GAO’s Cost and Schedule Assessment Guides U.S. Government Accountability Office Applied Research and Methods Cost Engineering Sciences Jason T Lee, Assistant.

Slides:



Advertisements
Similar presentations
Effective Contract Management Planning
Advertisements

Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
More CMM Part Two : Details.
Chapter 2 The Analyst As Project Manager In Managing Information Systems 2.3.
Copyright 2006 Prentice-Hall, Inc. Essentials of Systems Analysis and Design Third Edition Joseph S. Valacich Joey F. George Jeffrey A. Hoffer Chapter.
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall 3.1.
Copyright 2004 Prentice-Hall, Inc. Essentials of Systems Analysis and Design Second Edition Joseph S. Valacich Joey F. George Jeffrey A. Hoffer Chapter.
Project Management.
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall 3.1.
March 8, 2011 Portfolio Analysis and Management System (PAMS) Briefing for the Fusion Energy Sciences Advisory Committee Linda G. Blevins, Office of the.
GAO and the Federal Procurement System Presentation to the Department of Commerce 4 May 2011 For more information, contact Bill Woods,
1 LBNL Enterprise Computing (EC) January 2003 LBNL Enterprise Computing.
Modern Systems Analysis and Design Third Edition
What is a project? Project Management Institute definition
Systems Engineering Management
Purpose of the Standards
Trini Torres-Carrion. AGENDA Overview of ED 524B Resources Q&A.
Office of the Under Secretary of Defense (Comptroller) Physical Inventory Best Practices 1 Briefing for Joint Physical Inventory Working Group September.
Computer System Analysis
Copyright © 2009 Pearson Education, Inc. Publishing as Prentice Hall Essentials of Systems Analysis and Design Fourth Edition Joseph S. Valacich Joey F.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Essentials of Systems Analysis and Design Fourth Edition Joseph S. Valacich Joey F.
Implementation of DOE Order 450.1: Self-Declaration and Report Letters Steven R. Woodbury US Department of Energy March 9, 2005.
Best Practices By Gabriel Rodriguez
BSBPMG503A Manage Project Time Manage Project Time Unit Guide Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG503A.
Standards for Internal Control in the Government Going Green Standards for Internal Control in the Federal Government 1.
EARTO – working group on quality issues – 2 nd session Anneli Karttunen, Quality Manager VTT Technical Research Centre of Finland This presentation.
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management.
Welcome to Session 4 – Project Management Process Overview (continued) Instructor:Phyllis Sweeney Instructor: Phyllis Sweeney Project Management Certificate.
Certification and Accreditation CS Phase-1: Definition Atif Sultanuddin Raja Chawat Raja Chawat.
Copyright 2006 Prentice-Hall, Inc. Essentials of Systems Analysis and Design Third Edition Joseph S. Valacich Joey F. George Jeffrey A. Hoffer Chapter.
United States Department of Agriculture Food Safety and Inspection Service February William C. Smith Assistant Administrator Office of Program.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
© Mahindra Satyam 2009 Configuration Management QMS Training.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
P1516.4: VV&A Overlay to the FEDEP 20 September 2007 Briefing for the VV&A Summit Simone Youngblood Simone Youngblood M&S CO VV&A Proponency Leader
I n t e g r i t y - S e r v i c e - E x c e l l e n c e Business & Enterprise Systems The Integrated Master Plan (IMP) and the Integrated Master Schedule.
Subcommittee on Design New Strategies for Cost Estimating Research on Cost Estimating and Management NCHRP Project 8-49 Annual Meeting Orlando, Florida.
Earned Value Management Update Nancy L. Spruill Director, Acquisition Resources and Analysis Office of the Under Secretary of Defense (Acquisition, Technology.
Copyright 2002 Prentice-Hall, Inc. Chapter 3 Managing the Information Systems Project 3.1 Modern Systems Analysis and Design.
Project Initiation at The Regence Group 12/19/2015John Garrigues1.
1 American Recovery and Reinvestment Act of 2009: Challenges Facing the Department of Transportation and the Office of Inspector General’s Strategy for.
Information Systems System Analysis 421 Chapter 3 Managing the Information Systems Project.
Copyright © 2009 Pearson Education, Inc. Publishing as Prentice Hall Chapter 3 Managing the Information Systems Project 3.1.
Maintaining and Sustaining System Integrity Configuration Management for Transportation Management Systems Configuration management (CM) describes a series.
Independent Expert Program Review (IEPR) February 2006.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation ERCOT Board Of Directors – August 15, 2006 TPTF Meeting August.
Audit of predetermined objectives PFMA Reputation promise/mission The Auditor-General of South Africa has a constitutional mandate and, as the.
Evaluate Phase Pertemuan Matakuliah: A0774/Information Technology Capital Budgeting Tahun: 2009.
Copyright 2001 Prentice-Hall, Inc. Essentials of Systems Analysis and Design Chapter 2 Managing the Information Systems Project 2.1.
Preparation Plan. Objectives Describe the role and importance of a preparation plan. Describe the key contents of a preparation plan. Identify and discuss.
Team-Based Development ISYS321 Managing the Information Systems Project.
Project Management Processes for a Project Chapter 3 PMBOK® Fourth Edition.
NDIA - ICPM Program Planning and Scheduling Subcommittee Program Planning and Scheduling Subcommittee (PPSS) Initiative Presented by: Ms Carol Boser and.
Week 2 – Risk Planning & Identification. Risk & Risk Management.
OSAE sets the PACE: Premier Auditing Consulting and Evaluations! American Recovery and Reinvestment Act (ARRA) Readiness Review.
Large Facilities Manual New Guidance on Cost Estimating and Analysis 2016 NSF Large Facilities Workshop Kevin Porter Large Facilities Advisor, LFO, NSF.
Managing Schedule Slack/Float PMI Scheduling Forum January 6, 2015 January 6, 2015 Presented by: Ric Albani, PMP, PMI-SP, PMI-RMP, MCTS.
Project Management PTM721S
GAO Cost Estimating & Scheduling
Camera PDR/CD1 Planning 19 September 2008
Systems Analysis and Design in a Changing World, 4th Edition
Establishing and Managing a Schedule Baseline
Chapter 3 Managing the Information Systems Project
Project Management Process Groups
Chapter 3 Managing the Information Systems Project
Principal Investigator ESTCP Selection Meeting
Chapter 3 Managing the Information Systems Project
Principal Investigator ESTCP Selection Meeting
Chapter 3 Managing the Information Systems Project
Presentation transcript:

