero Serrano, Jesus Alonso, Lali Tchelidze 6/30/11 Benjamin Cheymol, Angel Jesus Romero Serrano, Jesus.
25/10/2007M. Dracos1 EURO The European Design Study for a high intensity neutrino oscillation facility (Rob Edgecock, Mats Lindroos, Marcos Dracos)
ADSR systems and their contribution to our energy needs Roger Barlow DIUS visit Manchester, 16 th September 2008.
ISIS, FETS and ASTeC David Findlay Head, Accelerator Division ISIS Department Rutherford Appleton Laboratory / STFC ASTeC 10 Years On, Thursday 13 October.
Front End Test Stand Klystron Commissioning Alan Letchford UKNF Plenary Meeting 22 nd April 2009.
FFAG Fixed Field Alternating Gradient synchrotrons, FFAGs, combine some of the main advantages of both cyclotrons and synchrotrons:  Fixed magnetic field.
UKNF OsC RAL – 21 & 22 June 2010 UKNF achievements & milestones J. Pozimski.
Solid Target R&D Programme Colliding the proton beam with a dense target is currently the only known way to produce enough muons for the neutrino factory.
Proposal for the continuation of the Front End Test Stand Accelerator peer review panel August 2011 Alan Letchford STFC, Rutherford Appleton Lab. On behalf.
1 st EuCARD 2 annual meeting G Bellodi – CERN WP4 AccApplic Hamburg G Bellodi - CERN / EuCARD2 Annual meeting.
M W PooleJoint DL-RAL Accelerator Workshop Jan 09 Introduction to ASTeC Programmes M W Poole Director.
Proton driver front end test stand Plans and organisation for 2004–05 David Findlay ISIS Accelerator Division STVLTVS EST QVI ACCELERATORIBVS CVRANDIS.
The ISIS strong focusing synchrotron also at the Rutherford Appleton Laboratory. Note that ISIS occupies the same hall as NIMROD used to and re- uses some.
Operational experience with high beam powers at ISIS David Findlay Accelerator Division ISIS Department Rutherford Appleton Laboratory / STFC ICFA HB2008,
The RAL Front End Test Stand Alan Letchford CCLRC RAL ISIS Injector Group Joint Accelerator Workshop 28–29 March 2006.
Related poster [1] TPAG022: Slow Wave Electrode Structures for the ESS 2.5 MeV Chopper – Michael A. Clarke-Gayther Status Funding bids have been prepared.
Proton Driver: Status and Plans C.R. Prior ASTeC Intense Beams Group, Rutherford Appleton Laboratory.
ISIS upgrades David Findlay Head, Accelerator Division ISIS Department Rutherford Appleton Laboratory / STFC Proton Accelerators for Science and Innovation,
1US-UK Workshop, Jan 12-14, 2012 Working Group 4 - High Power Proton Accelerators: Achievements and Plans for Second PASI Workshop John Thomason & Steve.
Secondary Particle Production and Capture for Muon Accelerator Applications S.J. Brooks, RAL, Oxfordshire, UK Abstract Intense pulsed.
S.J. Brooks RAL, Chilton, OX11 0QX, UK Extending FETS with a Ring Electron models are not sufficient for simulating the beam.
ISIS operational update David Findlay Accelerator Division ISIS Department Rutherford Appleton Laboratory / STFC DL-RAL Joint Accelerator Workshop, RAL.
Alexander Aleksandrov Oak Ridge National Laboratory
Simulations and Diagnostics for the Front End Test Stand Simon Jolly Imperial College 18 th April 2007.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
John Womersley Welcome Director of Particle Physics, CCLRC International Scoping Study Meeting, RAL April 2006.
PROTON LINAC FOR INDIAN SNS Vinod Bharadwaj, SLAC (reporting for the Indian SNS Design Team)
HWDB: Operations at the Spallation Neutron Source Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager.
A Path Toward Standardized Low-Energy Emittance Measurements Doug Moehs January 17, 2007.
Neutrino Factory R&D in Europe Rob Edgecock/RAL. Outline Introduction i.e. what has happened since last year European feasibility study Proton driver.
NEUTRINO DETECTORS Cutting-Edge Accelerator Research for a Neutrino Factory and Other Applications Ajit Kurup for the FETS and UKNF Collaborations Cutting-Edge.
Open Question: Should Fermilab consider joining the effort on R&D for Accelerator based Transmutation of nuclear Waste (ATW) Paul Lebrun - FNAL ● Context.
Copyright © 2015 SCKCEN ADS accelerator developments presently on-going for MYRRHA and possibly for the Chinese-ADS Dirk Vandeplassche 1 Eucard-2 — APAE.
IDS-NF Accelerator Baseline The Neutrino Factory [1, 2] based on the muon storage ring will be a precision tool to study the neutrino oscillations.It may.
Progress in the construction of the MICE cooling channel and first measurements Adam Dobbs, EPS-HEP, 23 rd July 2011.
Layout of the Front-End Test Stand Ajit Kurup UK Neutrino Factory Meeting 12 th January 2005.
The RAL Front End Test Stand David Findlay for Alan Letchford Accelerator Division, ISIS Department Rutherford Appleton Laboratory HIPPI-05, Cosener’s.
EU accelerator contributions to the IDS … R. Garoby ISS meeting RAL 28/04/2006.
FETS-HIPSTER A High-Flux Proton Irradiation Facility Steve Roberts (University of Oxford) Chris Densham (RAL), Alan Letchford (RAL), Juergen Pozimski (Imperial.
Proton Driver Keith Gollwitzer Accelerator Division Fermilab MAP Collaboration Meeting June 20, 2013.
The ISIS Facility John Thomason Synchrotron Group Leader ISIS Department Rutherford Appleton Laboratory / STFC (With thanks to David Findlay) Fermilab,
Operational experience with high power proton beams David Findlay Head, Accelerator Division ISIS Department Rutherford Appleton Laboratory / STFC ADSR.
ISIS OPTIMVS NEVTRONVM SPALLATIONENSIVM FONS MVNDI ISIS Developments David Findlay Accelerator Division ISIS Department Rutherford Appleton Laboratory.
Potential Berkeley Lab interests in ELENA Construction Hardware: Low-level RF controls Schottky diagnostics H- ion source Beam physics: Cooling S2E Simulations.
Beam losses on ISIS and induced radioactivity from MICE David Findlay Head, Accelerator Division ISIS Department Rutherford Appleton Laboratory / STFC.
Fermilab-India Agreements and Collaboration Shekhar Mishra Project-X, International Collaboration Coodinator Fermi National Accelerator Laboratory Batavia,
Proton Driver Developments and the Neutrino Factory Christopher R Prior ASTeC Intense Beams Group STFC Rutherford Appleton Laboratory, U.K.
1May, IPPP- Imperial College, London1 NF activities at IC (part II) m. apollonio.
Capabilities and Programmes of STFC’s Accelerator Science & Technology Centre (ASTeC)
ISIS operational update
UK Neutrino Factory Conceptual Design
The RAL Front End Test Stand
Accelerator R&D for Future Neutrino Projects
Introduction to ASTeC Programmes
Proton Driver Initiatives
Emanuele (ESS), Alessandro (CERN), Mikel (Tekniker), Hayley (ISIS)
Accelerator R&D for Future Neutrino Projects
Superbeams with SPL at CERN
ADS Accelerator Program in China
European Spallation Neutron Source ESNS
ISIS OPTIMVS NEVTRONVM SPALLATIONENSIVM FONS MVNDI
Roger Ruber for the FREIA team 11 June 2013, Uppsala
Presentation transcript:

