B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Path Definition (for studies) 

Slides:



Advertisements
Similar presentations
Building a Combined 25F Nomogram Step 0: Define Terms Safe operating area: System remains within limits following the next worst contingency, regardless.
Advertisements

NI Curtailment Risk Assessment Draft Update to PSASG 2004 Report 24 Sept 2007 Gordon Dobson-Mack Ellen Feng
Project Update Late 2005 the PSANI Policy Group reviewed mitigation efforts to reduce transmission curtailments in the Puget Sound Region Late 2005 the.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Public Service Company of New Mexico
EE 369 POWER SYSTEM ANALYSIS
Northwest Quadrant Joint Security Study Southern Company Headquarters Birmingham, Alabama August 12, 2002 Presented by Saeed Arabi.
1 Local Area Planning Update to TRANSAC – December 16, 2014.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
Buffalo Ridge Incremental Generation Outlet (BRIGO) Transmission Study Presentation to National Wind Coordinating Committee June 22, 2005 W Grivna, PE.
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
ColumbiaGrid Planning Update to PCC Marv Landauer October 7, 2014.
Borah Mitigators Remedial Action Scheme for the Borah West Path Sponsored by: IDAHO POWER Team Members: Kyle Jones Mark Magee Jason Rippee.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
System Operator Conference Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS Facilitator Team.
© 2000 PACIFICORP | PAGE 1 WYOMING WEST AREA STUDY DECEMBER 2013 Seongtae Kim/Jeremy Viula.
California Energy Commission Workshop Nuclear Power Plant Issues
RTP Update RPG Meeting July 21, RTP update  Reliability analysis for the contingencies where load shed is not allowed is complete.
1 Local Area Planning Update to TRANSAC – September 18, 2014.
Visibility 10/1/ Agenda Visibility Overview Status –WECC –ColumbiaGrid Issues Preliminary Thoughts Regarding Conclusions and Recommendations Next.
FRCC Seasonal Transmission Assessment & Operational Seasonal Study Winter 2012.
NW Transmission System Bottlenecks and Impacts of 2005 Summer Operation BPA Transmission Business Line Mike Viles January 2006.
ERCOT PUBLIC 4/21/ Loss of Load Probability Assessment for NERC April, 2015.
Grizzly-Summer Lake 500 kV Line Planned Outage May 27-June hours Mike Viles – BPA Transmission Operations Technical Management Team June.
Increasing Access to the Grid NIPPC September 8, 2005 Brian Silverstein VP, Operations and Planning Bonneville Power Administration.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
American Electric Power Service Corporation Jan 26, Coordinating Controls across CREZ  What dials are available to the operators?  What are the.
Puget Sound Energy Columbia Grid Presentation June 19, 2007 John Phillips.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
Application and Implementation of State Estimator at Idaho Power Company S. Kincic and M. Papic.
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Evaluating Hydro Capacity for Capacity Adequacy Standard: Selection of Hydro Events Eric King/ Mary Johannis PNW Resource Adequacy Technical Committee.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
AEP Corpus Christi TDC Advance Outage Scheduling Initiative.
Providing Resource Planning Guidance to Individual Utilities PNW Resource Adequacy Technical Committee Meeting June 20, 2007.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Puget Sound Energy Columbia Grid Presentation August 15, 2007 John Phillips.
© 2000 PACIFICORP | PAGE 1 –Main Transmission Sources  kV Transformers. Terminal, Mid Valley, 90 th South and Oquirrh –Generation: Gadsby (~350.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
A new Nomogram Development POM- based tool - Application results in the Idaho Power System. Orlando Ciniglio, IPC Marianna Vaiman, V&R Energy WECC TSS.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
Dynamic Transfer Limits Study WIST Update 12/17/09 Brian Tuck, BPA.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
2006 Preliminary Reliability Study Results Bryan Guy September 7, 2006.
Conclusion: reliable post contingency capacitor switching should be feasible to be planned. However, the simulation needs to be repeated as new information.
Oil Load Serving Study Update August 18 th, 2011.
Presentation For PSAST May 14, Outline Most Limiting N-1-X Events Voltage Limitations For Loss of Three Terminal Monroe- Echo Lake 500kV and Chief.
ERCOT – LP&L Study Status Update For Regional Planning Group Ben Richardson March 22, 2016.
Project WECC-0100 Standards Briefing WECC-0100 SDT April 7, 2016 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Puget Sound Area Transmission Expansion Plan Sensitivity Results Review
Visibility Ramu Ramanathan 10/1/2007.
CSC DETERMINATION PROCESS
Columbia Grid Wind Integration Study Team Dynamic Transfer Capability Studies Update 9/10/09.
Proposal to Remove from Service the PV-COI RAS
Eleanor Ewry Base Case Coordination Subgroup Chair
I-5 Corridor Reinforcement Project
PSASG Meeting BPA TBL Operation Concerns By Jerry Jackson II
DEC System Voltage Planning - June 2018
Recent Approved WECC Cases
Building a Combined 25F Nomogram Step 0: Define Terms
Palo Verde-COI RAS Retirement
Proposal to Remove from Service the PV-COI RAS
Palo Verde-COI RAS Retirement
ColumbiaGrid Planning Update to PCC Marv Landauer October 7, 2014
ColumbiaGrid Puget Sound Area Study Team
2018 CG MOD 33 updates CG Planning Meeting June 7, 2018
NI Curtailment Risk Assessment Draft Update to PSASG 2004 Report
Presentation transcript:

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Path Definition (for studies)  Chief Joe – Monroe #1 500kV  Schultz – Echo Lake 500kV  Schultz – Raver #1 500kV  Schultz – Raver #3 500kV  Schultz – Raver #4 500kV  Chief Joe – Snohomish #3 345kV  Chief Joe – Snohomish #4 345kV  Rocky Reach – Maple Valley 345kV  Grand Coulee – Olympia 300kV  Bettas Road – Covington 230kV  Rocky Reach – White River 230kV (PSE)  Kittitas – Woledale 115kV (PSE)  Gold Brite – Beverly 115kV (PSE)

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 2 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Purpose  To explore system additions and upgrades to increase path capacity. Critical Seasons  heavy winter due to increased westside loads (typically voltage stability limited)  late spring / early summer due to hydro runoff and low westside thermal gen (typically thermally limited)

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 3 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Study Assumptions  17hw1 WECC basecase as modified in 2009 BPA screening studies  +/- 5% Load Levels for interpolation  680MW PSA generation level  1500MW SN NI flow  Northwest load areas tuned for peak winter conditions. This optimizes the lower voltage reactive and transformer tap settings. (use what we have before building new)  Only BPA lines are reported in path totals

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 4 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Study Methodology  QV Curves for Critical Contingencies at 500kV Busses  Interpolation used to find WOCN flow where the reactive margin=0  Use of a “probing bus” for busses with shunt devices  Thermal limits were found via the ATC Tool using the Full-AC solution option  All devices were locked at pre-contingency levels except 500kV shunt reactors and capacitors (use RAS to switch in if needed)  SVCs were modeled as continuous shunts with discreet elements included

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 5 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Study Results (Existing System – Thermal) Winter Spring / Summer

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 6 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Study Results (Voltage Stability) Winter

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 7 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Projects  For Spring / Summer Thermal limitations BPA will upgrade the Columbia-Bettas Road 230kV line. (energized 2012)  For Winter Thermal limitations BPA will replace 7 bushings on the 345/230kV transformers at Snohomish and Chief Joe. (energized 2012)  For Winter Voltage Stability limitations BPA is proposing: –316.5MVAR shunt capacitor at Monroe 500kV (targeted 2014) –Series Capacitors on the Schultz-Raver 3&4 500kV lines (24 & 16 ohms respectively) (not launched yet)

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 8 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Next Steps (Study with Regional entities)  Evaluate various transmission line alternatives. (Initial studies show Sickler-Monroe 500kV is promising) –Utilize all smaller fixes first  Redispatch is a possible “non-wires” solution that would essentially negate the current generation displacement trend for the peak load hours when needed. (Initial studies show ~ 2-year delay per 1000MW displacement)