GAO’s Cost and Schedule Assessment Guides U.S. Government Accountability Office Applied Research and Methods Cost Engineering Sciences Jason T Lee, Assistant Director May 2016 Page 1

Agenda The role of GAO GAO Cost Guide and the characteristics of a reliable cost estimate GAO Schedule Guide and the characteristics of a reliable schedule How is the government performing? Proposed updates to the Cost Guide Reliability assessment example for a large-scale infrastructure project Page 2

Known as the investigative arm of Congress, GAO exists to support Congress in meeting its constitutional responsibilities. To that end, GAO works to Help improve the performance of federal government Ensure government agencies and programs are accountable to the American people Examine the use of public funds, and Evaluate federal programs by providing analyses and recommendations to help Congress make informed oversight and funding decisions Page 3 The Role of GAO in Government

Cost Estimating and Assessment Guide Drafted , published in 2009 Outlines GAO’s criteria for assessing cost estimates during audits Contains 20 chapters with supporting appendixes Chapters 1-17: developing credible cost estimates and the 12-step cost estimating process for developing high quality cost estimates Chapters address managing program costs once a contract has been awarded and discuss Earned Value and risk management Also provides case studies of prior GAO audits to show typical findings related to the cost estimating process Page 4

5 A Reliable Process for Developing Credible Cost Estimates

Characteristics of Reliable Cost Estimates Page 6 Comprehensive Develop the estimating plan Determine the estimating approach Accurate Develop the point estimate Compare the point estimate to an independent estimate Update the estimate with actual costs Credible Create an independent cost estimate Conduct sensitivity analysis Conduct risk and uncertainty analysis Well Documented Define the program Identify ground rules and assumptions Obtain data Document the estimate Present estimate to management Are all costs included? Is the estimate unbiased? What is the uncertainty? Can the estimate be recreated?