ISIS OPTIMVS NEVTRONVM SPALLATIONENSIVM FONS ORBIS TERRARVM RAL Front End Test Stand — Context David Findlay Accelerator Division ISIS Department Rutherford Appleton Laboratory

2 2 Front End Test Stand (FETS) aimed at future high power proton and H — accelerators (HPPAs) High power = megawatt-class HPPAs for neutron spallation sources neutrino factories transmutation facilities accelerator driven power reactor systems tritium production

3 3 Justification for working towards HPPAs? Four reasons:European policy UK policy CCLRC/PPARC policy ISIS policy Essentially spallation neutron sources and neutrino factories Synergy

4 4 ESS ~€1B

5 5 MW neutrons for Europe ~€500M UK contribution Neutrino factory ~€1B UK contribution

6 6 Front End Test Stand supported by

7 7 Underpinning ISIS ~£30M/year Front end test stand would become front end of new ISIS linac

8 8 HPPAs — expensive So suitable R&D essential “ESS” bid to FP7 expected May/June 2007 Likely to be long-pulse linac — UK provide front end? Upgrade to ISIS Probably cheapest route to MW neutrons — front end issues Synergy between neutron and neutrino applications Key element of support for front end test stand CERN test stand Specific, not generic test stand. Also less self-sufficient

9 9 Time lines ESFRI: ESS first users ≥2017 RCUK: MW neutrons, £25–50M/year from 2009–10 Neutrino factory, £25–50M/year from 2011–12 Consistent with 2007–10 for second half of FETS

10 Key points about HPPAs High power is difficult Imperative to keep beam losses low (~1 W/m) ISIS only ~0.2 MW, but ×2 beam losses would make life very difficult (2–3 mSv annual dose limit) Need good quality beam Space charge issues significant Implies beam chopper necessary even if no rings involved Need to control transients — RF and target issues Implies beam chopper very desirable

11 Need to demonstrate high quality working beam chopper Requires front end test stand Implies ion source, LEBT, ~3 MeV RFQ, diagnostics, RF,... Excellent progress achieved during 2004–07 On all fronts — as will become evident Looking forward to finishing the job during 2007–10

12

ISIS RFQ test standFront end test stand ISIS RFQ test stand

RAL test stand cf. CERN test stand Operationally proven ion sourceIon source from DESY / RAL Proven 3-solenoid LEBT2-solenoid LEBT Building 3 MeV RFQSaclay IPHI 3 MeV RFQ — should be ready Dec-06 Chopper pulser already provenChopper pulser not yet proven Tuneable deflector not yet builtMeander line deflector built Comprehensive laser-basedDiagnostics? beam diagnostics Successor to proven test standMajor time scale and location changes Substantial local involvementInsufficiently local support Firmly fixed at RALMoving to Saclay, then Linac4 preinjector