Schedule Assessment Guide Drafted , exposure draft published May 2012 Final publication December 2015 Outlines GAO’s criteria for assessing master schedules Contains chapters for each of the 10 best practices plus supporting appendixes Also provides case studies of prior GAO audits to show typical findings related to the scheduling process Page 7

Four Characteristics of a Reliable Schedule Page 8 Comprehensive Capture all activities Assign resources to all activities Establish durations for all activities Well Constructed Sequence all activities Confirm the critical path Confirm reasonable float (slack) Credible Confirm vertical and horizontal traceability Conduct a schedule risk analysis Controlled Update the schedule with progress Maintain a schedule baseline Is all effort included? Is the network logical? What is the uncertainty? Is progress measured?

How Is the Government Performing? The extent to which agencies are adhering to cost and schedule best practices Page 9

How is the government performing in developing cost estimates? Page 10 Data based on agencies and departments with three or more GAO cost estimate assessments Fully MetSubstantiallyPartiallyMinimallyNot Met ComprehensiveWell DocumentedAccurateCredible Veterans Affairs (VA) DOT DOD Missile Defense (MDA) IRS DHS DOE Agriculture Commerce

How is the government performing in developing and maintaining schedules? Page 11 Results reflect agencies and departments with three or more GAO schedule assessments BP 1 All effort BP 2 Logic BP 3 Resources BP 4 Durations BP 5 Traceable BP 6 Critical Path BP 7 Float BP 8 Risk BP 9 Statusing Veterans Affairs (VA) DOT DOD Missile Defense (MDA) DHS DOE NASA Fully MetSubstantiallyPartiallyMinimallyNot Met

Some Proposed Cost Guide Updates Integration with and references to the  GAO Schedule Assessment Guide (GAO-16-89G)  GAO Standards for Internal Control (GAO G)  GAO Technology Readiness Assessment Guide (expected summer 2016)  GAO Federal Agile Software Guide (issue date TBD) Improved definitions and descriptions of several best practices and their mappings to the 12 steps and 4 characteristics Applicability of best practices to all types of capital programs Appendixes: risk breakdown structures, spreading contingency dollars through the WBS; updated laws and guidance Page 12

13 GAO invites interested parties to meet with us and other experts to discuss further updates to the cost and schedule guides so that the guides continually reflect best practices. If interested, please your contact information to: Jason T Lee – Karen Richey - Invitation to Participate in Further Updates and Discussion about Best Practices

International Thermonuclear Experimental Reactor (ITER) Project: Background ITER is an international research facility being built in France to demonstrate the feasibility of fusion energy. Other countries involved in ITER include Russian Federation, Japan, European Union, People’s Republic of China, Republic of Korea, and India. The United States has committed to providing about 9 percent of ITER's construction costs through contributions of hardware, personnel, and cash, and DOE is responsible for managing those contributions, as well as the overall U.S. fusion program. GAO reviewed costs and schedules in 2014 (GAO ) Page 14

ITER: Cost estimates of U.S. Contribution Page 15

ITER: Key Findings Cost: Estimate of U.S. contribution has grown by almost $3 billion Schedule: Estimated completion date has slipped by 20 years Causes: 1) refined design and requirements of U.S. hardware; 2) changes to the international schedule; 3) changes to ITER design; 4) U.S. funding constraints and associated inflation; 5) increased ITER construction costs Assessment: U.S. schedule estimates substantially meet best practices U.S. cost estimates substantially meet best practices, but only partially meet Credible because they did not develop a sensitivity analysis or independent cost estimate DOE has been unable to set a cost and schedule baseline in part because the international schedule has not been set Page 16

ITER: Recommendations Revise U.S. ITER Project Office to develop a sensitivity analysis for the cost estimate and compare to an independent cost estimate Develop proposal describing what actions are necessary to create a reliable international schedule and improve ITER Organization program management Once ITER Organization creates a reliable master schedule, use that schedule to update the U.S. schedule Develop strategic plan to address DOE’s fusion program priorities Page 17

Conclusion The GAO Cost Guide and Schedule Guides provide criteria to evaluate many types projects The GAO Cost Guide and Schedule Guides can serve as the basis for agency project control guidance GAO recommendations have been aimed at improving oversight to keep projects on cost and schedule. Page 18

Thank you- Any Questions? Guides Available Online: GAO Cost Estimating and Assessment Guide: GAO Schedule Assessment Guide: Page 19